Forwards Rev 3 to QA Program Description.Rev Eliminates Assistant General Manager - Power & Radiation Protection Engineering Specialist & Adds Training Specialist
ML20133C662
Person / Time
Site: La Crosse File:Dairyland Power Cooperative icon.png
Issue date: 09/13/1985
From: Taylor J
DAIRYLAND POWER COOPERATIVE
To: James Keppler
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
Shared Package
ML20133C664 List:
References
LAC-11134, NUDOCS 8510070478
Download: ML20133C662 (3)


Text

f

, = ,

s D DA/RYLAND h [k COOPERAT/VE

  • PO BOX 817 2615 EAST AV SOUTH . LA CROSSE. WISCONSIN S4601 (608) 788 4000 September 13, 1985 In reply, pleasa refer to LAC-11134 DOCKET NO. 50-409 Mr. James C. Keppler, Regional Administrator PRIORITY ROUTING Directorate of Regulatory Operations first irr0L U. S. Nuclear Regulatory Commission a M Region III 799 Roosevelt Road P3 h ~ h ML

~

Glen Ellyn, IL 60137 flAJ Ebp ESS CL -

V om Q -

SUBJECT:

DAIRYLAND POWER COOPERATIVE FILE M -

LA CROSSE BOILING WATER REACTOR (LACBWR)

PROVISIONAL OPERATING LICENSE NO. DPR-45 QUALITY ASSURANCE PROGRAM

REFERENCE:

(1) 10CFR50, Section 50.54.(a)(3)

(2) 10CFR50.71 Gentlemen:

In accordance with References (1) and (2), we are sending Revision 3 of the La Crosse Boiling Water Reactor (LACBWR) Quality Assurance Program Description (QAPD) for your information.

This is an annual update, the changes are for reorganizational purposes and do not reduce our commitment of our previously accepted QADP.

This submittal is being transmitted in excess of the annual requirement of Reference (1) because of known organizational changes which took place in July and September 1985.

The changes involve the elimination of two positions (Assistant General Manager-Power and Radiation Protection Engineering Specialist) and the addition of one position (Training Specialist). The previous Assistant General Manager-Power has been selected to assume the responsibility as General Manager. In this position, the DPC General Manager will retain his responsibility for the Quality Assurance Program at LACBWR.

All references to Assistant General Manager-Power have been removed and the organizational charts have been revised- to reflect our current organizational structure.

8510070478 850913 PDR ADOCK 05000409 P PM SEP 3 01985 WP63 zm/ n i

E ]

d l

Mr. James G. Keppler, Regional Administrator Directorate of Regulatory Operations LAC-11134 U. S. Nuclear Regulatory Commission September 13, 1985 Only the revised sections of our QAPD are being transmitted. If there are any questions concerning this submittal, please contact us.

Very truly yours, DAIRYLAND POWER COOPERATIVE

/

gew)7)$ /

James W. Taylor, General Manager JWr:RW:aes CC: Resident Inspector NRC Document Control Desk John Stang, LACBWR Project Manager STATE OF WISCONSIN )

)

COUNTY OF LA CROSSE)

Personally came before me this JO day of September,1985, the above named James W. Taylor, to me known to be the person who executed the foregoing instrument and acknowledged the same.

s% > / h as Notary PublicVLa Crosse County, My Commission Expires February 21, 1988.

WP63 t - . . -

DAIRYLAND POWER COOPERATIVE LACBWR PLANT STATEMENT OF QUALITY ASSURANCE POLICY The Quality Assurance Program described herein has been developed by the Dairyland Power Cooperative to assure safe and reliable operation of LACBWR.

This program is designed to meet the requirements of Title 10 of the Code of Federal Regulations, Part 50, Appendix B, " Quality Assurance Criteria for Nuclear Power Plants and Fuel Reprocessing Plants."

The Quality Assurance Program applies to all activities affecting the safety related functions of the structures, systems, and components that prevent or

. mitigate the consequences of postulated accidents that could cause undue risk to the health and safety of the public. These activities include design, operations, maintenance, repair, refueling, testing, and modifications.

The LACBWR Plant Superintendent is responsible for the establishment of a Quality Assurance Program which meets the requirements of 10CFR50, Appendix B.

The LACBWR Quality Supervisor is responsible for implementing the program.

k/I$N/ W 4(i_ (General Managdr)