May 21, 1985 Docket No. 50-160 Dr. R. A. Karam, Interim Director Neely Nuclear Research Center School of Nuclear Engineering-and Health Physics Georgia Institute of Technology Atlanta, Georgia 30332
Dear Dr. Karam:
SUBJECT:
EXTENSION OF DATE FOR IMPLEMENTATION OF EMERGENCY PLAN In response to your letter dated May 7,1985, requesting an extension of time to complete the implementation of your emergency plan, we find your request acceptable and grant the extension of time until October 14, 1985.
However, you must assure yourself that any significant modifications to your facility do not decrease the effectiveness of the plan that we have reviewed and approved.
If you have further questions, please contact Robert E. Carter, our Project Manager for your facility at 301-492-9795.
Sincerely, Original signed by Cecil n. Thomas, Chief Standardization and Special Projects Branch Division of Licensing cc: See next page DISTRIBUTION
< Docket: File.Q Region II SSPB Reading DMatthews RCarter PAnderson HBerkow CThomas
- tm n
w 05/M/85 05$ /85 05/3)/85 05g//85 0
g
e%
y/
- }y UNITED STATES g
NUCLEAR REGULATORY COMMISSION t
WASHINGTON, D. C. 20555 k..... p i
May 21, 1985 Docket No. 50-160 Dr. R. A. Karam, Interim Director Neely Nuclear Research Center School of Nuclear Engineering and Health Physics Georgia Institute of Technology Atlanta, Georgia 30332
Dear Dr. Karam:
SUBJECT:
EXTENSION OF DATE FOR IMPLEMENTATION OF EMERGENCY PLAN In response to your letter dated May 7, 1985, requesting an extension of time to complete the implementation of your emergency plan, we find your request acceptable and grant the extension of time until October 14, 1985.
However, you must assure yourself that any significant modifications to your facility do not decrease the effectiveness of the plan that we have reviewed and approved.
If you have further questions, please contact Robert E. Carter, our Project Manager for your facility at 301-492-9795.
Sincerely, AbAC. w
- m : :*-
Cecil 0. Thomas, Chief Standardization and Special Projects Branch Division of Licensing cc: See next page F
.=
. e Georgia Institute of Technology 50-160 Office of Planning and Budget f
Room 615B 270 Washington Street, S. W.
Atlanta, Georgia 30334 Mayor 'of City of Atlanta Atlanta, Georgia 30301 Attorney General Law Department 132 Judicial Building Atlanh, Georgia 30334 j
l i
J C