Letter Sequence RAI |
|---|
|
Results
Other: AECM-83-0146, Forwards Response to Five of Six Items Contained in Re Util Work Addressing Containment Issues.Evaluation of Condensation Oscillation Loads Produced by Discharges from RHR HX Relief Valve Will Be Completed by Late Apr, AECM-84-0443, Forwards Approach to Chugging,Assessment of RHR Steam Discharge Condensation Oscillation in Mark III Containments, Per 830323 Commitment.Ae Evaluation Will Be Completed by mid-Dec 1984, AECM-85-0018, Forwards Evaluation of RHR Relief Valve Condensation Oscillation Loads on Structures & Piping.Info Demonstrates That All Loads Which Could Be Produced by Actuation of RHR HX Relief Valves Acceptable, AECM-85-0046, Provides Basis That Weir Wall Overflow Following Postulated Inadvertent Upper Containment Pool Dump Does Not Involve Significant Safety Problem.Evaluation Plans & Justification Provided, AECM-85-0233, Forwards Weir Wall Overflow Probability Analysis. Because of Very Low Probability of Occurrence & Leak of Safety Significance for Worst Case Postulated Overflow (Ref AECM-85/0046),corrective Actions Not Warranted, AECM-85-0376, Submits Info Re Wier Wall Overflow,Per 851021 Request.Topics Addressed Include Overflow Effect Upon Uninsulated Drywell Piping & Evaluation of Recirculation Piping Relative to Predicted Water Level.Ge Rept Re Containment Issue Encl, AECM-86-0143, Clarifies Planned Resolution of Possible Loads from Chugging Caused by Steam & Gas Venting Into Suppression Pool Through RHR Relief Valve Discharge Line.Rhr HX Vent Line Header Will Have Dedicated Discharge Line to Pool, ML20097F052, ML20137Q230, ML20204J145
|
MONTHYEARAECM-83-0146, Forwards Response to Five of Six Items Contained in Re Util Work Addressing Containment Issues.Evaluation of Condensation Oscillation Loads Produced by Discharges from RHR HX Relief Valve Will Be Completed by Late Apr1983-03-23023 March 1983 Forwards Response to Five of Six Items Contained in Re Util Work Addressing Containment Issues.Evaluation of Condensation Oscillation Loads Produced by Discharges from RHR HX Relief Valve Will Be Completed by Late Apr Project stage: Other ML20137Q2301983-07-31031 July 1983 Containment Issue Isolation Transient Project stage: Other ML20097F0521984-03-31031 March 1984 Approach to Chugging,Assessment of RHR Steam Discharge Condensation Oscillation in Mark III Containments Project stage: Other AECM-84-0443, Forwards Approach to Chugging,Assessment of RHR Steam Discharge Condensation Oscillation in Mark III Containments, Per 830323 Commitment.Ae Evaluation Will Be Completed by mid-Dec 19841984-09-0707 September 1984 Forwards Approach to Chugging,Assessment of RHR Steam Discharge Condensation Oscillation in Mark III Containments, Per 830323 Commitment.Ae Evaluation Will Be Completed by mid-Dec 1984 Project stage: Other AECM-85-0018, Forwards Evaluation of RHR Relief Valve Condensation Oscillation Loads on Structures & Piping.Info Demonstrates That All Loads Which Could Be Produced by Actuation of RHR HX Relief Valves Acceptable1985-01-24024 January 1985 Forwards Evaluation of RHR Relief Valve Condensation Oscillation Loads on Structures & Piping.Info Demonstrates That All Loads Which Could Be Produced by Actuation of RHR HX Relief Valves Acceptable Project stage: Other AECM-85-0046, Provides Basis That Weir Wall Overflow Following Postulated Inadvertent Upper Containment Pool Dump Does Not Involve Significant Safety Problem.Evaluation Plans & Justification Provided1985-02-25025 February 1985 Provides Basis That Weir Wall Overflow Following Postulated Inadvertent Upper Containment Pool Dump Does Not Involve Significant Safety Problem.Evaluation Plans & Justification Provided Project stage: Other ML20126J2671985-06-11011 June 1985 Forwards Request for Addl Info Re Steam Condensing Mode of RHR Sys.Info Requested by 850715 Project stage: RAI AECM-85-0287, Responds to NRC 850611 Request for Addl Info Re Steam Condensing Mode.Listed Methods for Predicting Chugging Will Be Evaluated.Evaluation Scheduled for Completion by 8512201985-09-13013 September 1985 Responds to NRC 850611 Request for Addl Info Re Steam Condensing Mode.Listed Methods for Predicting Chugging Will Be Evaluated.Evaluation Scheduled for Completion by 851220 Project stage: Request AECM-85-0233, Forwards Weir Wall Overflow Probability Analysis. Because of Very Low Probability of Occurrence & Leak of Safety Significance for Worst Case Postulated Overflow (Ref