hC[q JU L 0 51985 Georgia Power Company

/ ATTN: Mr. R. J. Kelly Executive Vice President P. O. Box 4545 Atlanta, GA 30302 Gentlemen:

SUBJECT:

MEETING

SUMMARY

- V0GTLE FACILITY - DOCKET NOS. 50-424 AND 50-425 This refers to the management meeting conducted at your request in the NRC Region II Office on June 25, 1985. This meeting was held to brief the NRC on the Vogtle Readiness Review Module entitled " Mechanical Equipment, Piping, and Other Components" as well as the Appendix I entitled " Project Quality Assurance Organization."

It is our opinion that this meeting was beneficial and provided a good forum for general Vogtle Readiness Review Program discussions as well as an informative briefing on the details of this Module and Appendix. This in-depth presentation will better enable the NRC to conduct its evaluations.

In accordance with Section 2.790 of NRC's " Rules of Practice," Part 2, Title 10, Code of Federal Regulations, a copy of this letter and its enclosures will be placed in the NRC Public Document Room.

Should you have any questions concerning these matters, we will be pleased to discuss them.

Sincerely, IS 'O. Ralsm boce J. Nelson Grace Regional Administrator

Enclosures:

1.

Attendance List 2.

GPC to NRC Submittal Schedule gc w/encls:

vR. E. Conway, Senior Vice President

, Nuclear Power V D. O. Foster, Vice President and General Manager Vogtle Project v H. H. Gregory, III, General Manager, Vogtle Nuclear Construction A. Bockhold, Jr., Vogtle Plant Manager vl< T. Gucwa, Chief Nuclear Engineer

\\

cc w/encls: (Cont'donpage2)

I

[ b k (l 8500090003 e50705 PDR ADOCK 05000424 A

PDR

JUL 0 e iW5 Georgia Power Company 2

cc w/encls:

(Cont'd)

Ruble A. Thomas, Vice President-Licensing Vogtle Project tEd Groover, Quality Assurance Site Manager VC. W. Hayes, OA Manager i T. Beckham, Vice President

& General Manager - Operations tJ' A. Bailey, Project Licensing Manager deorge F. Trowbridge, Esq.

Shaw, Pittman, Potts and Trowbridge druce W. Churchill, Esq.

Jhaw,Pittman,PottsanaTrowbridge W rnest L. Blake, Jr., Esq.

,Shaw, Pittman, Potts and Trowbridge vdames E. Joiner, Troutman, Sanders, Lockerman and Ashmore tJames G. Ledbetter, Commissioner Department of Human Resources vCharles H. Badger, Office of Planning and Budget, Management Review Division sSeppish Kirkland, III, Counsel Office of the Consumer's Utility

. Council v60uglasC.Teper,GeorgiansAgainst Nuclear Energy t t'surie Fowler, Legal Environmental Assistance Foundation dimJohnson,ExecutiveDirector Educational Campaign for a Prosperous Georgia uPforton B. Margulies, Esq., Chairman Administrative Judge, Atomic Safety and Licensing Board Panel L Ur. Oscar H. Paris, Administrative Judge Atomic Safety and Licensing Board Panel dustaveA.Linenberger,Jr., Administrative Judge, Atomic Safety and Licensing Board Panel bec w/encls:

(See page 3)

JUL00isg Georgia Power Company 3

_ bcS w/encls:

W. Reis, ELD LW' M. Hill, IE t#. Miller, NRR t4'.Brach, ED0 P. Bemis, RII M. Sinkule, RII W. Rankin, RII LNftC Resident Inspector Document Control Desk State of Georgia i

4 RII RII RII RII I

W in:ps MSinkule VBr n e ker J0 hinski W$

7/9[

/8 6

/

/85 6/ /85 6/

/

9(</ss 1l>lgs

i JUL O 51985 ENCLOSURE 1 LIST OF PRINCIPAL PARTICIPANTS V0GTLE READINESS REVIEW MEETING - JUNE 25, 1985 Georgia Power Company D. O. Foster, Vice President and Project General Manager /Vogtle Project P. D. Rice, Vice President, Quality Assurance C. W. Hayes, Vogtle Quality Assurance Manager W. C. Ramsey, Readiness Review Program Manager A. Nakashima, General Appendices Manager W. Wright, Design Discipline Manager t

