ML20126C416

From kanterella
Jump to navigation Jump to search
Ack Receipt of 841127 & s Informing NRC of Steps Taken to Correct Violations Noted in Insp Repts 50-313/84-29 & 50-368/84-29.SAR Separation Criteria Should Be Met W/O Reliance on Fire Barriers
ML20126C416
Person / Time
Site: Arkansas Nuclear  
Issue date: 06/10/1985
From: Hunter D
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
To: Jeffery Griffin
ARKANSAS POWER & LIGHT CO.
Shared Package
ML20126C420 List:
References
NUDOCS 8506140413
Download: ML20126C416 (6)


See also: IR 05000313/1984029

Text

h

.

.

In Reply Refer To:

JUN H 1985

Dockets:

50-313/84-29

50-368/84-29

Arkansas Power & Light Company

ATTN: John M. Griffin,

Senior Vice President -

Energy Supply

P. O. Box 551

Little Rock, Arkansas 72203

Gentlemen:

Thank you for your letters, dated December 27, 1984 and April 4, 1985, in

response to our letters, dated November 27, 1984 and March 5, 1985.

Your responses were discussed on May 7, 1985, in a meeting of our resident

inspectors with Mr. Lomax and other members of your staff.

In your letter dated December 27, 1984, you stated that although the plant

Safety Analysis Reports (SARs) mentian that solid cable tray covers are used

where minimum separation distances for fire protection are not satisfied, the

current fire hazards analysis submitted to the NRC in accordance with 10 CFR Part 50, Appendix R, takes no credit for the tray covers.

It should be noted that the separation requirements of Appendix R are based'on

large exposure fires while the separation requirements stated in your SARs are

based on fires initiated by faults and failures internal to the electrical

equipment or circuits, as is discussed in Regulatory Guide 1.75.

Also, the

separation criteria of Appendix R apply only to the electrical cabling required

for systems used for safe plant shutdown, while Regulatory Guide 1.75 and your

SARs contain separation criteria which are applicable to all redundant Class 1E

electrical cables.

Your letter of April 4, 1985, stated that AP&L has decided to delete or revise

portions of the Conduit and Cable Tray Notes and Details for clarification.

Prior to deleting your design requirements for cable tray covers and other

barriers, you should ensure that the separation criteria of your SARs are met

without reliance upon these barriers.

E

'

RPB2//

RPB2/ '

RPB

WJohnr)on:gb

LEMartin

DRHunter

'

4 // /85

4 ///85

6 / 1 /85

hb

ch

g()f

\\ \\

c

f

.

.

l-

L

Arkansas Power & Light Company

-2-

!

,

We have no further questions at this time and will review your corrective

action during a future inspection.

Sincerely,

l

aortgtnal signed Bys

l

D. R. HUNTER'"

!

D. R. Hunter, Chief

Reactor Projects Branch 2

l

cc:

l

.J. M. Levine, General Manager

Arkansas Nuclear One

P. O. Box 608

Russellville, Arkansas 72801

Arkansas Radiation Control Program Director

bec to DMB (IE01)

l-

bec distrib. by RIV:

  • RPB2
  • Resident Inspector

R. D. Martin, RA

!

  • EPARPB
  • SectionChief(RPB2/A)
  • D. Weiss,LFMB(AR-2015)
  • RIV File

R. Denise, DRS8P

  • MIS SYSTEM
  • RSTS Operator

,

!

.-

-

--.

- - - - - -

-

-

{

.p

]

-

-

-

.

--

.

.

,

/A

ARKANSAS POWER & LIGHT COMPANY

POST OFFICE BOX 551 UTTLE ROCK. ARKANSAS 72203 (501)3714000

December 27, 1984

_

dMBMN

'I

i

OCAN128405

sn- ABBS

\\ u{

'

,

Mr. Richard P. Denise, Director

b

~

'

DivisionofResidentReactorProjects

g

L

J

and Engineering Programs

U. S. Nuclear Regulatory Commission

L

Region IV

611 Ryan Plaza Drive, Suite 1000

Arlington, TX 76011

SUBJECT:

Arkansas Nuclear One - Units 1 & 2

Docket Nos. 50-313 and 50-368

License Nos. DPR-51 and NPF-6

Response to Inspection Reports

50-313/84-29 and 50-368/84-29

Gentlemen:

The subject inspection reports have been reviewed.

A response to the

" Notice of Violation" is attached.

Very truly yours,

J. Ted Enos

Manager, Licensing

JTE:RJS:ds

Attachment

cc:

Mr. Norman M. Haller, Director

Office of Management & Program Analysis

U. S. Nuclear Regulatory Commission

Washington, DC 20555

/

1

/

Mr. Richard C. DeYoung

..

Office of Inspection and Enforcement

3,

U. S. Nuclear Regulatory Commission

-

-

'

Washington, DC 20555

-

'

.

.

{

'i'

-

..

.

.

NOTICE OF VIOLATION

Based on the results of an NRC inspection conducted during the period of

October 1-31, 1984, and in accordance with the NRC Enforcement Policy

(10 CFR, Part 2, Appendix C), 47 FR 8583, dated March 8, 1984, the following

violatioris were identified:

A.

Failure to Maintain Cable Tray Installations as Required by

Design Drawings (Units 1 and 2)

10 CFR Part 50 Appendix B, Criterion V required hat " Activities

affectingqualItyshallbeprescribedbydocumentedinstructions,

procedures, or drawings, of a type appropriate to the

circumstances and shall be accomplished in accordance with these

instructions, procedures, or drawings."

