ML20127F379

From kanterella
Jump to navigation Jump to search
Provides Summary of Mgt Meeting on 921210 in Southport,Nc Re Restart Issues.List of Attendees,Summary & Slides Encl
ML20127F379
Person / Time
Site: Brunswick  Duke Energy icon.png
Issue date: 12/19/1992
From: Merschoff E
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
To: Watson R
CAROLINA POWER & LIGHT CO.
References
NUDOCS 9301200223
Download: ML20127F379 (24)


Text

..

o 7, c

C F i-t t-U ]

Docket Nos. 50-325, 50-324 f

i.1 J L' L

License Nos. DPR-71, DPR-62 Carolina Power and Light Company ATTN: Mr. R. A. Watson Senior Vice President Nuclear Generation P. O. Box 1551 Raleigh, NC 27602 Gentlemen:

SUBJECT:

MEETING

SUMMARY

- BRUNSWICK 1his refers to the management meeting conducted at NRC's request in the Brunswick Media Center in Southport, North Carolina, on December 10, 1992.

The purpose of the meeting was to discuss restart issues at Brunswick. A list of attendees, a summary, and a copy of your slides are enclosed.

It is our opinion that this meeting was beneficial in understanding the status of implementing your improvement programs. As mutually agreed, another such meeting (to be held in early January 1993) will be confirmed under separate correspondence.

In accordance with Section 2.790 of the NRC's " Rules of Practice," Part 2, Title 10. Code of Federal Regulations, a copy of this letter and its enclosures will be placed in the NRC Public Document Room.

Should you have any questions concerning this matter, please contact us.

Sincerely, Original signed by:

Jon R. Johnson /for Ellis W. Merschoff, Director l

Division of Reactor Projects

Enclosures:

1.

List of Attendees l

2.

Meeting Summary 3.

Licensee Slides cc w/encls:

R E. Morgan yg g n

~

Interim Plant Manager Brunswick Nuclear Project L

P. O. Box 10429 Southport, NC 28461 (cc w/encls cont'd - See page 2) l 9301200223 921219

-\\

PDR ADOCK 05000324 P

pon l

Y Carolina Power and Light Company 2

P'

! 9 ' 02 (cc w/encls cont'd)

H. Ray Starling Vice President - Legal Department Carolina Power and Light Co.

P. O. Box 1551 Raleigh, NC 27602 Kelly Holden Board of Commissioners P. O. Box 249 Bolivia, flC 28422 Chrys Baggett State Clearinghouse Budget and Management 116 West Jones Street Raleigh, NC 27603 Dayne H. Brown, Director Division of Radiation Protection N. C. Department of Environment, Health & Natural Resources P. O. Box 27687 Raleigh, NC 27611-7687 H. A. Cole Special Deputy Attorney General State of North Carolina P. O. Box 629 Raleigh, NC 27602 Robert P. Gruber Executive Director Public Staff - NCUC P. O. Box 29520 Raleigh, NC 27626-0520 Ms. Gayle B. Nichols Staff Counsel SC Public Service Commission P. O. Box 11649 Columbia, SC 29211 bec w/ encl:

(See page 3)

. a DIO i 9 W Carolina Power and Light Company 3

i i

bcc w/ enc 1:

j Document Control Desk H. Christensen, RII R. Lo, NRR NRC Resident inspector U.S. Nuclear Regulatory Commission l

Star Route 1, Box 208 Southport, NC 28461 l

I r

i V

i I

1' Ril:

Ril P:

RllpRP.

HChr stensen:tj DVerrelli

. JJohnson 12/ l /92 12/j /92

$/i'1/92 t

.2..

-.___.-_....._..,...,...._.a.,

u ENCLOSVRE 1 Carolina Power and Liaht Company l

W. Cavanaugh 111, President & C00 R. A. Watson, Senior Vice President, Nuclear Operations J. A. Dobbs, Special Assistant to Manager, Brunswick Nuclear Project R. E. Morgan, Interim Manager, Brunswick Nuclear Project M. J. Brown, Plant Manager, Unit 2, Brunswick A. M. Lucas, Vice President, Nuclear Engineering U. S. Nuclear Regulatory Commission S. D. Ebneter, Regional Administrator, Region 11,-(Rll)