D. Bush, Readiness Review Program Quality Assurance R. Sommerfeld, Construction Team Leader Stone and Webster Engineering Corporation R. McMellon, Technical Consultant C. Lundin, Technical Consultant Bechtel Power Corporation P. Karpa, Manager of Engineering, Western Power Division F. Marsh, Project Engineering Manager NRC-NRR, T. Novak, Assistant Director for Licensing, Division of Licensing (DL)

M. A. Miller, Licensing Project Manager, DL R. Pichumani, Mechanical Engineer, Division of Engineering NRC-IE W. M. Hill, Senior Reactor Systems Engineer NRC-Region II J. N. Grace, Regional Administrator R. D. Walker, Director, Division of Reactor Projects (DRP)

V. L. Brownlee, Chief, Reactor Projects Branch 2, DRP M. V. Sinkule, Chief, Reactor Projects Section 2D, DRP W. H. Rankin, Acting Project Engineer, DRP C. M. Upright, Chief, Quality Assurance Program Section, Division of ReactorSafety(DRS)

W. F. Sanders, Senior Resident Inspector, Construction, Vogtle E. H. Girard, Reactor Inspector, DRS B. R. Crowley, Reactor Inspector, DRS S. J. Vias, Reactor Inspector, DRS L. H. Jackson, Reactor Inspector, DRS G. A. Belisle, Reactor Inspector, DRS R. W. Wright, Reactor Inspector, DRS l

d

t JUL O S 1985 June 25,1985 ENCLOSURE 2 SCHEDULE MODULE TO NRC SCHEDULED FORECAST /

NO.

MODULE TITLE NRC ISSUE ACTUA L 1.

Conc ret e, Rebar and Cadwelds 03/14/85A 2.

Operations Training and Qualification 07/26/85 07/26/85F 3.A.

Ini tial Test Program, Preoperational Test Pnase 4/26/85 05/01/85A 3.B.

Initial Test Program, St ar tup Te st Phase 02/07/86 02/07/8 6F 4.

Mechanical Equipnent, Piping and Components 05/10/85 06/14/85A 5.

Operations Organization and Administration 06/12/85 07/12/8 5F 6.

Electrical Equipment 05/24/85 OPEN 7.

A.

Plant Operations 09/20/85 09/ 20/8 5F B.

Plant Security 8.

St ruc tural Steel 06/28/85 07/ 26/8 5F 9.

A.

Radiological Protection 10/04/85 10/04/85F B.

Chemist ry 10.

Operations Technical Support 11/15/85 11/15/85F 11.

Pipe Supports 07/01/85 11/01/85F 12.

Electrical Cables and Terminations 12/06/85 12/06/85F 13.

A.

Foundations and Backfill 09/06/85 09/06/85F B.

Coat ings C.

Po st Tensioning 14.

Plant Maint enance 12/20/85 12/20/85F 15.

Emergnecy Preparedness 10/18/85 10/18/85F 16.

NS SS 08/09/85 08/09/8 5F 17.

Raceways 08/23/85 08/23/85F 18.

A.

HVAC 01/03/86 01/03/86F B.

Fire Protection C.

Diesel Generators D.

Rad Waste 19.

Electrical Supports 02/21/86 02/21/8 6F 20 I& C 03/07/86 03/07/86F 21.

General Appencices A.

Orga niz at ion 05/17/85 07/12/8 5F B.

Design Control 05/17/85 0 7/12/85F C.

Procu reme nt 7/12/85 08/0 9/8 5F D.

Document / Control 7/12/85 07/19/85F E.

Material Cont rol 7/12/85 08/0 2/85F F.

Inspector Qualification / Certification 06/21/85 07/19/85F G.

Me a sur ing a nd Te st Equipment 06/21/85 07/19/85F H.

Non-Con f orma nces 06/21/85 07/19/85F I.

Project Quality Assurance Organization 06/21/85 05/ 24/8 5A J.

Equipnent Qualification TBD TBD K.

Const ruction Corpletion 07/12/85 OPEN 017 7C/l i