ML20128M405

From kanterella
Jump to navigation Jump to search
Ack Receipt of Informing NRC of Steps Taken to Correct Violations Noted in Insp Repts 50-250/84-23 & 50-251/84-23.Violation 4.a Occurred as Stated.Written Response Requested within 30 Days of Ltr Date
ML20128M405
Person / Time
Site: Turkey Point  NextEra Energy icon.png
Issue date: 06/25/1985
From: Walker R
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
To: Williams J
FLORIDA POWER & LIGHT CO.
References
NUDOCS 8507110704
Download: ML20128M405 (4)


See also: IR 05000250/1984023

Text

okl

-

,

.

JUN 251985

Florida Power and Light Company

ATTN: Mr. J. W. Williams, Jr.

Group Vice President

Nuclear Energy Department

P. O. Box 14000

Juno Beach, FL 33408

Gentlemen:

SUBJECT: REPORT NOS. 50-250/84-23 AND 50-251/84-24

Thank you for your response of November 21, 1984, to our Notice of Violation

issued on October 11, 1984, concerning activities conducted at your Turkey Point

facility.

We have evaluated your response to Violations 1, 2, 3 and 4.c and

found that it meets the requirements of 10 CFR 2.201.

We will examine the

implementation of your corrective actions during future inspections.

A careful review of the basis for your denial of portions of Violation 4,

subsections 4.a and 4.b., and your denial of the additional example of Violation

250/84-09-10 and 251/84-09-10 has been conducted.

With respect to subsection 4.b, we agree with your position concerning one of the

several examples (Ametek pump) as described in the enclosure to this letter.

Though the item is no longer considered to be an example of Violation 4.b, the

storage of uncalibrated equipment in the same location as calibrated equipment,

along with related aspects of the maintenance program, is designated as an

Unresolved Item (250/84-23-08 and ?.51/84-24-08) pending further NRC inspection.

With respect to the additional example of a previously cited Violation

(250/84-09-10 and 251/84-09-10), we agree with your position that this is an

original design deficiency.

Please provide a supplemental response addressing

what review is being done or has been done to assure that similar design

deficiencies have not occurred in the routing of power to miscellaneous relay

rack equipment which may require safety-related power sources.

This subject is

identified as an Inspector Followup Item (250/84-23-09 and 251/84-24-09).

With respect to subsection 4.a of Violation 4, we have concluded, for reasons

presented in the enclosure to this letter, that the violation occurred as stated

in the Notice of Violation.

Therefore, in accordance with 10 CFR 2.201(a),

please submit to this office within 30 days of the date of this letter a written

statement that, for subsection 4.a of Violation 4, describes the corrective steps

which have been taken and the results achieved, the corrective steps which will

be taken to avoid further violations, and the date when full compliance will be

-achieved.

8507110704 850625

PDR

ADOCK 05000250

G

PDR

,j

--

JUN 251985

-

.

Florida Power and Light Company

2

We appreciate your cooperation in this matter.

Sincerely,

Original Signed by

Roger D. Walker

Roger D. Walker, Director

Division of Reactor Projects

Enclosure:

Staff Evaluation of I.icensee Response

dated November 21, 1984

cc w/ enc 1:

C. M. Wethy, Vice President

Turkev "oint Nuclear Plant

C. J

r, Plant Manager

TL,

oint Nuclear Plant

R. J. . ssta, Plant QA Superintendent

bec w/ enc 1:

NRC Resident Inspector

Document Control Desk

State of Florida

RII -

RII

RII

RII

RII.

h

Qly

c

v

G LFck:dr

frS

d

VBrownlee

CUpr ght

GJenk ns

3

6/ )/85

6/g85

6/Jo/85

6

85

6/7l/85

3

l

!

, _ _ _

.-

- _ . _ _

. . - .

.

.

-

-

_

-

em

,

.

JUN 2519es

ENCLOSURE

STAFF EVALUATION OF LICENSEE

RESPONSE DATED NOVEMBER 21, 1984

Staff Evaluation of the Partial Denial of Violation 4.b.

The licensee made the following statement in the partial denial:

"FPL denies

part of the finding because Ametek pressure pumps do not require calibration and

as such are not part of the Instrument and Control Calibration Program."

,

~

After additional inspection in this area, we agree that the pump is not on a

l

calibration schedule but is on a preventive maintenance schedule and that it was

used beyond the maintenance expiration date.

This item has been deleted as an

example to subsection 4.b of Violation 4.

The storage of uncalibrated equipment

1

in the same location as calibrated equipment is designated as an Unresolved Item

(250/84-23-08 and 251/84-24-08) pending further NRC inspection.

