| Site: | Waterford |
| Issue date: | 08/02/1985 |
| From: | Johnson E NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION IV) |
| To: | Leddick R LOUISIANA POWER & LIGHT CO. |
| Shared Package | |
| ML20133B972 | List: |
| References | |
| NUDOCS 8508060304 | |
| Download: ML20133B969 (3) | |
See also: IR 05000382/1985016
Text
T
- .,
AUG 0 21985
In Reply Refer To:
Docket:
50-382/85-16
1
.
Louisiana Power & Light Company
ATTN:
R. S. Leddick, Sr. Vice President
Nuclear Operations
142 Delaronde Street
New Orleans, Louisiana 70174
Gentlemen:
This refers to the inspection conducted by Messrs. G. L. Constable,T. A.
Flippo, A. R. Johnson, and W. B. Jones of this office during the period April
1 through May 31, 1985, of activities authorized by NRC Operating Licenses
NPF-26 and NPF-38 for Waterford Steam Electric Station Unit 3, and to the
discussion of our findings with you and other members of your staff at the
conclusion of the inspection.
Areas examined during the inspection included control of design changes,
radioactive contamination of secondary system, startup test procedure review,
Phase III test witnessing, test results evaluation, and survey of
licensee responses to selected safety issues. Within these areas, the
inspection consisted of selective examination of procedures and
representative records, interviews with personnel, and observations by the
inspectors. These findings are documented in the enclosed report.
During this inspection, it was found that certain of your activities were in
violation of NRC requirements.
Consequently, you are required to respond to
these violations, in writing, in accordance with the provisions of Section
2.201 of the NRC's " Rules of Practice," Part 2,' Title 10, Code of Federal
Regulations.
Your response should be based on the specifics contained in
the Notice of Violation enclosed with this letter.
The response directed by this letter and the accompanying Notice is not
subject to the clearance procedures of the Office of Management and Budget as
required by the Paperwork Reduction Act of 1980, PL-96-511.
l
RIV:RRI
RPB1f8)
/p T[Uppo/rl
L(onstable
Johnson
l 7/A. /85
7/ M/85
'pl/85
I
M8EMA*Mjh2
geet
a
- lo
,
i
,
Louisiana Power & Light Company
-2-
Should you have any questions concerning this inspection, we will be pleased
to discuss them with you.
Sincerely,
Cricinal Siened By.
J. P. Jawlon
E. H. Johnson, Chief
Reactor Project Branch 1
Enclosures:
1.
Appendix A - Notice of Violation
- 2.
Appendix B - NRC Inspection Report
50-382/85-16
cc w/ enclosures:
Louisiana Power & Light Company
ATTN:
F. J. Drummond, Manager,
Nuclear Services
142 Delaronde Street
New Orleans, Louisiana 70174
.
.
Louisiana Power & Light Company
ATTN:
R. P. Barkhurst, Plant Manager
P. O. Box B
Killona, Louisiana 70066
Middle South Services
ATTN:
Mr. R. T. Lally
P. O. Box 61000
New Orleans, Louisiana 70161
Louisiana Power & Light Company
ATTN:
T. F. Gerrets, QA Manager
142 Delaronde Street
New Orleans, Louisiana 70174
Louisiana Power & Light Company
ATTN:
G. E. Wuller, Onsite Licensing
Coordinator
P. O. Box B
Killona, Louisiana 70066
Louisiana Div. of Rad. Control
._
$
..
Louisiana Power & Light Company
-3-
~bec to DM8 (1E01)
bec distrib. by RIV:
- RPB1
- Resident Inspector
R. D. Martin, RA
- EP&RPB
- G. Constable, RPB1/B
- MIS System
- RIV File
- R.
Denise, DRS&P
C. Wisner, PA0
- RSTS Opr.
D. Powers, E0
- w/766
{
1
i