ML20133C451

From kanterella
Jump to navigation Jump to search
Ack Receipt of Informing NRC of Steps Taken to Correct Violations Noted in Insp Repts 50-348/85-25 & 50-364/85-25.Requests That Responses to Violations 1b,2a, 3 & 4 Be Resubmitted within 30 Days
ML20133C451
Person / Time
Site: Farley  Southern Nuclear icon.png
Issue date: 10/01/1985
From: Grace J
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
To: Mcdonald R
ALABAMA POWER CO.
References
NUDOCS 8510070365
Download: ML20133C451 (6)


See also: IR 05000348/1985025

Text

ygllgw

9 *.

-

October 1,1985

labama Power Company

TTN: Mr. R. P. Mcdonald

Senior Vice President-Nuclear Generation

P. O. Box 2641

Birmingham, AL 35291

Gentlemen:

SUBJECT:

REPORT NOS. 50-348/85-25 AND 50-364/85-25

Thank you for your response of August 16, 1985, to our Notice of Violation issued

on July 18, 1985, concerning activities conducted at your Farley facility. With

regard to Violation 1, parts b and c. Violation 2, part a, and Violation 4, we

have concluded, for the reasons presented in the enclosure to this letter, that

the violations occurred as stated in the Notice of Violation.

Therefore,.in

accordance with the requirements of 10 CFR 2.201, and within 30 days of the date

of this letter, please resubmit your response to the Notice of Violation.

With regard to Violation 1, part a, we are reviewing this matter further and will

respond to this item at a later date.

With regard to Violation 2, part b, we agree with your position and have deleted

this part of the violation from our records.

With regard to Violation 3, we have concluded for the reasons presented in the

enclosure to this letter that your proposed corrective action to avoid further

violations is unacceptable.

Therefore, in'accordance with the requirements of

10 CFR 2.201, and within 30 days of the date of this notice, please resubmit

your response to the Notice of Violation.

With regard to your denial that Violations 1, 2, and 4 are properly designated as

Severity Level IV, we have concluded, for the reasons presented in the enclosure

to this letter, that the proper severity levels were designated.

We appreciate your cooperation in this matter.

Sincerely,

(Original signed by JNGrace)

..

J. Nelson Grace

Regional Administrator

Enclosure:

(See Page 2)

$$b4g

PDR

y

(

.r.E o I

L

.

._

. . -

-

. - .

.

.

. . .

.

___.

, _-_-_

- . _ . .

..

_

_

.

.

Alabama Power Company

2

October 1,1985

Enclosure:

Staff Evaluation of Licensee Response

Dated August 16, 1985

. O. Whitt, Executive Vice President

f.D.Woodard,PlantManager

W. G. Hairston, III, Manager

Nuclear Engineering and Technical

/. Support

J

W. McGowan, Manager-Safety Audit

/ and Engineering Review

JH. O. Thrash, Manager, Nuclear

/ Operations and Administration

W. G. Ware, Supervisor-Safety Audit

and Engineering Review

cc w/ enc 1:

RC Resident Inspector

E. Reeves, Project Manager, NRR

Document Control Desk

State of Alabama

f

~ . -

.

.

RII

RII

RII

RII'-

RII

MRunylf

56f

GF

an:dr

ABelisle

C

an

AGi) on

MCantrell

9/ n/85

9/9/85

9//[/85

094y85

T 09/gg/85

RII

RI

RII

N

ih-

s

GJ6M s

r

Jpshinski

09)e/85

09/9 85

09/ /85

l

!

a

,

_

__

.

..

.

ENCLOSURE

STAFF EVALUATION'0F LICENSEE RESPONSE.

DATED AUGUST 16, 1985

Our assessment of your reasons for denial of the violation is as follows:

1.b. You make the following statement in your denial:

Alabama Power Company does not agree that failure to document

evaluations of mechanical test equipment is a violation of the cited

requirements, since ANSI N45.2.4-1972 is not applicable to mechanical

test equipment.

FNP-0-AP-15 does require that an evaluation be

performed when mechanical test equipment is found out of tolerance;

however, there is no requirement to document this evaluation. We agree

that FNP-0-AP-15 can and will be improved by adding and implementing a

requirement to document evaluations.

We agree with your statement that ANSI N45.2.4-1972 does not specifically

apply to mechanical test equipment.

However, you are also committed to

Regulatory Guide 1.28 which endorses ANSI N45.2-1971.

This standard

(Section 13) clearly applies to mechanical equipment and states the same

,

requirement to evaluate previous test results when measuring and test

'

equipment (M&TE) is found out of calibration.

You should also note that

the citation was for failure to evaluate, not failure to document.

Your

response addresses only documentation.

Additionally, when directly

questioned by the inspector, Farley plant personnel stated that evaluations

'

were rarely perfomed and never documented.

1.c You make the following statement in your denial:

No ANSI standard requires that a time interval be established for

performing these evaluations.

Alabama Power Company does not consider

that lack of formal definition of "promptly" regarding test equipment

evaluation is a violation of regulatory requirements.

A plant review

of all test instruments over the first 5 months of 1985 revealed that

the average time for review was 29 days. We concur that an enhancement

of the program would be a definition of "promptly" which we will

incorporate into our procedures.

We agree that ANSI standards do not prescribe the establishment of a time

limit for evaluations.

However, it is our position that the safety impli -

cations of this issue merit the application of 10 CFR 50, Appendix B,

Criterion XVI, and the accepted QA program requiring measures be established

to assure that conditions adverse to quality are promptly identified and

corrected.