Electrical Drawings E-59 and E-2059, " Conduit and Cable Tray Notes

and Details" state:

All solid bottom instrument trays shall have covers for their

full length.

Solid covers shall be provided on vertical t-ays for a

minimum of 6 feet above the floor level.

Tray bottom covers shall be affixed flush to the outside of

tray side rail.

Tray top covers shall be held in place by means of stainless

steel cover connection clips or equal.

Contrary to the above, cable tray installation for trays ER302,

ER303, and FJ016 for Unit 1, and trays EB129 EC261, EC212. EJ210,

CJ304, DC456 0C279,andEB129forUnit2falltomeetoneormore

of the installation requirements stated above.

This is Severity level IV Violation.

(SupplementI)(313/8429-01;

368/8429-01)

RESPONSE

The cable trays identified by the inspector as having installation

deficiencies were walked-down and job orders were issued for

correcting the discrepancies between design requirements and

actual installation.

Repairs of the Unit 2 cable trays have boon

completed.

Additional walk-downs of Unit I cable trays were

performed to identify other cable tray cover deficiencies

associated with the present refueling outage work activities.

.

r

4

..

,

.

Discrepancies noted by the inspector and the walk-down effort will

be corrected by the end of the Unit 1 outage.

A management

directive was issued to maintenance supervision requiring

implementation of practices to prevent further degradation

resulting from maintenance activities.

An evaluation of the

requirements for cable tray covers has been conducted.

Although

the plant FSARs mention that solid covers are used where minimum

separation distances for fire protection are not satisfied, the

current Fire Hazards Analysis (0CAN08404) submitted to NRC in

accordance with 10CFR 50.48 (Appendix R) takes no credit for the

tray covers.

Therefore, tray covers do not fulfill a safety

function but should be maintained to facilitate good housekeeping.

Housekeeping inspections in the future will in':rease the focus on

cable tray covers to insure that they are promptly replaced

{

following maintenance or modifications. We are presently in full

I

compliance.

j

B.

Failure to Adequately Maintain the Refueling Shuffle Procedure (Unit 1)

Technical Specification 6.8.1 states, in part, " Written procedures

shall be established, impicmented, and maintained covering . . .

Refueling Operations . . . ."

Procedure 1502.04, " Refueling Shuffle," has been established in

accordance with this Technical Specification.

Technical Specification 3.8.7 states, " Isolation valves in lines

containing automatic containment isolation valves shall be operable, or

at least one shall be closed." This specification is applicable during

i

refuelin0 operations.

Contrary to the above, on October 31, 1984, the NRC inspector found

l

that the licensee had issued a change to Procedure 1502.04 on

l

October 28, 1984, adding the following note:

"If one automatic

isolation valve is failed open, the other valve in that line must be

closed or capable of automatic actuation."

In that this discrepancy

was identified and corrected prior to commencement of refueling

)

operations, Technical Specification 3.8.7 was not violated.

This is a Severity Level IV Violation.

(Supplement I) (313/8429-04)

RESPONSE

The procedure discrepancy was corrected prior to commencement of

refueling operations and full compilance has been achieved as noted in

the violation.

To prevent recurrence, an Operations Department

directive was issued to all Senior Reactor Operators (SRO) who, by

virtue of their SRO licenso, have interim approval authority for

proceduro changes.

Proceduro revisions to safety-related operating

procedures are to be made usino a temporary or permanent change only

- _ _ _ _ _ _ _ _ .

n

.

. . . '

.

.

.

.

.

when absolutely necessary to complete or allow a required operation or

when the procedure is clearly in error, and only with concurrence of

the Operations Manager, Operations Superintendent of the affected unit,

or a permanent Operations Technical Staff SRO.

Minor procedure

discrepancies or desired improvements will be accomplished by revision

which requires Plant Safety Committee and General Manager approval

. prior to implementation.

C.

Failure to Adhere to the Requirements of the Refueling Shuffle

. Procedure (Unit 1)

Technical Specification 6.8.1 states, in part, " Written procedures

shall be established, implemented, and maintained covering . . .

Refueling Operations . . . ."

Procedure 1502.04, " Refueling Shuffle,"'has been established in

accordance with this Technical. Specification. Section 4.7 of this

procedure states, " Access to the Reactor Building fuel handling area

,

and elevations above and adjacent to the fuel transfer canal shall be

'

limited to personnel required to support the refueling effort or

maintenance of required systems.

Measures shall be established to

'

prevent loose objects or foreign material from entering the above clean.

area.

Tools shall be secured by lanyards prior to entry into the clean

!

area."

l

Contrary to the above, on October 31, 1984, the NRC inspectors found

!

l

several loose objects and tools, including nuts, bolts, and a wrench on

the fuel handling bridges.

l

This is a Severity Level V Violation.

(Supplement I) (313/8429-05)

RESPONSE

Corrective action was taken by the Shift Supervisor on duty at the time

the items were identified by the inspectors.

The Unit I refueling

Outage Manager and the Nuclear Support Supervisor ensured that the

bridges were clear of all unsecured items during fuel movement.

Full

'

'

compliance was achieved immediately and maintained for the duration of

the shuffle.

Re-enforcement of the necessity of controlling loose

material in the vicinity of the refueling canal will be emphasized with

refueling personnel prior to fuel handling operations during future

l

refueling outages.

l

.

.

.

.

.

_ _ - - - -