Forwards Insp Rept 50-346/85-17 on 850311-15.No Violation Noted.Findings Demonstrate Weakness in Evaluation & Implementation of Manufacturer Recommendations for Diesel Generators,Reactor Trip Breakers & Fire Dampers
ML20129B616
Person / Time
Site: Davis Besse Cleveland Electric icon.png
Issue date: 06/26/1985
From: Zech G
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE)
To: Crouse R
TOLEDO EDISON CO.
Shared Package
ML20129B621 List:
References
NUDOCS 8507150547
Download: ML20129B616 (2)


See also: IR 05000346/1985017

Text

UNITED STATES

E o NUCLEAR REGULATORY COMMISSION

g*  :: E WASHINGTON, D. C. 20555

\**.../ June 26, 1985

Docket No. 50-346

Toledo Edison Company

ATTN: Mr. Richard P. Crouse

Vice President, Nuclear

Edison Plaza

300 Madison Avenue

Toledo, Ohio 43652

Gentlemen:

Enclosed is the report of the inspection performed at Davis-Besse by Messrs.

E. T. Baker and J. J. Petrosino, and Ms. N. J. Miegel of the Vendor Program Branch

on March 11-15, 1985. The purpose of the inspection was to determine if technical

information regarding factory recommended maintenance and operation related to

emergency diesel generators, reactor trip breakers, auxiliary feedwater steam

turbine, DC battery racks, Pacific Scientific Snubbers, and Ruskin Fire dampers

was being reviewed and implemented effectively. The inspectors reviewed documents

and activities authorized under the provisions of NRC License No. NPF-3, and

discussed their findings with the plant staff members identified in Report

Section 1, Details. The findings demonstrate a weakness in evaluation and

implementation of manufacturers' recommendations and a failure to communicate

with the manufacturers prior to making design changes.

The Inspection Report contains one finding related to reviewing, evaluating, and

implementing vendor supplied documentation that may result in enforcement action.

Resolution of the Potential Enfore ment Finding will be handled by the NRC

Region III office. Further, there are two Unresolved Items and one Open Item

that require additional information before further action (if any) can be taken.

NRC Region III will handle resolution of these items.

In accordance with 10 CFR 2.790(a), a copy of this letter and the enclosed

Inspection Report will be placed in the NRC Public Document Room.

The responses directed by this letter are not subject to the clearance procedures

of the Office of Management and Budget as required by the Paperwork Reduction

Act of 1980, PL 96-511.

,

For18 M SINE

Original document not available tM

B507150547 850626 Certified byM1AAA-t-  %

PDR ADOCK 05000346 o

G PDR: ,

T

o .-

. .

Toldeo Edison Company -2- June 26, 1985

Should you have any questions concerning this matter, we would be pleased to

discuss them with you.

Sincerely, l

ORIGWAl SIGNED BY:

GARY G. ZECH

Gary G. Zech, Chief

Vendor Program Branch

Division of Quality Assurance, Vendor

and Technical Training Center Programs

Office of Inspection and Enforcement

Enclosure:

Inspection Report No. 50-346-85-017

DISTRIBUTION:

DCS , 4pg{

VPB Reading

DQAVT Reading

RVollmer

GHolahan, NRR

EMerschoff

EBaker

JPetrosino

NMiegel

  • SEE PREVIOUS PAGE FOR CONCURRENCE.

VPB:DQAVl* VPB: 0QAVT* VPB:DQAVl* SC/VPB:DQAVT* 8 PB:0QAVT . AVT

EBaker: sam NMiegel JPetrosino EMerschoff ech Grimes

5/ 1785 5/13 /85 5/16 /85 5/16 /85 /gD/85 //9/85