Forwards Fifteenth Edition of IIs for Songs,Units 2 & 3
ML20133F733
Person / Time
Site: San Onofre  Southern California Edison icon.png
Issue date: 01/10/1997
From: Rainsberry J
SOUTHERN CALIFORNIA EDISON CO.
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
References
NUDOCS 9701140339
Download: ML20133F733 (7)


Text

.

g g a seco, a u m us,.

Le_J EDISON An I DisON IVil f(N 47IO N it. Company January 10, 1997 U. S. Nuclear Regulatory Connission Attention: Document Control Desk Washington, D. C.

20555 Gentlemen:

Subject:

Docket Nos. 50-361 and 50-362 Fifteenth Edition of the Integrated Implementation Schedule (IIS)

San Onofre Nuclear Generating Station Units 2 and 3

Reference:

Letter from W. C. Marsh (SCE) to Document Control Desk (NRC),

dated July 17, 1996; Fourteenth Edition of the Integrated Implementation Schedule (IIS).

Enclosures 1 and 2 provide the Fifteenth Edition of the Integrated Implementation Schedule (IIS) for t'ne San Onofre Nuclear Generating Station (SONGS), Units 2 and 3. updates the Schedule A, B, and C projects listed in the Fourteenth Edition of the IIS (referenced) for SONGS 2 and 3. provides the current Schedule A, B, and C projects for SONGS 2 and 3 for Cycles 9 and 10.

There are no ongoing evaluations of major issues for SONGS 2 and 3.

The Westinghouse Analytical Ranking Program (WARP) was not used to rank the relative safety significance of each Schedule A and B modification because their implementation schedules have been established in separate correspondence.

If you have any questions on the Fifteenth Edition of the San Onofre Units 2 and 3 IIS, please let me know.

Verf truly yours, f

f)f I

6

(

J.

ainsberry 970114o339 97011o ADOCR 0500 1

Manager, Plant Lic si g fDR Enclosures 1 q 0100 cc:

L. J. Callan, Regional Administrator, NRC Region IV K. E. Perkins, Jr., Director, Walnut Creek Field Office, NRC Region IV J. A. Sloan, NRC Senior Resident Inspector, San Onofre Units 2 & 3 M. B. Fields, NRC Project Manager, San Onofre Units 2 and 3 P.O.Ikm 128 San Clemente, CA 92674 0128

ENCLOSURE 1 SCHEDULE A, B, AND C UPDATES (14th Edition IIS dated 07/17/96)

).

i - 14th Edition IIS Schedule Updates i

Schedule A l

i i

i Updsee Unit Duc Date DCP Number Desonpuun Co= =

t There are no Schedule A items identined at this time

),

i 6

Schedule B 1

Update Unit Duc Dune DCP Numher Desenphon Comsneses i

Add 2

Cycle 10 N/A Shutdown Cooling Inverter SCE to NRC Letter 8/26/96 l

Replacment i

Add 2

Cycle 10 N/A Chlorine Analyzer for Outfall Regional Water Qualny Control l

Board 1

Add 3

Cycle 10 N/A Shutdown Cooling Inverter SCE to NRC letter 8/26/96 Replaement Add 3

Cycle 10 N/A Chlorine Analyzer for Outfall Regional Water Quality Control Board i

. Schedule C Update Unit Duc Date DCP Nander Descripion No change 2

Cycle 9 2064.00 Modify 11. P. Turbine No change 2

Cycle 9 6683.04 Snubber Reduction No change 2

Cycle 9 6683.05 Snubber Reduction - Phase VI No change 2

Cycle 9 6876.00 Containment Purge and Plant Vent Stack Radiation Monitor From 2

Cycle 9 6926.00 Replace Nuclear Monitoring Corporation Radiation Monitors Cycle 9 to Cycle 10 Complete 2

Cycle 9 N/A Containment Application for Reduced Exposure (ALARA Reduction)

Add 2

Cycle 9 N\\A Independent System Operator - Revenue Metering

)

Add 2

Cycle 10 N/A LP Turbine Rotor Replacement Add 2

Cycle 10 N/A Main Steam Line Radiation Monitor Upgrade No change 3

Cycle 9 2064.00 Modify 11. P. Turbine No change 3

Cycle 9 6876.00 Contamment Purge and Plant Vent Stack Radiation Monitor No change 3

Cycle 9 6683.04 Snubber Reduction No change 3

Cycle 9 6683.05 Snubber Reduction - Phase VI From 3

Cycle 9 6926.00 Replace Nuclear Monitoring Corporation Radiation Monitors Cycle 9 to Cycle 10 No change 3

Cycle 9 N/A Containment Application for Reduced Exposure (ALARA Reduction)

Add 3

Cycle 9 N/A independent System Operator - Revenue Metermg Add 3

Cyle 10 N/A LP Turbine Rotor Replacement Add 3

Cycle 10 N 'A Main Steam Line Radiation Monitor Upgrade

i i

ENCLOSURid 2 FIFTEENTH EDITION IIS (SONGS 2 AND 3)

SONGS 2 & 3 Integrated Implementation Schedule Fifteenth Edition i

i Schedule A Uns Duc Deee DCP Number Descnption Comaments There are no Schedule A items identified at this time i

Schedule B i

Unis Duc Dane DCP Number Desenptson Comments s

2 Cycle 10 N/A Shutdown Cooling Inverter SCE to NRC letter 8/26/96 Replacment 2

Cycle 10 N/A Chlorine Analper for Outfall Regional Water Quahty Control Board 3

Cycle 10 N/A Shutdown Cooling Inverter SCE to NRC letter 8/26/96 l

Replacment j

3 Cycle 10 N/A Chlorine Analyzer for Outfall Regional Water Quality Control Board l

2 I

1 i

l 1

l l l I

Schedule C Unit Due Date DCP Number Description l

2 Cycle 9 2064.00 Modify 11. P. Turbine 2

Cycle 9 6683.04 Snubber Reduction 2

Cycle 9 6683.05 Snubber Reduction - Phase VI 2

Cycle 9 6876.00 Containment Purge and Plant Vent Stack Radiation Monitor 2

Cycle 10 6926.00 Replace Nuclear Monitoring Corporation Radiation Monitors 2

Cycle 9 N tA Independent System Operator - Revenue Metermg 2

Cycle 10 N/A LP Turbine Rotor Replacement 2

Cycle 10 N/A Main Steam Line Radiation Monitor Upgrade 3

Cycle 9 2064.00 Modify 11. P. Turbine 3

Cycle 9 6876.00 Containment Purge and Plant Vent Stack Radiation Monitor 3

Cycle 9 6683.04 Snubber Reduction 3

Cycle 9 6683.05 Snubber Reduction - Phase VI 3

Cycle 10 6926.00 Replace Nuclear Monitormg Corporation Radiation Monitors 3

Cycle 9 N/A Containment Application for Reduced Exposure (ALARA Reduction) 3 Cycle 9 N/A Independent System Operator - Revenue Metering 3

Cycle 10 N'A LP Turbine Rotor Replacement 3

Cycle 10 N/A Main Steam Line Radiation Monitor Upgrade