Application for Amends to Licenses DPR-39 & DPR-48,revising Tech Specs Re Reactor Protection Instrumentation & Logic Per Requirements of Generic Ltr 83-28.Fee Paid
ML20128D911
Person / Time
Site: Zion  File:ZionSolutions icon.png
Issue date: 03/25/1985
From: Cascarano R
COMMONWEALTH EDISON CO.
To: Harold Denton
Office of Nuclear Reactor Regulation
Shared Package
ML20128D918 List:
References
9913N, GL-83-28, NUDOCS 8507050216
Download: ML20128D911 (2)


Text

_ _ _ _ _

Commonw=lth Edison O one First National Plaza, Chicago. Illinois Address Reply to: Post Office Box 767 Chicago, Illinois 60690 March 25, 1985 Mr. Harold R. Denton, Director Office of Nuclear Reactor Regulation U.S. Nuclear Regulatory Commission Washington, DC 20555

Subject:

Zion Nuclear Power Station Units 1 and 2 Proposed Amendment to Facility Operating License Nos. DPR-39 and DPR-48 NRC Docket Nos. 50-295 and 50-304

Reference:

January 23, 1985 letter from S. A. Varga to D. L. Farrar.

Dear Mr. Denton:

Attachment 1 to this letter is a proposed amendment to Facility Operating License Nos. DPR-39 and DPR-48, Appendix A, Section 3.1 - Reactor Protection Instrumentation an'j Logic for your staff's review and approval. The proposed amendment statisfies a requirement of Generic Letter 83-28 as addressed in the referenced letter. The revised Technical Specifications, with changes indicated in the margins, have been prepared based on the license in effect following Amendment Nos. 87 and 77 to DPR-39 and DPR-48, respectively.

The plant modification being incorporated in the Technical Specifications by the proposed amendment is scheduled to be installed during the Unit 1 refueling outage which started January 30, 1985 and 1985.

the Unit 2 refueling outage scheduled to commence September 5, The effective date of the proposed amendment should be no earlier than 60 days from the date of issuance or modification operation authorization approval, whichever is later, to permit adequate time for implementation of necessary procedure changes.

Attachment 2 to this letter is a demonstration that the proposed amendment involves no siginificant hazards considerations.

The proposed amendment has received On-Site and Off-Site review and approval.

I ojk Y 0 h'O <#

pga7o:88aa888ajige i 'Po P

H. R. Denton March 25, 1985 A $150.00 fee remittance is enclosed in accordance with 10 CFR 170. As required by 10 CFR 50.91, the State of Illinois is being notified of this amendment request by transmittal of a copy of this letter and the attachments.

If there are any further questions regarding this matter, please contact this office.

Three (3) signed originals and thirty-seven (37) copies of this transmittal and its attachments are hereby provided for your review.

Sincerely,

/. m R. N. Cascarano Nuclear Licensing Administrator 1m cc: NRC Resident Inspector - Zion J. Norris - NRR G. Wright - IDNS Attachments to SUBSCRIBEDANDSWOpp>