W. T. Russell, Associate Director for Inspection and Technical Assessment, Office of Nuclear Reactor Regulation (NRR)

C. H. Berlinger, Chief, Electrical Engineering Branch, NRR G. C. Lainas, Assistant Director for Region 11 Reactors, NRR J. R. Johnson, Deputy Director, Division of Reactor Projects (DRP), Ril

-t E. G. Adensam, Director, Project Directorate (PD) 11-1 D. M. Verrelli, Chief, Reactor Projects Branch 1, DRP, RIl R. H. Lo, Project Manager, PD 11-1, NRR R. L. Prevatte, Senior Resident inspector - Brunswick, DRP, Ril J. J. Lenahan, Reactor Inspector, Materials and Processes Section, Division of Reactor Safety, RII K. M. Clark, Senior Public Affairs Officer, Ril

?

I

,,, -, _ -, _ ~, - - -, - -. -. - _.

-... _ - _... _ - _ _ - _ _, _. _. _.. _.. _ _ _, _ _. - _ _.. _ _ _ _ -. -. _ _.. ~. _ _ _

ENCLOSURE 2 t

Meeting Summary The Regional Administrator opened the meeting by stating that the NRC has received the Carolina Power and Light Company (CP&L) submittals for the Brunswick Unit 2 Integrated Restart Schedule and the Corporate Improvement initiatives.

He expressed concern with the lack of quantitative goals for those items that will not be 100 3ercent complete before restart.

CP&L's proposed readiness reviews of bot 1 cquipment and personnel which are described i

in the November 30, 1992, submittal need to be strengthened.

He requested that CP&L meet with the NRC after completion of their readiness reviews to present their results.

CP&L representatives provided an overview of the progress on the Unit 1 scope and schedule.

The system work logic has been defined and is being sequenced i

into the outage networks.

A definitive plan will be submitted by December 30, 1992.

The licensee emphasized that their commitments for restart of Unit 2 are contained in Appendix 3 to their July _ 23, 1992, submittal.

Discussion of the status of each item is contained in their November 30, 1992 letter. The licensee intends to conduct their readiness review by their Nuclear Assessment Department, and will use INPO to review select systems and to train Brunswick's personnel.

Inspections of the site's four Emergency Diesel Generators is continuing and will be performed sequentially and not in parallel.

Shutdown risk is being performed by a process comparable to NUMARC 91-06.

This will ensure defense in depth.

Changes to the scheduled work are assessed for risk prior to implementation. Diesel Generator No. 1 issues are being actively pursued.

Upon completion of repairs, the diesel will undergo break-in as well as a 13-day endurance run.

The backlog review of Short-term Structural Integrity (STSI) issues is continuing using the criteria specified in PN-30 to determine which items can be delayed until after restart.

However, the licensee indicated that all STSI issues will be completed by the end of the next Refueling Outage.

The validation of previous hotside/coldside_ walkdowns began on December 1.

1992.

The percent of revalidation will depend on the number of discrepancies identified and the licensee's evaluation of any operability question.

Walkdowns of the miscellaneous steel verification program are complete and components requiring repair are being corrected.

Building walls requiring repair will be completed by the end of January 1993.

During the closing remarks the Regional Administrator stated that the tour of l

the_ facility indicated _that progress was being made in rectifying deficient conditions.

He believed the-meeting to be very productive.

He suggested the next meeting be held in early January to maintain communications on the status of open issues. The next meeting agenda-should include as a minimum:

L l

lL-

Inclosure 2 2

1.

The scope and schedule for readiness review of both equipment and personnel; 2.

Quantified standards and goals for issues such as hot and cold side reverification, maintenance backlog and management; MOV testing program implementation, Corporate program to improve corrective actions and self-assessments.

I ENCLOSURE 3 I

AGENDA I

CP&UNRC Meeting On Brunswick Nuclear Project I

Thursday, December 10,1992 3:00 p.m. to 5:00 p.m.

1.

Opening Remarks NRC 3:00 I

CP&L I

II.

Unit 1 Integrated Startup Scope & Schedule l

  • Progress on Unit 1 Schedule Dobbs 3:15 l

Ill. Unit 2 Integrated Startup Scope & Schedule e General Overview / Key Milestones Brown 3:20

  • Startup Readiness Review
  • Progress of Major Activities

- Diesel Generator #1

- Backlog Review Cowan 3:45

- Miscellaneous Structural Steel Leininger 4:05

- Seismic Walls

'l IV. Tl tree Year Plan Overview Morgan 4:15 l

V.

