Discusses GL 92-01,Rev 1,Supp 1, Reactor Vessel Structural Integrity. Info Requested on 950817 Received.Nrc Considers RPV Integrity Data for BSEP 1 & 2 to Be Complete
ML20132F893
Person / Time
Site: Brunswick  Duke Energy icon.png
Issue date: 12/23/1996
From: Trimble D
NRC (Affiliation Not Assigned)
To: Campbell W
CAROLINA POWER & LIGHT CO.
References
GL-92-01, GL-92-1, TAC-M92652, TAC-M92653, NUDOCS 9612260127
Download: ML20132F893 (3)


Text

Wo-II j e tro g n~

t UNITED STATES f

j NUCLEAR REGULATORY COMMISSION 2

WASHINGTON, D.C. soseHoot

%..... g' December 23, 1996 Mr. W. R. Campbell Vice President Brunswick Steam Electric Plant i

Carolina Power & Light Company Post Office Box 10429 Southport, North Carolina 28461

SUBJECT:

CLOSE0VT FOR CAROLINA POWER & LIGHT COMPANY'S RESPONSE TO GENERIC LETTER 92-01, REVISION 1, SUPPLEMENT 1 FOR THE BRUNSWICK STEAM ELECTRIC PLANT, UNITS 1 AND 2 (TAC NOS. M92652 AND M92653)

Dear Mr. Campbell:

On May 19, 1995, the NRC issued Generic Letter 92-01, Revision 1, Supplement 1 l

(GL 92-01, Rev.1, Supp.1), " Reactor Vessel Structural Integrity."

In GL 92-01, Rev.1, Supp.1, the NRC requested that nuclear plant licensees perform a review of their reactor pressure vessel structural integrity assessmente in order "to identify, collect, and report any new data pertinent to [the] analysis of [the] structural integrity of their reactor pressure vessels (RPVs) and to assess the impact of that data on their RPV integrity analyses relative to the requirements of Section 50.60 of Title 10 of the Code l

of Federal Regulatfons (10 CFR 50.60), 10 CFR 50.61, Appendices G and H to 10 CFR Part 50 (which encompass pressurized thermal shock (PTS) and upper shelf energy (USE) evaluations), and any potential impact on low temperature overpressure (LTOP) limits or pressure-temperature (P-T) limits."

J More specifically, in GL 92-01, Rev.1, Supp.1, the NRC requested that addressees provide the following information in their responses:

(1) a description of those actions taken or planned to locate all data relevant to the determination of RPV integrity, or an explanation of why the existing data base is considered complete as previously submitted; (2) an assessment of any change in best-estimate chemistry based on consideration of all relevant data; (3) a determination of the need for the use of the ratio procedure in i

accordance with the established Position 2.1 of Regulatory Guide 1.99, Revision 2, for those licensees that use surveillance data to provide a basis for the RPV integrity evaluation; and (4) a written report providing any newly acquired data as specified above and (1) the results of any necessary revisions to the evaluations of RPV j

integrity in accordance with the requirements of 10 CFR 50.60, hp 10 CFR 50.61, Appendices G and H to 10 CFR Part 50, and any potential impact of the LTOP and P-T limits in the technical specifications, or (2) a certification that previously submitted evaluations remain valid. I b

I 2G0004 9612260127 961223 PDR ADOCK 05000324 P

PDR

i t

' Revised evaluations and certifications were to include consideration of Position 2.1 of Regulatory Guide 1.99, Revision 2, as applicable, and any new data. Thelinformation in Reporting Item (1) was to be submitted within 90 days of the issuance of the GL. The information in Reporting Items (2) - (4) l was to be submitted within 6 months of the issuance of the GL, i

The staff has noted that'Ca'rolina Power & Light Co. (CP&L) submitted the information requested in Reporting Item (1) on August 17, 1995, and requested in Reporting Items (2)

(4),on November.16, 1995.

Since CP&L has submitted I

the requested information and has indicated that the previously submitted evaluations remain valid, the-staff considers the RPV integrity data for the Brunswick = Steam Electric Pla'nt,~ Units 1 and 2,,(BSEP 1 & 2) to be complete at 3

this time, ! The staff therefore/ concludes that' no additional inform: tion regarding the' structural integrity.of the'~ RPVs at the BSEP 1 & 2 is available at this' time,.and that your efforts regarding GL 92-01, Rev. 1, Supp. I are complete. This completes 'all' actions related to the referenced TAC Numbers M92652 and M92653.,~

>+

Thank you for your cooperation.

l i

j Sincerely,

%Y0 SY David C. Trimble, Project Manager Project Directorate 11-1 Division of Reactor Projects - I/II Office of Nuclear Reactor Regulation l

l Docket Nos.:

50-325 and DISTRIBUTION:

1 50-324 PUBLIC PD 11-1 RF

~ Docket File D. Mcdonald cc:

See next page FILENAME - G:\\BRUNSWIC\\BR92652.1tr PM:PDII-l LA:FDII-l D:PDII-d DTrimble N EDunningt@ MReinhah 12/19> /96 12/ /f /96 12/J$/9I (fes7No (el/No Yesh 0FFltfAL RECORD COPY l

I l

l t

Jir. W. R. Campbell Brunswick Steam Electric Plant Carolina Power & Light Company Units I and 2 Cc' Mr. William D. Johnson Ms. Karen E. Long Vice President and Senior Counsel Assistant Attorney General Carolina Power & Light Company State of North Carolina Post Office Box 1551 Post Office Box 629 Raleigh, North Carolina 27602 Raleigh, North Carolina 27602 Mr. Jerry W. Jones, Chairman Mr. Robert P. Gruber Brunswick County Board of Commissioners Executive Director Post Office Box 249 Public Staff - NCUC Bolivia, North Carolina 28422 Post Office Box 29520 Raleigh, North Carolina 27626-0520 Resident Inspector U.S. Nuclear Regulatory Comission Mr. W. Levis

)

8470 River Road Director i

Southport, North Carolina 28461 Site Operations Brunswick Steam Electric Plant j

Regional Administrator, Region II Post Office Box 10429 U.S. Nuclear Regulatory Commission Southport, North Carolina 28461 101 Marietta St., N.W., Ste. 2900 Atlanta, Georgia 30323 Mr. William H. Crowe, Mayor City of Southport i

Mr. Dayne H. Brown, Director 201 East Moore Street Division of Radiation Protection Southport, North Carolina 28461 N.C. Department of Environmental, Commerce and Natural Resources Mr. Dan E. Summers Post Office Box 27687 Emergency Management Coordinator Raleigh, North Carolina 27611-7687 New Hanover County Department of Emergency Management Mr. R. P. Lopriore Post Office Box 1525 Plant Manager Wilmington, North Carolina 28402 Carolina Power & Light Company Brunswick Steam Electric Plant Mr. J. Cowan Post Office Box 10429 Vice President Southport, North Carolina 28461 Nuclear Services and Environmental Support Department Public Service Commission Carolina Power & Light Company State of South Carolina Post Office Box 1551 - Mail OHS 7 Post Office Drawer 11649 Raleigh, North Carolina 27602 Columbia, South Carolina 29211 Mr. Gerald D. Hicks Mr. Milton Shymlock Manager - Regulatory Affairs U. S. Nuclear Regulatory Commission Carolina Power & Light Company 101 Marietta Street, N.W. Suite 2900 Post Office Box 10429 Atlanta, Georgia 30323-0199 Southport, North Carolina 28461 I