i GPU Nuclear,Inc.
\\
One Upper Pond Road NUCLEAR Parsippany, NJ 070M-1095 Tel 201316-7000 December 9,1996 B000 058 6730 2352 U. S. Nuclear Regulatory Commission Attention: Document Control Desk Washington, DC 20555 Gentlemen:
i
Subject:
Oyster Creek Nuclear Generating Station (OCNGS)
Docket No. 50-219/ License No. DPR 16 Long Range Planning Program (LRPP)
Annual Update ofIntegrated Schedule i
"ABC" Projects Listing - December,1996 Pursuant to condition 2.C.(10) of Operating License DPR-16, GPU Nuclear has implemented the Long Range Planning Program for OCNGS. As required by Section V.A of the Plan, the following e
attachments are submitted to provide the annual project list update:
1.
Attachment A contains a new project list of Category A, B and C projects, annotated by an asterisk (*) to identify new projects. Completed projects have been removed from the schedule listing. Also noted by a double asterisk (**) are f
budget activity numbering changes.
(
2.
Attachment B contains a summary of Category A, B, and C projects which have been completed, deleted, deferred, changed in scope. Category A and B projects yg}
which have had schedule changes are provided with explanations, as appropriate.
- i U J
9612160427 961209 PDR ADOCK 05000219 p
PDR 160023
December 9,1996 B000 - % - 058 6730 2352 Page 2 j
l l
Pursuant to the LRPP for Oyster Creek, it will be assumed that you are in agreement with the actual j
Category B changes above ifyou do not respond to this submittal within 15 days of receipt.
]
Sincerely, i
l
)
['l Peter E. Maricondo Vice President and Director Financial & Planning Services I
PEM/GMG/
l cc:
Director, Project Directorate I-4 Oyster Creek NRC Project Manager Senior NRC Resident Inspector, OCNGS l
l l
l l
i i
i l
l
't p
l l
l ATTACHMENT A PROJECT LISTING INTEGRATED SCHEDULE ANNUAL UPDATE (DECEMBER 1996) l IM30ll63 I
t OYSTER CREEK PROJECT LISTING.
LEGEND NRC INTEGRATED SCHEDULE NEW PROJECTS
- BA NUMBER CHANGE CATEGORY
'B' PROJECTS u
SORT BY CATEGORY / CYCLE /BA STATUS AS OF 12/04/1996 OBS BA DESCRIPTION CYCLE /
CLASSIFICATION NUMBER YEARS 1 328030 CNTL RM HUMAN FACTORS DESGN REVIEW 16 NRR CR REPAINT, REFURBISH & RELABEL CR PANELS 1R THRU 10R,6XR,11XR,12R,12XR,14R,14XR, 16R AND 11F,9XR&11R.NUREG 0737 SUP 1.
i 2 403042 THERMO-LAG FIRE BARRIER MODIFICATIONS 16 NRR THIS MODIFICATION WILL MODIFY THE TSI THERMO-LAG FIRE BARRIERS TO MEET THE APPROPRIATE FIRE REQUIREMENTS 3 403092 SEISMIC QUALIFICATION MODS - PHASE II 16 NRR t
IMPLEMENT SQUG MODIFICATIONS AS NECESSARY 4 32XAHD RX. VESSEL INTERNAL INSPECTION -17R 17R NRR 119 VISUAL INSPECTION OF SELECTED INTERNAL COMPONENTS AND SURFACES AS REQUIRED BY ASME CODES i
5 32XAHE RCS AUG-IGSCC INSPECTION - 17R 17R NRR RB DW INSPECT PIPING WELDS PER NUREG 0313 REV2 i
6 403042 THERMO-LAG FIRE BARRIER MODIFICATIONS 17R NRR THIS MODIFICATION WILL MODIFY THE TSI THERMO-LAG FIRE BARRIERS TO MEE"T THE APPROPRIATE FIRE REQUIREMENTS i
7 403048 ECCS SUCTION STRAINERS 17R MRC TOR INSTALL NEW SUCTION STRAINERS TO THE ECCS SYSTEM IN THE TORUS AS RECOMM.
BY NRC, CONTING. ON ACCEPT. DESIGN i
_. ~
-- ~.-. -._.-.- -. - - - _.-.~ ~.