Corporate improvement Plan Overview Watson 4:30 VI. Closing Remarks NRC CP&L I

I

h IMPROVEMENT PLANS g

I I

DELIVERABLE DA TE DUE STATUS I

INTEGRA TED STARTUP PLAN AND 11/30/92 SUBMITTED UNIT 2 SCHEDULE CORPORA TEIMPROVEMENT 11/30/92 SUBMITTED iNmAriveS BRUNSWICK THREE-YEAR PLAN 12/15/92 ON-SCHEDULE l

UNIT 1 INTEGRA TED STARTUP 12/30/92 ON-SCHEDULE SCHEDULE CNIP

[

UNIT 1 INTEGRA TED STARTUP SCHEDULE DEVELOPMENT I

l e UNIT 1 STARTUP SCOPE WAS SUBMITTED TO THE NRC ON NO VEMBER 30,1992 IN THE INTEGRA Tf!D STARTUP PLAN I

I e UNIT 1 SYSTEM WORK WINDOW LOGIC HAS BEEN DEFINED AND l

IS CURRENTL Y BEING SEQUENCED INTO THE OUTAGE NETWORK I

  • SEQUENCING OF CORRECTIVE AND PREVENTIVE MAINTENANCE, l

MODIFICATIONS, PROJECTS, AND TESTING IS IN PROGRESS I

e FINAL SCHEDULE REVIEW AND SITE MANAGEMENT SIGN-UP BY DECEMBER 28,1992

  • REVISION O TO BE APPROVED BY MANAGEMENT AND SUBMITTED TO THE NRC ON DECEMBER 30,1992 UllSSO

UNIT 2

[

INTEGRA TED STARTUP SCHEDULE

[

CRITICAL PA TH REMAINING DURA TIONS AS OF DECEMBER 10,1992 l

l

  • DIESEL INSPECTIONS 51 DA YS I
  • 4160V BUS / BREAKER WORK 4 DA YS I
  • CRD MAINTENANCE 13 DA YS I
  • SYSTEM CLOSEOUT / LINEUPS 21 DA YS
  • STARTUP/ SYNCHRONIZATION 9 DA YS TOTAL 108 DA YS 5

' l I

r I

l SHUTDOWN RISK ASSESSMENT I

I. CURRENT ASSESSMENTPROCESS

" GUIDELINES FOR INDUSTRY ACTION TO ASSESS l

SHUTDOWN MANAGEMENT" e PROCESS SPECIFICALL Y ENSURES DEFENSE IN DEPTH I

OF THE FOLLOWING SHUTDOWN SAFETY FUNCTIONS:

l

- DECA Y HEAT REMOVAL

- INVENTORY CONTROL l

- AC POWER AVAILABILITY

- REACTIVITY CONTROL l

- CONTAINMENT CONTROL l

e LOGIC CHANGES TO OUTAGE SCHEDULE ARE ASSESSED PRIOR TO SCHEDULE CHANGE I

e EXAMPLES OF POTENTIAL SCHEDULE CHANGES REQUIRit!G ASSESSMENTARE: CONCURRENTDIESEL GENERATOR WORK AND STARTING AUXILIARY TRANSFORMER LOGIC CHANGES I

I I

l

l r

L STARTUP READINESS PLAN I

I l

PRIOR TO UNIT 2 STARTUP:

  • EQUIPMENT AND SYSTEM READINESS l

- PN-30 PROCESS l

- ENCLOSURE 3 ITEMS (JUL Y 23,1992) l

  • STARTUP TESTING PLAN l

- SURVEILLANCE TESTING

- POST-MAINTENANCE TESTING l

SPECIAL TESTING I

I i

I STARTUP READINESS PLAN l

  • SELF-ASSESSMENT

- MANAGEMENT READINESS ASSESSMENT OF EACH UNIT PRIOR TO STARTUP l

- READINESS WILL COVER KEY PERFORMANCE AREAS:

