ML20129D997
| ML20129D997 | |
| Person / Time | |
|---|---|
| Site: | Beaver Valley |
| Issue date: | 09/06/1996 |
| From: | Jain S DUQUESNE LIGHT CO. |
| To: | NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM) |
| Shared Package | |
| ML20129E000 | List: |
| References | |
| NUDOCS 9609300256 | |
| Download: ML20129D997 (3) | |
Text
E
~_.
Beave Valley Power Stat Shippingport, PA 15077 0004 i
aN ra 4:
September 6, 1996 i
c rv s Nuckar Power DMalon l
U. S. Nuclear Regulatory Commission Attention: Document Control Desk Washington, DC 20555-0001
Subject:
Beaver Valley Power Station, Unit No. I and No. 2 BV-1 Docket No. 50-334, License No. DPR-66 BV-2 Docket No. 50-412, License No. NPF-73 Proposed Operating License Change Request Nos. 213 and 80 Pursuant to 10 CFR 50.90, Duquesne Light Company requests an amendment to the above licenses in the form of changes to the technical specifications. The proposed changes would revise Table 3.3-3, titled " Engineered Safety Feature Actuation System Instrumentation," Table 3.3-5, titled " Engineered Safety Features Response Times," for Beaver Valley Power Station (BVPS Unit No.1 only), Table 3.3-4, titled " Engineered Safety Features Actuation System Instrumentation Trip Setpoints," (for BVPS Unit No. 2 only), Table 4.3-2, titled " Engineered Safety Feature Actuation System Instrumentation Surveillance Requirements," (for BVPS Unit No. 2 only). Table 4.3-6, titled " Remote Shutdown Panel Monitoring Instrumentation Surveillance Requirements," Table 4.3-7, titled
" Accident Monitoring Instrumentation Surveillance Requirements,"
and specification 3.7.1.2, titled " Auxiliary Feedwater System," and associated Bases.
The proposed technical specification changes for Unit No. I and Unit No. 2 are presented in Attachments A-1 and A-2, respectively. The safety analysis (including the no significant hazards evaluation) is presented in Attachment B.
[
An implementation period of 60 days is requested following the effective date of the amendment.
p
)
\\
s DEllVERING gg(Q QUAlliV ENERGV 9609300256 960906 t
PDR ADOCK 05000334 p
PDR J
' Beaver Valley Power Station, Unit No. I and No. 2 Proposed Operating License Change Request Nos. 213 and 80 Page 2 This change has been reviewed by the Onsite Safety Committee and Offsite Review Committee. The change was determined to be safe and does not involve a significant hazard consideration as defined in 10 CFR 50.92 based on the attached safety analysis.
Sincerely, J_J L %
Sushil C. Jain c:
Mr. D. M. Kern, Sr. Resident Inspector Mr. H. J. Miller, NRC Region I Administrator Mr. D. S. Brinkman, Sr. Project Manager Mr. W. P. Dornsife, Direcior BRP/DEP Mr. M. P. Murphy (BRP/DEP) 1
AFFIDAVIT FOR APPLICATION OF AMENDMENT j
COMMONWEALTH OF PENNSYLVANIA)
) SS:
COUNTY OF BEAVER
)
Subject:
Beaver Valley Power Station, Unit No. I and No. 2 BV-1 Docket No. 50 334, License No. DPR-66 BV-2 Docket No. 50-412, License No. NPF-73 Proposed Operating License Change Request Nos. 213 and 80 Before me, the undersigned notary public, in and for the County and Commonwealth aforesaid, this day personally appeared Sushil C. Jain, to me known, who being duly sworn according to law, deposes and says that he is Division Vice President, Nuclear Services of the Nuclear Power Division, Duquesne Light Company, he is duly authorized to execute and file the foregoing submittal on behalf of said Company, and the statements set forth in the submittal are true and correct to the best of his knowledge, information and belief.
W
~
Sushil C. Jain Subscribed and swom to before me on this[d ay of d
,/776 y
A 2 1 2 2 -.
'~
Njstan[Public w
W eeuw m.