.. _.. -. ~ - ~ - - -. - _.. _ -
- ~ --. _. ~. - ~ ~ -. ~ ~ ~....
OYSTER CREEK PROJECT LISTIEG LEGENT NRC INTEGRATED SCHEDULE NEW PROJECTS
- BA NUMBER CHANGE CATEGORY
- B' PROJECTS SORT BY CATEGORY / CYCLE /BA STATUS AS OF 12/04/1996 OBS BA DESCRIPTION CYCLE /
CLASSIFICATION NUMBER YEARS 8 403092 SEISMIC QUALIFICATION MODS - PHASE II 17R NRR IMPLEMENT SQUG MODIFICATIONS AS
{
NECESSARY r
v
?
9 32XAHD RX. VESSEL INTERNAL INSPECTION -18R 18R NRR 119 VISUAL INSPECTION OF SELECTED INTERNAL l
COMPONENTS AND SURFACES AS REQUIRED BY ASME CODES g
10 32XAHE RCS AUG-IGSCC INSPECTION - 18R 18R NRR
['
RB DW INSPECT PIPING WELDS PER NUREG 0313 REV2 11 326216 RX. VESSEL BELTLINE INSPECTION 18R NRR
[
119 i
UT ACCESSIBLE WELD SEAMS IN THE RPV BELTLINE REGION. INSPECTIONS WILL BE DONE i
RMCfrELY. ASME SECT. XI REQUIREMENTS L
i r
I v
i a
r i
I L
OYSTER CREEK PROJECT L I S T I 95 G LEGEND NRC INTEGRATED SCH.EDULE NEW PROJECTS
- BA NUMBER CHANGE CATEGORY
'C' PROJECTS SORT BY CATEGORY / CYCLE /BA STATUS AS OF 12/04/1996 OBS BA DESCRIPTION CYCLE /
CLASSIFICATION NUMBER YEARS i
12 312000 SPENT FUEL TRANS TO INTERIM STORAGE 17 MRC TRANSFER SPENT FUEL FROM FUEL POOL TO DRY STORAGE FACILITY 13 312600 VALVE RELIABILITY & MAINTENANCE-17R-17R MRC PERFORM CORRECTIVE AND PREDI CIVE MAINT ON SELECTED VALVES 14 312600 CRD HCU REBUILD - 17R 17R MRC REBUILD HYDRAULIC CONTROL UNITS 15 312600 SCAFFOLD & INSULATION - 17R 17R MRC INSTALL SCAFFU1D TO SUPPORT PROJECTS &
MAINTENANCE DURING THE OUTAGE 16 323LO3
'IURBINE INSP.-17R 17R MRC TB INSPECT MISCELLANEOUS 'IURBINE RELATED COMPONENTS FOR NML REQUIREMENTS AND MANUF. SUGGESTION 17 323748 REFUEL PIDOR RX DISASSEMBLY / REASSEMBLY 17R MRC 119' TASKS ASSOCIATED WITH REACTOR DISASSEMBLY AND REASSEMBLY AND t
SUPPORTING ACTIVITIES 18 32696G OUTAGE ISI 17R NRR ALL INSPECT HANGERS, PIPING WELD,&
COMPONENTS TO SATISFY SECTION XI REQUIREMENTS
OYSTER CREEK PROJECT LISTING LEGEND NRC INTEGRATED SCHEDULE NEW PROJECTS
- BA h M ER CHANGE CATEGORY
'C' PROJECTS SORT BY CATEGORY / CYCLE /BA STA7US AS OF 12/04/1996 OBS BA DESCRIPTION CYCLE /
CLASSIFICATION NUMBER YEARS i
19 328378 PIPE WALL THINNING - 17R 17R ISM REMOVE INSULATION, PREP SURFACES &
PERFORM UT ON SELECTED PIPING SYSTEMS.