COMMITMENTS I

OUTSTANDING CORRECTIVE ACTIONS ADVERSE CONDITION REPORTS I

PLANTMATERIAL CONDITION LIMITING CONDITIONS FOR OPERATIONS (LCO) l PERSONNEL PERFORMANCE EQUIPMENT TESTING RESULTS l

OUTSTANDING TEMPORARY CONDITIONS

- DURING STARTUP l

PERFORMANCE EVALUATION l

AUTHORIZE STARTUP ACTIVITIES TO CONTINUE SENIOR MANAGEMENT ON SHIFT I

e INDEPENDENT ASSESSMENTS

- NUCLEAR ASSESSMENT DEPARTMENT

-INPO I

I 1

c DIESEL GENERATOR

SUMMARY

L

[

[

I. DIESEL #1 ISSUES e FLEX DRIVE GEAR ALIGNMENT FRACTURED NO. 9 BEARING l

CRANKSHAFT STRAIGHTNESS

  • BROKENIDLER GEAR TEETH e OVERHEATED THRUSTRING l
  • DIESEL MOVEMENT ON THE FOUNDA TION ll. ACCEPTANCE TESTING l

e EDDY CURRENT TESTING

  • " BREAK-IN" RUNS
  • 13 DA Y ENDURANCE RUN l

Ill. PLANNED INSPECTIONS, DIESELS #2, #3, AND #4 l

  • BEARINGS
  • THRUSTRINGS e FLEX DRIVES

L BACKLOG REVIEW l

l I

Work Item Review Process (PN-30) l I

l

  • Work Item Status l

l

  • Validation of Previous Walkdowns to l

identify WorkItems l

1 l

SSCKREV

~

~

ss" D

WORK ITEM REWEW PROCESS

[

PN-30 l

l

  • ESTABLISHED THEINTEGRATED STARTUP SCHEDULE (ISS) INITIAL SCOPE l
  • REV 1 IMPROVES THE SYSTEM READINESS REVIEW PROCESS l
  • REV 1 PROGRAMMATICALLY TRANSITIONS FROM ISS SCOPE DEVELOPMENT TO ISS l

SCOPE CONTROL I

I I

l

wa sus i

ra n1 i

1 - t__;

l UNITS 1 AND 2 CORRECTIVE MAINTENANCE BACKLOG 12,000 11,000 10,000 9,000

,0

/

8,000 p/

O

/

7,000

/

O g,000

_. o.

- f 9_....

- o 0

, 9...... 0

~ ~

,/

k 5,000

'g/

- t k. _- - - - - B '

'g~.

/g' 4,000

'Y - L ~ ~ - - L _ ~ ' ' '~ - g

~

3,000

\\

y 2,000

/

-g 1,000

,/

0 y

i i

i 04/21 05/21 06/21 07/21 08/21 09/21 10/21 11/21 DA TE INITIATED COMPLETE TOTAL BACKLOG PRE 04/21

- -e - -

---B---

-a - -

cumoa

[

VALIDATION OF PREVIOUS WALKDOWNS l

  • WALKDOWNS CONSIST OF THREE PHASES --

EVALUATE EFFECTIVENESS ONGOING AND AT THE l

COMPLETION OF EACH PHASE l

  • TEAM COMPOSITION

- TEAM LEADER

- civil, MECHANICAL, ELECTRICAL PERSONNEL

- MINOR MAINTENANCE TEAM l

- JANITORIAL ASSISTANCE 1

e PHASE 1 BEGAN ON DECEMBER 'i,1992.

  • WALKDOWN STATUS

- APPROXIMATELY 450 ITEMS IDENTIFIED

- ONLY 2 POTENTIAL OPERABILITY QUESTIONS /

l IDENTIFIED - ACRs WRITTEN

- 28 ITEMS UNDER EVALUATION l

- REMAINING HA VE BEEN REPAIRED OR SCHEDULED e OPERABILITY QUESTIONS

- SUPPORT OF 1 INCH CARBON DIOXIDE LINE

- 1 CONDUIT SUPPORT SPAN VALIDMV

MISCELLANEOUS STEEL VERIFICATION PROGRAM L

l.