Additionally,

j

further inspection will be conducted into the preventive maintenance program and

,

will be addressed in future inspection reports.

t

Staff Evaluation of the Denial of an Additional Example of Previous Violation

'

250, 251/84-09-10

'

The licensee made the following statement in the denial:

"FPL denies the finding

because the control circuitry for pressure controllers PC-600 and PC-601 was part

i

of the original design of the plant and that design provided power for both

relays from the same non-vital source.

This is a design deficiency and not

another example of an incorrectly classified PC/M [ Plant Change / Modification].

This deficiency was processed under the provisions of 10 CFR Part 21 and our QA

requirements, and was reported to the NRC under 10 CFR 50.72 and 50.73. A PC/M

.

(84-132, Unit 3 and 83-133, Unit 4), classified as nuclear safety-related, has

been developed to provide separate and redundant Class 1E feeds to each control

relay to correct this design deficiency as described in Licensee Event Report

(LER) 250-84-018."

This item was an example of a previous violation which addressed classifying

design changes as non-safety-related when they were safety-related.

It was

maintained that the 10 CFR 21 report on pressure controllers PC-600 and PC-601

addressed an original design deficiency.

We concur in that determination;

however, the licensee should provide a supplemental response addressing what

review is being done or has been done to assure that similar design deficiencies

have not occurred in the routing of power to miscellaneous relay rack equipment

which may require safety-related power sources.

Staff Evaluation of the Partial Denial of Violation 4.a

The licensee made the following statement in the partial denial: "FPL denies the

j

discrepancy of the pressurizer heater bypass switches not being labeled.

FPL

denies part of the finding because discussions with start-up personnel confirmed

that the walkdown of PC/M 81-30 had been performed on May 23, 1984, and the label

!

_-

.

-

_ _ _ , _ _ _ _ _

_ _.. ___ _ ___,__

_ _

. _ . _ _ , _ _ _ _ _

_ _ _ . _ _ _ _ . . _ .

_

_

_

__

JUN 251985

,

Enclosure

2

1

was found on the switch at that time.

The label described the PC/M required

(Normal - Emergency) settings and it was installed as such."

Response 2.b to subsection 4.a of Violation 4 implies that start-up personnel

accompiished what procedure AP 0103.17 intended when on May 23, 1984, they

confirmed that the pressurizer heater lockout bypass switch position label

(Normal - Emergency) was installed on Unit 4 as PC/M 81-30 required.

The

response does not address PC/M 81-29, which is for Unit 3, but does state that

.

when the lack of information on the labels was identified by the NRC inspector

'

that temporary lables were installed to indicate the function of the switches.

Prior to this, the Unit 3 switches had no labels or visible identification at

all.

Inherent in the labeling process are the requirements to adequately identify the

component to a drawing and/or a procedure. There are two effective requirements

to which the FPL quality assurance program (FPL-NQA-100A) has committed.

The

first is that a component's identity be maintained from receipt to installation

and be in accordance with drawings, equipment lists, specifications and

established procedures (Regulatory Guide (R.G.) 1.116 and ANSI N45.2.8,

Section 3.2, Identification, and Section 5, Installed Systems Inspection and

Test).

These requirements must be met by appropriate tags / labels adequate to

relate to purchase specifications and operating drawings and procedures.

The

second requirement is that a continuing program of inspection be conducted of

activities affecting safety to verify (conformance with applicable documented

instructions, procedures and drawings

R.G 1.28 and ANSI N45.2, Section 2).

This, in turn, requires that the operating staff be provided sufficient component

identification labeling to comply with the applicable documents.

We conclude that labels to identify the components were not specified by either

PC/M (81-29 or 81-30), and that start-up personnel who were charged with the

responsibility for the walkdown of the system to identify discrepancies did not

initiate corrective action for the inadequate switch labeling.

We have evaluated the licensee's response to Violation 4.a, and found that it

does not meet the requirements of 10 CFR 2.201.

Therefore, the licensee should

respond to the original violation and submit a supplemental response to this

violation addressing:

(1) why the design change review process did not correct

the inadequate labeling discrepancy; and (2) what controls are in place to assure

that components are properly labeled or otherwise identified such that each

component can be properly operated and readily traced to drawings and procedures.

References:

R.G. 1.116-1976 (modifies ANSI N45.2.8-1975)

QA Requirements for Installation and Testing of

Mechnical Equipment and Systems

R.G. 1.28-1972 (modifies ANSI N45.2-1971)

QA Program Requirements.