Text
F
i
'
.
.
,
APPENDIX A
Gulf States Utilities
Docket:
50-458/85-33
River Bend, Unit 1
Permit:
CPPR-145
During an NRC inspection conducted on June 26, 1985, a violation of NRC
requirements was identified. The violation involved the making of changes to
quality assurance records.
In accordance with the " General Statement of
Policy and Procedure for NRC Enforcement Actions," 10 CFR Part 2, Appendix C
(1985),theviolationislistedbelow:
1.
Criterion XVII of Appendix B to 10 CFR Part 50 requires that inspection
records identify the inspector, the results, and the acceptability.
Contrary to the above, the NRC inspector determined that the results for
the general clearances attribute on Inspection Reprt Number P5400381
dated June 12, 1985, had been changed on June 13, 1985, from "not
applicable" to " satisfactory" by a reviewer who neither had performed the
inspection nor had any other inspection documentation to support the
change.
The two supports identified in Inspection Report Number P5400381 were
inspected by the NRC inspector and complied with th? general clearance
requirements of Construction Site Instruction Number 3.1.1, Revision 4.
A preliminary review by the licensee determined ttet e small percentage
of other safety-related inspection reports contair.cd similar changes.
This is a Severity Level V Violation.
(SupplementII.E)
Pursuant to the provisions of 10 CFR 2.201, Gulf States Utilities is hereby
required to submit to this office, within 30 days of the date of this Notice, a
written statement or explanation in reply, including:
(1) the reason for the
violation if admitted; (2) the corrective steps which have been taken and the
resultsachieved;(3)correctivestepswhichwillbetakentoavoidfurther
violations; and (4) the date when full compliance will be achieved. Consid-
eration may be given to extending your response time for good cause shown.
Dated at Arlington, Texas
this 5" day of July,1985.
.