Notifies of 850717 Meeting in King of Prussia,Pa to Hear Util Recirculation Sys Pipe Replacement Presentation. Schedule & Agenda Encl
ML20126J367
Person / Time
Site: Vermont Yankee File:NorthStar Vermont Yankee icon.png
Issue date: 06/04/1985
From: Wenzinger E
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
To: Wittmer W
VERMONT YANKEE NUCLEAR POWER CORP.
References
NUDOCS 8506100567
Download: ML20126J367 (4)


Text

_

f_r ,a g

JUN 0 41985 Docket No. 50-271

~s,

' Vermont Yankee Nuclear Power Corporation

~

ATTN: Mr. W. L. Wittmer Project Manager Recirculation System Pipe Replacement Project RD 5, Box.169 Ferry Road Brattleboro, Vermont 05301 Gentlemen:

Subject:

Schedule and Agenda for Vermont Yankee Recirculation System Pipe Replacement Presentation at Region I Office Pursuant to our previous conversations, the subject meeting is scheduled for Wednesday, July 17, 1985 at 9:00 a.m. in the Main Conference Room, NRC Region I Headquarters, 631 Park Avenue, King of Prussia, Pennsylvania.

-Please be prepared to discuss the items on the enclosed agenda. The agenda has been revised to incorporate comments by NRC staff on the May 9 draft agenda.

Further revision may be necessary pending NRC review of the Vermont Yankee radi-ation protection program description submittal on June 1, 1985. If we need infor-mation.in addition to that outlined on the enclosed agenda, we will inform you by July 3, 1985.

If you have any questions regarding this matter, please contact F. A. Casella of my staff. Your cooperation with us is appreciated.

Sincerely, yriginalSigned Byj u>so -J Edward C. Wenzinger, Chie Projects Branch No. 3 ,

Division of Reactor Projects j

Enclosure:

Agenda for July 19, 1985 Vermont Yankee Recirculation System Pipe Replacement Presentation 8506100567 85060 7g

        • =

St= 3/ 1 i

m --

r. ,-
t. .

Vermont-Yank'ee' Nuclear Power 2 Corporation JUN 0 41985 l 1

cc w/ encl:

Mr. W. P. Murphy, Vice President and 'ianager of Operations Mr. R. W. Capstick, Licensing Enginear LMr. W. F...Conway, President and Chiat Executive Ott1cer Mr. J. P. 'Pelletier, Plant Manager Mr. Donald Hunter, '_Vice President -

-Mr. Cort Richardson, Vermont Public interest Research Group, Inc.

Public Document _ Room (PUK)

Local'Public Document Room (LPUR)

Nuclear Safety information Center-(NSIC)

NRC Resident Inspector

-State of-New Hampshire State of Vermont P.-Paul, Vermont Public Service Department

~bcc w/ encl:

Region-l Docket Room (with concurrences)

Senior 0)erations Otticer (w/o encis)

Section ;hiet, URP R. W. Starosteck1,;R1 S. D. Ebneter R1 W.F.Kane,RI G. W. Meyer, R1 V.'L. Roone PM, NRR J. P. Durr,y,1R

-E. H. Gray, R1 W. S. Pasciak, R1 H. J. Bicehouse, R1

-Rl: P ,

R P R P lla/meo 1p n in r

(,

S/30/8b . [g g j p 0FFIC AL RECURD COPY

f:

_r -7 AGENDA FOR JULY 19, 1985 VERMONT. YANKEE RECIRCULATION SYSTEM PIPE REPLACEMENT PRESENTATION AT NRC REGION I HEADQUARTERS

-1. ORGANIZATION a; Division of Work

b. Control of Contracts

-2. INTERFACE CONTROL ,

a. Design-
b. Construction
c. Field Change Process
3. QUALITY ASSURANCE
a. Design
b. -Construction
4. DESIGN DESCRIPTION
a. Codes and Standards
b. Pipe Analysis Procedures
c. Inspection Allowances
d. Materials Used for Replacement Piping
e. Welding Equipment
f. NDE (PT, RT,' UT, VT)

.5. ALARA

a. Organization
b. Implementation Plans
c. Person-Rem Estimates
d. Mitigating Measures to Reduce Radiation Exposures
e. Job Control in High Radiation Areas
f. Storage Plan for Equipment That Is To Be Reinstalled
g. -Temporary Ventilation Design and Effects on Permanent System >

b

6. TRAINING PLANS
a. Mock-ups h
b. Welder Source  !
c. Welder Qualifications
7. PLANT PREPARATION - REMOVAL OF INTERFERENCES
8. DECONTAMINATION
a. System Configuration
b. Waste Removal and Disposal
c. Process Chemistry

-[ _ ,h h 2

i9. WORK' DESCRIPTION / DETAILS-a.. Current Schedule and Sequence

b. Preparation of Work Controlling Documentation (Travellers) (who will do, who will review)-
c. Control of. Records
10. :0LD PIPE DISPOSAL

-11. PLANTL RESTORATION - REPLACEMENT OF ' INTERFERENCES

12. PREOPERATIONAL TESTING AND INSPECTION
a. PSI-
b. HYDRO
13. SECURITY-
14. ~ HOUSEKEEPING