POSSIBLE REPLACEMENT OF FITTINGS / PIPING 20 408957 VALVE REPLACEMENT / RETIREMENT-17R 17R REL RB TB CBAY DW REPLACE SELECTED VALVES IDENTIFIED AS i
HAVING DEFICIENCIES 21 312600 VALVE RELIABILITY & MAINTENANCE-18R 18R MRC 1
PERFORM CORRECTIVE AND PREDICTIVE MAINT ON SELECTED VALVES 22 312600 CRD HCU REBUILD - 18R 18R
.MRC REBUILD HYDRAULIC CONTROL UNITS 23 312600 SCAFFOLD & INSULATION - 18R 18R MRC INSTALL SCAFFOLD TO SUPPORT PROJECTS &
MAINTENANCE DURING THE OUTAGE 24 323LO3 TURBINE INSP.-18R 18R MRC TB INSPECT HP AND LPA AND OTHER TURBINE RELATED COMPONENTS FOR NML NML REQUIREMENTS AND MANUF. SUGGESTION l
25 323748 REFUEL FIDOR RX DISASSEMBLY / REASSEMBLY 18R MRC 119' s
TASKS ASSOCIATED WITH REACTOR DISASSEMBLY AND REASSEMBLY AND SUPPORTING ACTIVITIES
+
i i
OYSTER CREEK PROJECT LISTING LEGEND NRC INTEGRATED SCHEDULE NEW PROJECTS
- BA NUMBER CHANGE CATEGORY
'C' PROJFCTS SORT BY CATEGORY / CYCLE /BA STA'IUS AS OF 12/04/1996 OBS BA DESCRIPTION CYCLE /
CLASSIFICATION NUMBER YEARS 26 32696G OUTAGE ISI 18R NRR ALL INSPECT HANGERS, PIPING WELD,&
COMPONENTS TO SATISFY SECTION XI REQUIREMENTS 27 328378 PIPE WALL THINNING - 18R 18R ISM REMOVE INSULATION, PREP SURFACES &
PERFORM UT ON SELECTED PIPING SYSTEMS.
POSSIBLE REPLACEMENT OF FITTINGS / PIPING 28 408957 VALVE REPLACEMENT / RETIREMENT-18R 18R REL RB TB CBAY DW REPLACE SELECTED VALVES IDENTIFIED AS HAVING DEFICIENCIES t
29 402980 CONFIGURATION MANAGEMENT-DBD 92-97 92-97 ISM t
DEVEIOPMENT OF OC SYSTEM DESIGN BASES 30 328370 VESSEL & INTERNALS PROJECT (BWR VIP) 94-99 NRR
(
f EVALUATE THE REACTOR AND INTERNALS FOR POTENTIAL CRACKING AND DEVELOP METHODS FOR INSPECTION / MITIGATION / REPAIR 31 409307 REPLICATOR SIlWLATOR MODS - 1997/99 97/99 NRR i
?
UPGRADE THE SIMULATOR TO MATCH PLANT f
MODS AS APPLICABLE i
s 1
(
f I
l l
ABC Classifications i
a)
Meet NRC Reauirements (NRR) - Activities that a) must be carried out to fulfill specific NRC requirements or b) have been committed to the NRC by the Company or c) are j
such that if not accomplished would result in an NRC non-compliance even though the specific activity is not required by the NRC.
b)
Meet Environmental Reauirements (ERR)- Activities that a) are specifically required by environmental regulatory agencies (State and Federal) or b) have been committed to environmental agencies by the Company or c) are such that if not accomplished would result in a regulatory non-compliance even though the specific activity is not required by an environmental regulatory agency.
c)
Meet Other Reauirements (ORR) - Activities not covered by the NRC or environmental requirements but that are required by local, state, or federal ordinances, codes, court order or lawsuit settlement, or other guidance to which the Company is committed or if not accomplished would result in a violation of that ordinance, code or guidance, court order, etc.
d)
Increase Safety Mareins (ISM) - Activities that, if implemented, will improve nuclear plant or personnel safety but are neither required for regulatory compliance nor required by safety regulations, codes or guidance.
e)
Decrease Environmental Effects (E) - Activities that, if implemented, will result in an improved environmental quality but are neither required for regulatory compliance nor required by environmental regulations, codes or guidance.