AECM-85/0046),corrective Actions Not Warranted1985-10-0404 October 1985 Forwards Weir Wall Overflow Probability Analysis. Because of Very Low Probability of Occurrence & Leak of Safety Significance for Worst Case Postulated Overflow (Ref AECM-85/0046),corrective Actions Not Warranted Project stage: Other AECM-85-0376, Submits Info Re Wier Wall Overflow,Per 851021 Request.Topics Addressed Include Overflow Effect Upon Uninsulated Drywell Piping & Evaluation of Recirculation Piping Relative to Predicted Water Level.Ge Rept Re Containment Issue Encl1985-11-27027 November 1985 Submits Info Re Wier Wall Overflow,Per 851021 Request.Topics Addressed Include Overflow Effect Upon Uninsulated Drywell Piping & Evaluation of Recirculation Piping Relative to Predicted Water Level.Ge Rept Re Containment Issue Encl Project stage: Other AECM-86-0012, Discusses Status of Util Activities in Response to NRC 850611 Request for Addl Info Re Review of Possible Condensation Oscillation Loads from Chugging. Dedicated Lines from RHR HX Noncondensible Vents Preferred Resolution1986-01-28028 January 1986 Discusses Status of Util Activities in Response to NRC 850611 Request for Addl Info Re Review of Possible Condensation Oscillation Loads from Chugging. Dedicated Lines from RHR HX Noncondensible Vents Preferred Resolution Project stage: Request AECM-86-0143, Clarifies Planned Resolution of Possible Loads from Chugging Caused by Steam & Gas Venting Into Suppression Pool Through RHR Relief Valve Discharge Line.Rhr HX Vent Line Header Will Have Dedicated Discharge Line to Pool1986-05-16016 May 1986 Clarifies Planned Resolution of Possible Loads from Chugging Caused by Steam & Gas Venting Into Suppression Pool Through RHR Relief Valve Discharge Line.Rhr HX Vent Line Header Will Have Dedicated Discharge Line to Pool Project stage: Other AECM-86-0175, Corrected Response to 860326 Request for Addl Info Re Listed Humphrey Concerns,Including Addl Submerged Structure Loads & Containment Open Area,Correcting Omission of Page 2 from Attachment 31986-08-14014 August 1986 Corrected Response to 860326 Request for Addl Info Re Listed Humphrey Concerns,Including Addl Submerged Structure Loads & Containment Open Area,Correcting Omission of Page 2 from Attachment 3 Project stage: Request ML20204J1451987-03-23023 March 1987 SER Supporting Licensee Responses to Humphrey Concerns on Safety of Mark III Containment Design Project stage: Other ML20204J1161987-03-23023 March 1987 Forwards SER Re Licensee Responses to Humphrey Concerns on Mark III Containment Design.Humphrey Concerns Satisfactorily Resolved.Licensee Will Continue to Prohibit Use of RHR Steam Condensing Mode Until Design Mods Implemented Project stage: Approval 1985-11-27
[Table View] |
Text
7 DISTRIBUTION:
i 5
E 9
g q
UNITED STATES RC R
g g
NUCL AR REGULATORY COMMISSION Local,PDR j
WASHINGTON, D. C. 20555 i
PRC S tem g
/
June 11, 1985 l
iDocket No. 50-416 Mr. Jackson B. Richard Senior Vice President, Nuclear Mississippi Power & Light Company
- P.O. Box 23054 Jackson, Mississippi 39205 De~ r Mr. Richard
a
Subject:
Grand Gulf Unit 1 - Request for Additional Information Regarding
~
Steam Condensing Mode of Residual Heat Removal (RHR) System The NRC staff is reviewing condensation oscillation loads which could result from steam discharges through the RHR relief valve discharge pipe when the RHR is. operating in the steam condensing mode.
Infonnation on these loads was prov.ided by Mississippi Power & Light Company letters dated March 23, 1983, September 7,1984 and January 24, 1985.
Additional information described in the enclosure is needed to complete our evaluation.
In order to meet the schedule for completion of this review, you are requested to provide the information identified in the enclosure by July 15, 1985.
If you cannot meet this date, you should advise the NRC Project Manager, L. L. Kintner, within 7 days of receipt of this letter.
The reporting and/or recordkeeping requirements contained in this letter affect fewer than ten responderits; therefore, OMB clearance is' not required under P.L.96-511.
Sincerely, Elinor G. Adensam, Chief Licensing Branch No. 4 Division of Licensing
Enclosure:
As stated cc:
See next page 8506180573 850611 PDR ADOCK 05000416 P
PDR
GRAND G LF Mr. Jackson S. Richard Senior Vice President, Nuclear Mississippi Pcwer & Light Carpany P.O. Box 23054 Jackson, Mississippi 39205 cc: Robert S. McGehee, Escuire The Honorable Willia: J. Guste, Jr.