Measures do not exist to assure promptness.

We do not concur

with your implication that completion times have been acceptable.

-

- - -

--

-

-

-

- - -

- . - . - - - - -

. - - . - -

. . - - .

- _

_

_

.--

-__.

_

'

.--

.

Enclosure

2

October 1,1985

You make the following statement in your denial:

Additionally, Alabama Power Company would deny that the alleged

violation is properly designated as Severity Level IV.

'

Failure to perform evaluations, to document those evaluations, and to

establish measures to assure conditions adverse to quality are promptly

corrected constitutes a failure to meet regulatory requirements that has

more than minor safety significance.

In conclusion, it is our position that Violations 1.b and 1.c occurred and

,

that the proper severity level was assigned.

i

2.a You make the following statement in your denial:

The violation states that measures have not been established to assure

that suitable environmental conditions are provided for measuring and

test equipment calibration.

Adequate measures do exist for providing

and controlling environmental conditions in the I&C laboratory;

however, these conditions are not verified and recorded prior to

i

calibration of each individual instrument.

Moreover, the inspection

report does not identify an occurrence where the existing level of

adninistrative controls resulted in improper calibrations.

After a

.'

detailed review, the inspector indicated on page 11 of the inspection

report that the I&C laboratory humidity had remained within the most

limiting test instrument calibration environmental condition for almost

every day during the past year.

We agree that hardware measures (air conditioning, heater, dehumidifiers,

etc.), exist, but the violation was specifically against the failure to

+

provide programmatic measures to assure proper environmental controls.

It

is evident that a systennatic assessment of the environmental sensitivities

of shop standards and test equipment has never been accomplished.

We did

state that test conditions were almost always met for Fluke digital multi-

meters, but this was not intended to imply that the same conclusion applies

to all other pieces of test equipment you currently own or may purchase in

the future.

.

i

You make the following statement in your denial:

Additionally, Alabama Power Company would deny that the alleged

violation is properly designated as Severity Level IV.

Failure to establish suitably controlled conditions for performing

activities affecting quality constitutes a failure to meet regulatory

requirements that has more than minor safety significance.

In conclusion, it is our position that Violation 2.a occurred and that the

proper severity level was assigned.

.

.- -

,n

.

--,------,,aw,,,

.,,,.- , ,-, --

,--,m-,,e-,

-m,----,,_,a-w_,,-rw,,,,,

, - , -

, , - - -

-

-,eg,g-,

, - ,. -

,,nw.,c-,

,

-

E-

.,

..

Enclosure

3

October 1,1985

3.

You make the following statement regarding steps to avoid further

violations:

FNP-0-AP-11 will be revised to document evaluation of calibration

interval changes, when such changes are indicated by test equipment

being found out of calibration.

Your response states that interval changes will be documented, but does not

describe a method of trend or failure analysis to determine when such a

change in calibration frequency is warranted.

Your current method of

historical calibration recordkeeping does not provide the means to perform

this analysis.

4.

You make the following statement in your denial:

FN-0-AP-11, Section 4.8 states,

" Storage

4.8.1

Test equipment will be stored in the Calibration Lab or in

such secure locations as the responsible foreman may direct.

4.8.2 /

Storage location environment shall be maintained such that

test equipment accuracy to specifications will be maintained.

4.8.3

Daily access to test equipment will generally be limited to

those personnel assigned to the Calibration Lab for cali-

bration and test equipment checkout activities."

Nothing in the above cited requirement requires any access controls in

addition to those which currently exist.

The subject measuring and

test equipment is physically located for storage in the I&C Calibration

Laboratory wherein a check-out log is maintained. The laboratory is an

enclosed room, not continuously manned at all times, but opens into the

maintenance and storeroom area which is manned 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> a day. Addi-

tionally, the access to the maintenance and storeroom areas as well as

the laboratory itself is in the Owner Controlled Area with access

controlled by Central Security Control.

Neither 10 CFR 50 Appendix B

Criterion XII nor FNP-0-AP-11 Section 4.8 contains any additional re-

quirements for more stringent access control, nor are any warranted.

Our contention is that you have failed to follow your own procedure.

Section 4.8.3 of FNP-0-AP-11 states that " daily access to test equipment

will generally be limited to those personnel assigned to the calibration lab

for calibration and test equipment checkout activities."

There was no

evidence during the inspection that access was ever restricted for anyone

who could gain access to the Owner Controlled Area. The two NRC inspectors

walked in and were unnoticed for 10 minutes. There was no evidence that any

security was provided by personnel in the maintenance and storeroom areas.

Access to the laboratory is actually by a hallway leading to these areas and

-

does not require passage through the maintenance and storeroom area.

The

security issue is therefore twofold.

First, unescorted visitors or

.

. _ _ , _ _ _ _ _ .

_ . , _ _ _ _ . . . _ _

, . _ , _ . _ . , _ _ _ _ _ - . . _ _ . _ _

.

.

.

_ _ . _ _ _ .

r

..

,

.

Enclosure

4

October 1,1985

contractor personnel could tamper with shop standard = or test equipment.

Second, Farley personnel could use test equipment at any time without

ensuring that the usage is properly documented.

You make the following statement in your denial:

Additionally, Alabama Power Company would deny that the alleged

violation is properly designated as Severity Level IV.

Failure to provide security for shop standards and positive accountability

for test standards constitutes a failure to meet regulatory requirements

that has more than minor safety significance.

In conclusion, it is our position that Violation 4 occurred and that the

proper severity level was assigned.

I