I f)
Imorove Radiolocical Conditions (RAD) - Activities that, if implemented, will result in improved radiological conditions, lower man-rem exposure rates, or radwaste control / reduction but are neither required for regulatory compliance nor required by radiological regulations, codes or guidance.
g)
Maintain Reliabilitv/Canability (MRC) - Activities that, if implemented, will maintain power production at existing levels by preventing deterioration of plant systems or equipment. Includes activities in response to national codes and standards, insurance policies, equipment vendor specifications or nuclear industry high unavailability equipment data without which the plant could not operate prudently, h)
Imorove Reliabilitv/ Capability (REL) - Activities that, if implemented, will increase power generation by improving availability or capacity factor to maximize energy j
output.
l
ABC Classifications (continued) i)
Imorove Operationai ht'tectivcaces (IOE) - Activities that, if implemented, will improve staff efficiency or provide a direct economic payback in terms of reduced operating / maintenance costs, j)
Imorove Personnel Facilities (FAC) - Activities that, if implemented, will improve working conditions and the usefulness of personnel facilities.
k)
Provide Contingency / Blanket (CUI) - Activities that, if implemented, will provide management flexibility to respond in a timely manner to emergent work requirements or the ongoing requirements to procure, replace or repair minor items essential to support routine operations.
1)
Imoroves Heat Rate Performance (HRP) - Activities, that, if implemented, will increase power production by enhancing the heat rate efficiency.
m)
General Working Conditions (GWC) - Activities, tools, and equipment that if implemented will improve working conditions, but will not demonstrate a direct cconomic payback.
l I
i l
i i
l l
ATTACHMENT B
)
1 OYSTER CREEK NUCLEAR GENERATING STATION i
l l
NRC INTEGRATED SCHEDULE ANNUAL UPDATE 1
CATEGORY "A" PROJECTS Completions:
409791 - Security Intrusion Protection Upgrade l
i i
l B4501163
~-
l j
CATEGORY "B" PROJECTS Additions:
As denoted by
- next to the Project Title in Attachment A.
]
l Completions:
328226 - SQUG Program Implementation - Cycles 14 /15 328382 - Reactor Vessel Internal Inspection - 16R 328393 - 16R Outage ISI & RCS Augmented IGSCC Inspections Schedule Change:
328030 - Control Room Human Factors Design Review The cycle for implementing the Detailed Control Room Design 1
Review (DCRDR) recommendations for the back panels has been extended from Cycles 14/15 to Cycle 16. A limited amount of painting and relabeling of back panels has been completed.
However, due to resource reallocation in preparation for the 16R refueling / maintenance outage, all work could not be completed as previously scheduled. GPUN fully intends to resolve the DCRDR human engineering deficiencies, as previously planned, on the control room back panels.
i
\\
B450ll63
- - - = = -
l t
I I
i CATEGORY "C" PROJECTS i
l l
Additions:
As denoted by
- next to the Project Title in Attachment A.
Completions:
312600 - Valve Reliability & Maintenance - 16R 312600 - CRD HCU Rebuild - 16R l
32F245 - Drywell Scaffold & Insulation '16R 323704 - Valve Reliability Maintenance - 15 323747 - 16R Turbine Overhaul Project 323748 - Refuel Floor Reactor Disassembly / Reassembly - 16R 328148 - Plant Life Assurance & Extension 1992-95 328321 - Pipe Wall Thinning - 16R 328383 - EDG Unique Maintenance - 16R l
402821 - Recirculation Pump & Motor Vibration Monitors - 16R 402880 - Spent Fuel Storage Capacity Expansion - 15 402982 - IPE External Events 1992-95 403024 - SQUG Mods - 16R 1
403036 - Spent Fuel Cask Handling Upgrades - 15 403053 - Upgrade MSIV Limit Switches - 16R 403060 - Deaerating Steam System Retirement - 16R 403063 - Remove High Recirculation Flow Scram Function - 16R 403075 - LP-C Replacement Turbine Rotor - 16R 403079 - Generic Letter 89-1016R Modifications 408957 - Valve Replacement / Retirement - 16R 409280 - Replica Simulator Mods - 1995 Deletions:
312000 - Spent Fuel Transfer to Interim Storage - Cycle 15 328148 - Oyster Creek Life Assurance / License Renewal 40996D - Replica Simulator Mods,96-00 Schedule Change:
403063 - Remove High Recirculation Flow Scram Function The schedule for this project was changed from a 15U outage of opportunity to the 16R Outage.
J Other Changes:
326L15 - BA Number for Scaffold & Insulation,17R and 18R, was changed to 312600.
328370 - Vessel & Internals Project j
Years changed from 94-96 to 94-99.
l 402980 - Configuration Management - DBDs Years changed from 92-00 to 92-97 B4501163
.. _ _