July 29,1985 MJssissippi Power and Light Company H TTN: Mr. J. B. Richard Senior Vice President, Nuclear P. O. Box 23054 Jackson, MS 39205 Gentlemen:
SUBJECT:
GRAND GULF OPERATIONAL QUALITY ASSURANCE PROGRAM Your letters to this office dated June 29, 1984, (AECM-84/0332) and October 12, 1984, (AECM-84/0489) provided changes to Revision 3 of the operational quality assurance program (MPL-TOP-1A) for the Grand Gulf station (Docket No. 50-416).
Additional clarification was provided during a telephone conversation conducted between Mr. G. Belisle of my staff and Mr. W. Edge and Ms. L. Burgess of your staff on October 3, 1984.
This clarification was provided in response to questions transmitted by my letter dated August 23, 1984. As agreed during that conversation, NRC concerns would be incorporated into MPL-TOP-1A at a later date.
In order to achieve full implementation of requested MPL-TOP-1A changes, a Technical Specification amendment was requested from the Office of Nuclear Reactor Regulation on January 30,1985, ( AECM-85/0033). This amendment was approved by the Office of Nuclear Reactor Regulation on April 1, 1985.
MPL-TOP-1A status was discussed between Mr.
G.
Belisle of my staff and Ms. L. Burgess of your staff on May 9,1985.
Your letter to this office dated May 14,1985, ( AECM-85/0100) transmitted Revision 4 of MPL-TOP-1A. Additional clarification was provided during a telephone conversation conducted between Mr. G. Belisle of my staff and Mr. S. Feith, Mr. W. Edge, and Ms. L. Burgess of your staff on July 8,1985.
Our review of this information indicates that the Grand Gulf operational quality assurance program continues to satisfy 10 CFR 50
~
Appendix B requirements and is therefore acceptable.
Please contact us if you have any questions concerning this letter.
We appreciate your timely submittal and responses to our questions regarding the information' required by 10 CFR 50.54 (a).
Sincerely, (Original signed by VLBrownlee/for)
Roger D. Walker, Director i
Division of Reactor Projects cc:
D. Kingsley, Vice President Nuclear Operations
/ E. Cross, General Manager F. Dale, Director, Nuclear
@ Licensing and Safety i
(cc:
continued on page 2) i i O 8508130597 850729 PDR ADOCK 05000416 P
PDR p
z
~
e Mississippi Power and Light Company 2
July 29,1985 ud( T. Lally, Manager of Quality Assurance Middle South Services, Inc.
' d M. Feith, Director Quality Assurance ud(I B. McGehee, Esquire Wise, Carter, Child, Steen and' Caraway LSI. S. Reynolds, Esquire Bishop, Liberman, Cook, Purcell
_ J Reynolds W. W. Jackson, Project Engineer bcc: d C Resident Inspector W. L. Belke, IE G. A. Belisle, RII Document Control Desk State of Mississippi
/
}
- SEE PREVIOUS CONCURRENCE PAGE i
4 l
RII RII RII RII RII
- GBelisle
- CUpright
- AGibson
- Panciera
- VBrownlee 07/ /85 07/ /85 07/ /85 07/ /85 07/ /85
4 Mississippi Power and Light Company 2
bec: NRC Resident Inspector W. L. Belke, IE G. A. Belisle, RII Document Control Desk State of Mississippi
- RII R1I RII RI RII GBe sie ubi AGib on Pa ciera VBro ee 07/p/85 07@/85 07p/85 0/[/85 07/2 /85 4
7
.