MONTHYEARML23087A2922023-04-12012 April 2023 2022 Annual Assessment Meeting ML22301A1662022-09-29029 September 2022 Presentation 4 - Recent Biennial PI&R Team Inspection Insights ML22251A2352022-09-14014 September 2022 Presentation Slides for September 14, 2022, Observation Public Meeting ML22257A2392022-09-14014 September 2022 Presentation Slides for September 14, 2022, Observation Public Meeting ML22151A2652022-05-31031 May 2022 Presubmittal Licensee Presentation for 3.3.2 ESFAS Proposed LAR ML22109A2122022-04-20020 April 2022 Duke Energy Pre-Submittal Public April 20, 2022, Meeting Presentation ML22083A1072022-03-30030 March 2022 Presubmittal Licensee Presentation for SR 3.8.1.16 Proposed License Amendment Request (EPID L-2022-LRM-0021) (Slides) ML22007A2592022-02-0202 February 2022 Presubmittal Licensee Presentation for TS 3.5.3 PIV Testing LAR ML21322A3262021-11-29029 November 2021 Duke Energy November 29, 2021 Pre-Submittal Public Meeting Slides for EOF Relocation Licensing Amendment Request ML21174A3212021-06-24024 June 2021 Licensee Presentation for Robinson Presubmittal Meeting TSTF 577, Rev. 1 ML21167A0852021-06-24024 June 2021 Licensee Presentation for Robinson Pre-submittal Meeting TSTF-577 ML21105A7522021-04-15015 April 2021 2020 Robinson - EOC Presentation Slides ML21053A0472021-02-25025 February 2021 Duke Energy Pre-Submittal Meeting - February 25, 2021 - H. B. Robinson 3rd Interval Containment ISI Relief Request ML20132A0002020-05-11011 May 2020 EOC Presentation ML19318F2912019-11-18018 November 2019 Duke Energy Presentation for the Pre-submittal Meeting on November 18, 2019, Regarding the RPV Stud Examination Relief Request ML19214A0562019-08-0707 August 2019 Presentation: Duke Energy Presubmittal Meeting - August 7, 2019 ML17331A6272017-11-29029 November 2017 Duke Energy Pre-Submittal Meeting Presentation, Brunswick, Harris, and Robinson License Amendment Requests Regarding 10 CFR 50.69 ML17244A2272017-09-0707 September 2017 Duke Energy Presentation - H.B. Robinson 2017-09-07 Pre-sub Transmission Upgrade Meeting ML17200C7802017-07-19019 July 2017 Duke Energy Pre-submittal Meeting Presentation, August 3, 2017, Harris and Robinson License Amendment Request to Support the Transition to Duke Non-LOCA Analysis Methods, MF9824, MF9825 ML16112A2932016-05-0202 May 2016 05/02/2016 Presentation for Closed Pre-Submittal Meeting with Duke Energy Progress, Inc., to Discuss Fuel Reload Design Methodology Reports and Proposed LAR Re. H. B. Robinson And Shearon Harris Plants (CAC Nos. MF7443 And MF7444) ML16105A3342016-04-20020 April 2016 H. B. Robinson Steam Electric Plant, Unit 2 - April 20, 2016, Duke Energy Presentation for 24-Month Fuel Cycle Pre-submittal Meeting (CAC No. MF7503) ML15231A6062015-08-19019 August 2015 Duke Energy Presentation - Robinson Nuclear Plant Transmission Upgrade Pre-submittal Meeting 08-26-2015 - MF6477 ML15099A5872015-04-14014 April 2015 Duke Energy Slides for April 14 Meeting on NFPA-805 for Catawba, McGuire and Robinson ML14181A0782014-06-30030 June 2014 June 30 NRC Slides for Public Meeting with Duke - NTTF 2.1 - Seismic Reevaluation - GMRS ML14154A0932014-06-0303 June 2014 May 28, 2014, Summary of Category 1 Public Meeting - Annual Assessment of H.B. Robinson Steam Electric Plant ML13312A9882013-11-0808 November 2013 Summary of Public Meeting with Duke Energy Carolinas, LLC, to Provide Opportunities to Discuss the Planned Fukushima-Related Modifications ML13308A0072013-11-0101 November 2013 Open Phase Resolution Update Meeting Duke Energy Entitled Open Phase Detection and Protection. ML13238A0542013-08-23023 August 2013 Meeting Summary - Category 1 Public Meeting Regulatory Conference, H.B. Robinson Steam Electric Plant, Docket No. 50-261 ML13150A0742013-05-29029 May 2013 Meeting Summary - Category 1 Public Meeting - Annual Assessment of H.B. Robinson Steam Electric Plant ML13127A0802013-04-18018 April 2013 Fleet Fire Protection Program NFPA 805 National Fire Protection Association NFPA 805 Pre-LAR Application for CNS, MNS, RNP ML12107A3552012-04-16016 April 2012 4/11/2012 Summary of Category 1 Public Meeting - Annual Assessment of H.B. Robinson Steam Electric Plant ML1124200662011-08-30030 August 2011 Meeting Summary - Robinson - NRC Slides ML1124200682011-08-30030 August 2011 Meeting Summary - Robinson - Progress Energy Slides ML1123601792011-08-24024 August 2011 8/25/2011- Robinson Nuclear Plant Regulatory Performance Meeting Slides ML1123603572011-08-24024 August 2011 Meeting Slides ML12083A0492011-07-20020 July 2011 Meeting Slides - Meeting with Carolina Power & Light Company to Discuss the H. B. Robinson Steam Electric Plant, Unit 2 Performance Improvement Plant and New Management ML1113703442011-05-11011 May 2011 05/11/2011 Meeting Slides Regarding Strategic Plan ML11102A0052011-04-12012 April 2011 Progress Energy - Slides for NFPA 805 Pre-LAR Application Meeting April 12, 2011 ML1108909072011-03-30030 March 2011 Slides of Meeting Regarding