Wise, Carter, Child, Steen and Caraway Attorney General P.O. Box 651 Departsent.of Justice Jackson, Mississippi 39205 State of Louisiana Baton Rcuge, Louisiana 70804 Nicholas S. Reynolcs, Esquire Bishop Liberman Ceak, Purcell Mr. Oliver.D. Kingsley, Jr.
and Reynolds Vice President, Nuclear Operations 1200 17th Stre at, % W.
Mississippi Power & Light Corpany Washington, D, C.
20036 P.O. Box 23054 Jackson, Mississippi 39205 Mr. Ralph T. t:lly Manager of Out: ity Assurance Middle South Services, Inc.
P.O. Box 61000 New Orleans, Louisiana 70161 Mr. Larry F. Dale, Director Nuclear Licensing and Safety Mississippi Power & Light Company P.O. Box,23054 3
. Jackson, Mississippi 39205 Mr. R. W. Jackson, Project Engineer Bechtel Power Corporation 15740 Shady Grove Road Gaithersburo, Maryland 20760 Mr. Ross C. Butcher Senior Resident Inspector U.S. Nuclear Regulatory Commission Route 2, Box 399 Port Gibson, Mississippi 39150 J. Nelson Grace, Regional Administrator
!!,S. Nuclear Regulatory Ccrmission, Aegion II 101 Marietta Street, N.W., Suite 2900 Atlanta, Georgia 30323 Mr. J. E. Cross, General Manager Grand Gulf Nuclear Station
. Mississippi Power & Light Caepany P.O. Box 756 Port Gibson, Mississippi 39150
Enclosura 5
REQUEST FOR ADDITIONAL INFORMATION
)
GRAhD GULF, UNIT 1 HUMPHREY CONCERN 3.0 1.
In Reference 1 ik is stated that "The heat exchangers in the Grand Gulf Nuclear Station (GGNS) Residual Heat Removal (RHR) ' Systems are each designed with vents at two locations on the steam side of the heat i-exchanger. The vents remove non-condensible gases which could collect in-4 the heat exchangers and. degrade their performance. When the RHR system is operating in the steam condensing mode, (SCM), these vents provide a small but continuous dump of steam to the suppression pool through the j
RHR heat exchanger relief valve discharge line. The flow rate of steam 4
through the relief valve discharge line is such that chugging could occur 4
in the pool as long as the RHR system operates in this mode." Therefore, either justify why chugging need not be considered during RHR operation in the steam condensing mode or. include these chugging cycles.in the development of the load specification.
i
.1 j
2.
.To estimate the corresponding lateral loads on the discharge line, MP&L employs the Mark II load methodology of Reference 2.
The Mark II lateral load methodo' logy of Reference 2 was modified by the NRC staff's acceptance criteria (Reference 3) to take into account the stochastic l
nature of the chugging phenomenon. The modification consists of an f
l i
l
+ adjustment to the design load amplitude, F, according to the relation F = - r in (P)
(1) where P is the exceedence probability of the load F and d-is an empirical constant derived from the pertinent data base. A detailed description of the basis for this modification and its derivation is provided in Reference 4.
Based on our evaluation of your submittal, it does not appear that.the NRC modification has been incorporated into the load specification.
Provide an amended a'alysis'which is consistent with the staff's
~
acceptance criteria or justify the apparent deviation.
- 3. ' Provide the number of chugs, and the basis for this value, that would be' experienced on the relief valve line during the life of the plant. Also include the value of exceedence probability described in que tion (2), if appropriate.
4.
Indicate if one or both RHR heat exchangers would be used during SCM operations.
4 5.
If the number of chugs considered for design exceeds 10, discuss how fatigue considerations have been included in the analysis.
The discussion should include not only the discharge line but any submerged structures that may experience loads due to the chugging at the vent exit.
i
~e
--~----'^"Y
~ ~ ' " ' ' " " '
. It is stated insReference 1 that the lohd on the discharge line is 6.
"... uniformly distributed over the bottom 4 feet of the discharge pipe exit." This seems to be an incorrect interpretation of the Mark II methodclogy which requires that the load be ' distributed uniformly over 1 to 4 feet of the downcomer end.
Secondly, the load should be scaled to pipe diameter. An acceptable approach would be to take the ring of application as i to 2 pipe diameters.from the discharge line exit.
Indicate if you plan to confonn to this Mark II methodology or provide justification for all deviations.
i 0
i i
I 4
0
-_.,.-._,_,..m.
m-.
,y y
o
REFERENCES:
6, dated March 23, 1983, from e, M L to Dn n 2.
av
,W
" Mark II Main Vent lateral Loads," GE Report NEDE-23806-P, 3.'
Anderson,' C., " Mark II Containment Program Load Evaluation and Acceptance Criteria,"~NRC NUREG-0808, 4.
Lehner, J.,
" Selected Evaluations of Mark II LOCA Loads Performed by BNL and its Consultants for the Mark II Generic Program," BNL NUREG/CR-2191,-
March 1982.
o t
M 1
I r
6 6
,,,.._,..----_,-.__,._.y
.,,._s.-__,
-