Informs That Procedures Re Subcooling Margin Will Be Revised & Approved Prior to Restart,Per .Due to 850609 Event,Resources Heavily Allocated for Completion of Related Investigations & Corrective Actions
ML20133G650
Person / Time
Site: Davis Besse Cleveland Electric icon.png
Issue date: 10/10/1985
From: Williams J
TOLEDO EDISON CO.
To: Stolz J
Office of Nuclear Reactor Regulation
References
1190, TAC-61937, NUDOCS 8510160065
Download: ML20133G650 (1)


Text

_ . . - _ ._ - - . _ _ _ _ _ _ - _ _

TOLEDO

%mm EDISON Docket No. 50-346 JOE WituAMS. JR Gerwr Vtv prownprt. %: lear License No. NPF-3 $ $$NE Serial No. 1190 a

October 10, 1985 l

i Director of Nuclear Reactor Regulation Attention: Mr. John F. Stolz Operating Reactor Branch No. 4 Division of Licensing United States Nuclear Regulatory Commission Washington, D.C. 20555

Dear Mr. Stolz:

Toledo Edison has been reviewing the adequacy of the specified subcooling margin for the Davis-Besse Nuclear Power Station Unit No. I as stated in our letter dated July 15, 1985 (Serial No. 1169). We have determined that a revision to our specified subcooling margin is appropriate.

Due to the June 9, 1985 event, our resources are heavily allocated to the completion of related investigations and the implementation of '

corrective actions. However, we plan to revise and approve the appropriate procedures concerning subcooling margin and provide your j office with any necessary submittals, prior to Restart.

Very truly yours,

/a ^

f$$

JW: GAB:lah 4

cc: DB-1 NRC Resident Inspector 8510160065 851010 i PDR ADOCK 05000346 P PDR THE TOLEDO EDISON COMPANY EDISON PLAZA 300 MADISON AVENUE TOLEDO, OHIO 43052 Y I O