Forwards Environ Assessment & Finding of No Significant Impact Re One Time Schedular Exemption from Requirements of 10CFR50,App E
ML20126F320
Person / Time
Site: Trojan File:Portland General Electric icon.png
Issue date: 12/18/1992
From: Kokajko L
Office of Nuclear Reactor Regulation
To: Cross J
PORTLAND GENERAL ELECTRIC CO.
Shared Package
ML20126F324 List:
References
TAC-M85146, NUDOCS 9212300235
Download: ML20126F320 (3)


Text

{{#Wiki_filter:December 18, 1992 Rgdig g g dge {o December 29, 1992 Docket No. 50-344 Hr. James E. Cross Vice President and Chief Nuclear Officer Portland General Electric Company 121 S.W. Salmon Street Portland, Oregon 97204

Dear Mr. Cross:

SUBJECT:

ENVIRONMENTAL ASSESSMENT AND FINDING OF NO $1GNIFICANT IMPACT TROJAN NUCLEAR PLANT (TAC NO. M85146) Enclosed for your information is a co)y of an ' Environmental Assessment and Finding of No Significant Im)act." Tie Environmental Assessment relates to your application dated Decem>er 11, 1992, requesting a one time schedular exemption from the requirements of 10 CFR 50, Appendix E, (IV)(F)(2) for the Trojan Nuclear Plant. The Environmental Assessment has been sent to the Office of the Federal Register for publication. Sincerely, Original signed by Lawrence E. Kokajko, Senior Project Manager Project Directorate V Division of Reactor Projects Ill/IV/V Office of Nuclear Reactor Regulation

Enclosure:

DISTRIBullpj: As stated Docket File NRC & Local PDRs PDV Reading File JRoe cc w/ enclosure: MVirgilio TQuay See next page DFoster LKokajko SPeterson OGC, 15B18 EJordan, 3701 ACRS(10), P315 OPA, 2G5 PDV Plant File KPerkins, RV 0FC: LA/PDV PM/PDV V OGC D/PDV NAME: DFoster% SPetNon b W TQNy lKokajko (D O/ V N0 I 15 /\\f/iV DATE: /g//1/f2-l'L/n / % / // 0FFICIAL RECORD COPY DOCUMENT NAME:TJ85146.EA 0 30005i t y jd' = $k obh 0$0h0044 p PDR l

  • "'Nv Redistributed due to nec signature on EA o

.f NUCLEAR REQU TO OMMISSION cember 29. m 2 wAsHisa7oN, D.C. sages December 18, 1992 Docket No. 50-344 Mr. James E. Cross Vice President and Chief Nuclear Officer Portland General Electric Company 121 S.W. Salmon Street Portland, Oregon 97204

Dear Mr. Cross:

SUBJECT:

ENVIRONMENTAL ASSESSMENT AND FINDING OF NO SIGNIFICANT IMPACT TROJAN NUCLEAR PLANT (TAC NO. H85146) Enclosed for your information is a co)y of an " Environmental Assessment and Finding of No Significant Im)act." Tie Environmental Assessment relates to your application dated Decem)er 11, 1992, requesting a one time schedular exemption from the requirements of 10 CFR 50, Appendix E. (IV)(F)(2) for the Trojan Nuclear Plant. The Environmental Assessment has been sent to the Office of the Federal Register for publication. Sincerely, f -{ Gjs Lawrence E. Kokajko, Senior Project Manager Project Directorate V Division of Reactor Projects III/IV/V Office of Nuclear Reactor Regulation

Enclosure:

As stated cc w/ enclosure: See next page t-m

Mr. James E. Cross Portland General Electric Company Trojan Nuclear Plant cc: Senior Resident inspector U.S. Nuclear Regulatory Commission Trojan Nuclear Plant i Post Office Box 250 Rainier, Oregon 97048 Mr. Michael J. Sykes Chairman Board of County Comlssioners Columbia County St. Helens, Oregon 97501 Hr. David Stewart-Smith Oregon Department of Energy Salem, Oregon 97310 Regional Administrator, Region V U.S. Nuclear Regulatory Comission 1450 Maria Lane, Suite 210 Walnut Creek, California 94596 Mr. Tom Walt General Manager, Technical Functions Trojan Nuclear Plant 71760 Columbia River Highway Rainier, Oregon 97048 Mr. Lloyd K. Harbet 19142 S.E. Bakers Ferry Road Boring, Oregon 97009 Mr. Jerry Wilson Do it Yourself Committee 570 N.E. 53rd Hillsboro, Oregon 97124 Mr. Eugene Rosolie Northwest Environmental Advocates 302 Haseltine Building 133 S.W. 2nd Avenue Portland, Oregon 97204 Mr. Robert Pollard Union of Concerned Scientists 1616 P Street, Suite 310 Washington, DC 20036 l l}}