UNIT 2 STARTUP STATUS

  • ENGINEERING IN FINAL STAGE OF COMPLETION l

- WALKDOWNS - 100% COMPLETE (9,728 COMPONENTS)

- EVALUA TIONS - 98% COMPLETE (3,798 COMPONENT l

lRREGULARITIES)

- PLATFORM ANALYSES - 95% COMPLETE I

  • RESULTS TO DATE l

545 COMPONENTS REQUIRING ACTION

- 357 MAINTENANCE l

- 103 INDUSTRY PRACTICE

- 85 RESTORE DESIGN MARGINS

- 0 OPERABILITYISSUES

  • PHYSICAL REPAIRS IN PROGRESS / SCHEDULED FOR g

l COMPLETION BY FEBRUARY 1,1993 II.

UNIT 1 STARTUP STATUS

- WALKDOWNS - 68% COMPLETE (8,037 COMPONENTS)

- EVALUA TIONS - JUST BEGUN MSVPU1U2

3 BUILDING WALLS I

STA TUS (12-02-92) l l

e Two hundred forty-four (244) walls in Class I Structures were inspected and reviewed e Fifty-one (51) walls were reclassified as l

safety-related I

  • Sixty-one (61) walls required modification l

- 52 to meet seismic requirements 3 to meet tornado requirements 6 to meet seismic and tomado requirements l

e Of the 61 walls, 38 have been modified and l

declared operable and the remaining 23 are in various stages of design, construction, l

inspection, and as built design verification e Remainder are scheduled to be completed by the end of January BWSTA12

7

[

[

THREE YEAR PLAN OVERVIEW

[

e VISION-ORIENTED STRATEGY

~

l

- SITE OWNERSHIP e PLANT & PEOPLEIMPROVEMENTS I

  • MANAGEABILITY l

l e STANDARDS / PLANNING / ACCOUNTABILITY I

e 1993 DETAILS I

l

  • EVALUATE ACHIEVEMENT / ADJUST I

e UPDATE FALL 1993 I

e COMMITMENT EXPECTATIONS

  • DYNAMIC COMMUNICATIONS 3YWtSUAf

's i

i IMPROVEMENT PLANS g

I

-l l

DEllVERABLE DA TE DUE STA TUS I

INTEGRA TED STARTUP PLAN AND 11/30/92 SUBMITTED UNIT 2 SCHEDULE CORPORA TEIMPROVEMENT 11/30/92 SUBMITTED INITIA TIVES BRUNSWICK THREE-YEAR PLAN 12/15/92 ON-SCHEDULE l

UNIT 1 INTEGRA TED STARTUP 12/30/92 ON-SCHEDULE l

SCHEDULE I

I I

g g

I

CAROLINA POWEli & LIGHT COMPANY

}

CORPORATEIMPROVEMENTINITIATIVES e ORGANIZATIONAL STUDY e NUCLEAR SAFETY REVIEW PROGRAM ENHANCEMENTS I

e NUCLEAR SAFETY ORIENTA TION AND CONTINUOUS IMPROVEMENT I

e PEER GROUP PROGRAM IMPLEMENTATION e SUPERVISORY ASSESSMENT CENTER IMPLEMENTA TION e SUPERVISORY DEVELOPMENT PROGRAM COMPLETION l

  • MANA GEMENT DEVELOPMENT / SUCCESSION PLANNING PROGRAM IMPLEMENTATION I

e TECHNICAL TRAINING PROGRAM DEVELOPMENT I

e INTEGRATED SCHEDULE PROGRAM DEVELOPMENT e WORK PLANNING AND CONTROL PROCESS IMPROVEMENTS

  • BACKLOG REDUCTION PLAN DEVELOPMENT l

e HOUSEKEEPING AND MATERIAL CONDITIONIMPROVEMENTS

_ _ _ _ _ ~ - _ _ _ _ _ _ _ _. _ _ _ _ _ _ _ __

~

0

SUMMARY

  • UNIT 2 START-UP SCHEDULED FOR MARCH 28,1993
  • UNIT 1 START-UP SCHEDULE TO BE DEVELOPED

~

BY YEAR-END

  • BRUNSWICK'S THREE-YEAR PLAN FOR PREMIER, WORLD-CLASS PERFORMANCE WILL BE SUBMITTED DECEMBER 15,1992
  • CORPORATEIMPROVEMENTINITIATIVES WILL RAISE STANDARDS AND LEVELS OF PERFORMANCE A T ALL NUCLEAR STATIONS
  • CORPORA TE MANAGEMENT AND BRUNSWICK EMPLOYEES ARE COMMITTED TO THE SUCCESS OF THESE PLANS

SUMMARY

.