ML20133B715

From kanterella
Jump to navigation Jump to search
Responds to Generic Ltr 85-07 Re Implementation of Integrated Schedules for Plant Mods.Informal Integrated Living Schedule Implemented.Formal Integrated Schedule Unnecessary
ML20133B715
Person / Time
Site: Yankee Rowe
Issue date: 08/02/1985
From: Papanic G
YANKEE ATOMIC ELECTRIC CO.
To: Zwolinski J
Office of Nuclear Reactor Regulation
References
FYR-85-79, GL-85-07, GL-85-7, NUDOCS 8508060245
Download: ML20133B715 (3)


Text

- - - - - - -

Tc'ephone (6") s' -s 'oo YANKEE ATOMIC ELECTRIC COMPANY TWX 710-380 7619

(

, ;yi i 1671 Worcester Road, Framingham, Massachusetts 01701 2.C.2.1

,f,[

[ M / FYR 85-79 August 2, 1985 United States Nuclear Regulatory Commission Washington, D. C. 20555 Attention: Mr. John A. Zwolinski, Chief Operating Reactors Branch No. 5 Division of Licensing

References:

(a) License No. DPR-3 (Docket No. 50-29)

(b) USNRC Letter to YAEC, dated May 2, 1985 (c) YAEC Letter to USNRC, dated June 24, 1985

Subject:

Implementation of Integrated Schedules for Plant Modifications (General Letter 85-07)

Dear Sir:

Enclosed is our response to Generic Letter 85-07 on integrated schedules, '

Reference (b), in the format requested. The date for submittal of this information was modified to August 12, 1985, Reference (c). Yankee believes that a form of integrated schedules is warranted and necessary as an internal tool for scheduling engineering and construction to meet NRC and other requirements. We have been using an informal integrated schedule for the past two refueling cycles and have been able to successfully integrate the NRC required workload into our overall engineering and construction workload. A large portion of our NRC workload has been SEP items, which have been spread out over a number of refueling cycles based on a schedule worked out with the staff.

This method of scheduling hau met our needs, and we believe has adequately addressed all NRC requirements. We do not foreseo any workload from the NRC or internally that we cannot accommodate with our present planning process. Therefore, we do not believe that a formal integrated schedule is necessary.

Very truly yours, George Pspanic, Jr.

Senior Project Engineer - Licensing CP/dps 9

h[

'l e

4 l

ENCLOSURE 2 Response Format - Generic Letter 85-Plant Name: Yankee Nuclear Power Station Utility: Yankee Atomic Electric Company I. Intentiona A. Intend to work with the stall to develop an ILS B. Have reservations that must be resolved before developing ILS C. Do not presently intend to negotiate an ILS X with the staff _

D. Have implemented an informal ISL X II. Status A. If you answered I.A above:

1. Have you settled on a method for prioritizing the work at your plant (s)?

Circle One: Yes No Priority for informal ILS is based upon management judgement of the following factors:

(1) Safety Significance - Some use of PRA (2) SEP Work - Prioritize SEP workload to front end more important issues (3) NRC Mandated Items - Items such as EQ, FSAR, NUREG 0737 (4) Plant Betterments - Feedwater replacement, RPS replacement, etc (5) Discretionary Workload - INPO, NRC and internal inspection findings (6) Refueling length (7) Engineering manpower capability (8) Plant manpower capability (9) Cost

2. What is your estimated date for making a submittal to the NRC -

or If not presently available, planned date for scheduling a submittal to the NRC.

(

l

e 4

I B. If you answered I.B. above:

1. Please explain your reservations on separate sheet (s) or provide your schedule for supplying an explanation.

See separate sheets (s) or Separate submittal scheduled for (Date)

2. If available to meet with the staff to discuss your concerns, propose a time frame for such a meeting and provide a contact that can make arrangements.

Contact / Time Frame Phone Number C. If you answered I.C:

1. Would you be willing to meet with the staff to discuss the development of an ILS for your facility (s)?

Circle One: Yes No If yes, propose a time frame for such a meeting and provide s. contact that can make arrangements.

Contact Project Manager Time Framo Meeting was held on July 24 1985 Phone Number If no, any constructive comments your.have would be appreciated.

III. Additional Items l

Please make any suggestions you may have as to ho*f a utility sponsored availability / reliability project might be credited for plant safety enhancement. Provide additional constructive comments as appropriate, i

l i

l