ML20129D698

From kanterella
Jump to navigation Jump to search
Requests Status of Implementation Schedule for Completion of Control Items in 850128 Stipulation Settling Util Licensing Case
ML20129D698
Person / Time
Site: Clinton 
Issue date: 07/10/1985
From: Samelson A
ILLINOIS, STATE OF
To: Siegel B
Office of Nuclear Reactor Regulation
References
NUDOCS 8507160626
Download: ML20129D698 (1)


Text

,

N EIL F. H ARTIG AN ATTO R N EY GENERAL STATE OF ILLINOIS SPRINGFIELD 62700 g J/6 /

July 10, 1985 Mr. Byron Siegel Division of Nuclear-Reactor Regulation U.S. Nuclear Regulatory Commission Mail Code 416 Washington, D.C.

20555 Re:

Illinois Power Company Clinton Power Station

Dear Mr. Siegel:

I am writing to inquire regarding the status of the imple-mentation schedule for completion of the control items contained in the January 28, 1985 Stipulation settling the Clinton Unit 1 licensing case-(NRC no. 50-461 OL).

Based upon our review of recent corres-pondence, it appears the timetable for the applicant's actions and NRC's reviews has been revised.

Consequently, in order to properly plan for the implementation of this office's rights under the January 28, 19F5 Stipulation, I am requesting current information as to the applicant's. implementation schedule and the NRC's review schedule for

.the following items:

(1)

Water Level Measurement System Improvements; (2)

Safety Parameter Display System Improvements; (3)

Regulatory Guide 1.97 Instrumentation; and (4)

Detailed Control Room Design Review.

Please call Greg Minor (408) 266-2716 or me (217) 782-9031 if you have any questions with respect to this request.

Very truly yours, DO K hh00k61 PDR Allen Samelson Assistant Attorney General Environmental Control Division AS:rsr cc:

Sheldon Zabel John McCaffrey g/

Richard Goddard Greg Minor