Forwards Safety Evaluation of Util 831104 Response to Generic Ltr 83-28,Item 1.2 Re post-trip Review - Data & Info capability.Post-trip Review Data & Info Acceptable
ML20128C225
Person / Time
Site: Fort Calhoun Omaha Public Power District icon.png
Issue date: 06/13/1985
From: Butcher E
Office of Nuclear Reactor Regulation
To: Andrews R
OMAHA PUBLIC POWER DISTRICT
Shared Package
ML20128C228 List:
References
GL-83-28, NUDOCS 8507030512
Download: ML20128C225 (1)


Text

~

Juna 13, 1985 DISTRIBUTION:

Docket No. 50-285 t 6 ACRS +10 NRC PDR ABournia Local PDR RFroelich ORBf3 Rdg Mr. R. L. Andrews HThompson Division Manager, Nuclear Production OELD Omaha Public Power District EJordan 1623 Harney Street BGrimes Omaha, Nebraska 68102 JPartlow EGTourigny

Dear Mr. Andrews:

PMKreutzer

SUBJECT:

GENERIC LETTER 83-28, ITEM 1.2 - POST-TRIP REVIEW - DATA AND INFORMATION CAPABILITY We have completed our review of Post-Trip Review - Data and Information Capability for the Fort Calhoun Station, Unit No. 1. Our review was based on your November 4,1983 response to our July 8,1983 Generic Letter entitled -

" Required Actions Based on Generic Implications of Salem ATWS Events". As you know, we forwarded to you our draft Technical Evaluation Report on May 7, 1985 as prepared by our contractor, Science Applications International Corpo-ration. We also had a telephone conference on May 28, 1985 which focused on two incomplete areas. Based on our review of your November 4,1983 submittal and the telephone conference which was conducted on May 28, 1985 we have con-cluded that the post-trip review data and information capability for Fort Calhoun Station, Unit No. 1 is acceptable.

Our Safety Evaluation is enclosed.

Sincerely, Oylainal signed.by(

Edward J. Butcher, Acting Chief Operating Reactors Branch #3 Division of Licensing

Enclosure:

As stated cc w/ enclosure See next page 1

,,w, c a/a 23 -

G/o/6r ra7osom8'4h>

P