H.B. Robinson Annual Assessment Meeting ML1032006182010-11-16016 November 2010 Public Meeting Summary - Category One - Regulatory and Enforcement Conference Meeting (Robinson) ML1013904942010-05-12012 May 2010 Event Review for Robinson - Slides ML1011703342010-04-27027 April 2010 Summary of Category 1 Public Meeting with Carolina Power and Light Company Regarding NRC Reactor Oversight Process Annual Assessment H.B. Robinson Steam Electric Plant, Unit 2 ML0912706522009-05-0606 May 2009 Summary of Category 1 Public Meeting Discussed NRC Reactor Oversight Process Annual Assessment of H. B. Robinson, Unit 2 ML0830800052008-10-31031 October 2008 Meeting Slides, Progress Energy Public Meeting, NRC Region II Visit ML0813706302008-05-0707 May 2008 Slides from H. B. Robinson Meeting Re. Robinson Steam Electric Plant Annual Assessment Meeting Reactor Oversight Program - Cy 2007 ML0722100412007-07-26026 July 2007 Meeting Slides NRC Region Meeting Robinson Nuclear Plant. ML0716505352007-05-21021 May 2007 Enclosure - Slides for NRC CY2006 Annual Assessment Meeting ML0611402602006-04-0404 April 2006 Public Meeting Slides - Category One Management Meeting H. B. Robinson, Unit 2 ML0615301932006-03-27027 March 2006 NFPA 805 Pilot Observation Visit Trip Report - March 2006 - Handouts ML0523604402005-08-11011 August 2005 Attachment 4 - Progress Energy Slides 2023-04-12
[Table view] |
Text
H.B. Robinson Unit 2 Annual Assessment Meeting 2019 Reactor Oversight Process (ROP)
U.S. Nuclear Regulatory Commission Region 2 / Division of Reactor Projects ML20132A000
Agenda Introductions - Robinson Resident Inspectors and Regional Staff Responsible for Robinson Oversight Strategic Plan Goals Annual Assessment Summary Findings Performance Indicators NRC Plans for 2020 COVID-19 Response
Introductions
Resident Inspectors Matthew Fannon- Senior Resident Inspector Amy Beasten, PhD- Resident Inspector Regional Personnel Randy Musser - Branch Chief Lundy Pressley - Senior Project Engineer Adam Wilson - Project Engineer
The NRCs Resident Inspectors NRC Strategic Plan Goals Safety - Ensure adequate protection of public health and safety and the environment Security - Ensure adequate protection of the secure use and management of radioactive materials
NRC Annual Assessment Summary H.B. Robinson Duke Energy Progress, LLC/H.B. Robinson operated the plant safely and in a manner that preserved the public health and safety and protected the environment.
H.B. Robinson was in the licensee response Column (Column 1 of IMC 0305) of the NRCs ROP Action Matrix for the last quarter of 2019.
NRC Inspection Activities H.B. Robinson for 2019 Approximately 6000 hours0.0694 days <br />1.667 hours <br />0.00992 weeks <br />0.00228 months <br /> of inspection and related activities 2 Resident inspectors onsite for full-time inspection coverage throughout the year 8 Onsite inspections involving regional inspectors
NRC Inspection Activities H.B. Robinson for 2019 - cont.
2 major team inspections Emergency Preparedness Exercise Inspection Design Basis Assurance Inspection
H.B. Robinson PIs and Findings January 1 through December 31, 2019 All Green Performance Indicators One Green Non-cited violation 3 Apparent Violations, which were closed out to a Confirmatory Order issued in March 2020
NRC Plans for 2020 NRC plans baseline inspections at H.B. Robinson for the remainder of 2020.
This includes:
Force-on-Force Exercise Inspection Inservice Inspection (ISI)
Radiation Safety during Refueling Outage Design Basis Assurance Inspection (Programs)
Triennial Fire Protection Program Inspection Problem Identification and Resolution Inspection (completed)
NRC Response to Mission Critical Functions Monitoring plant activities remotely through inspections and oversight Maintaining emergency response capabilities with Regional IRCs and HQ Limiting and risk-informing on-site inspections by residents and region-based inspectors
NRC Response to Additional Actions Expanded use of telework Ongoing Review of Continuity of Operations Plan Coordinating actions with industry to minimize inspection impacts while protecting inspectors and plant staff
H.B. Robinson Plant Response The H.B. Robinson priority is maintaining the health and safety of its employees.
The site is engaged in social distancing by conducting virtual meetings and having employees telework when possible.
Work on site will be focused on a narrow set of responsibilities to ensure customer needs are met.
Getting in Touch with the NRC Website - www.nrc.gov Questions/Information -
OPA2.Resource@nrc.gov or 404-997-4417 Allegations 800-695-7403 Employment - 301-415-7400 or www.usajobs.gov
NRC Social Media
https://service.govdelivery.com/accounts/USNRC/subscriber/new
End of Presentation Nuclear Regulatory Commission Region 2 Please submit questions or feedback regarding the meeting by emailing Randy.Musser@nrc.gov Roger.Hannah@nrc.gov
NRC - Region 2 QUESTIONS?
COMMENTS Randy.Musser@nrc.gov Roger.Hannah@nrc.gov