Deficiency Evaluation Rept DER 85-07 Re Lack of Bolt Nut Retention Mechanisms on C-E Instrument Rack Design.Bolt Nut Retention Mechanisms Installed.Final Rept Expected by 850615
ML20126B190
Person / Time
Site: Palo Verde  Arizona Public Service icon.png
Issue date: 05/16/1985
From: Van Brunt E
ARIZONA PUBLIC SERVICE CO. (FORMERLY ARIZONA NUCLEAR
To: Kirsch D
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION V)
References
ANPP-32654-TDS, DER-85-07, DER-85-7, NUDOCS 8506140023
Download: ML20126B190 (2)


Text

m c.o Arizona Nuclear Power Project 1985 HAY 28 PH 12: 37 P o. BOX 52034 e PHOENIX. ARIZONA 85072-2034 May 16, 1985 9EGION VIf,E ANPP-32654-TDS/PJC U. S. Nuclear Regulatory Commission Region V 1450 Maria Lane - Suite 210 Walnut Creek, California 94596-5368 Attention:

Mr. D. F. Kirsch, Acting Director Divincn of Reactor Safety and Projects

Subject:

Time Extension for Report - DER 85-07 A 50.55(e) Potentially Reportable Deficiency Relating to the Lack of Bolt Nut Retention Mechanism on CE Instrument Rack Design File: 85-019-026; D.4.33.2

Reference:

(A) Telephone Conversation between L. Miller and T. Bradish on March 5, 1985 (B) ANPP-32329, dated April 8, 1985 (Interim Report)

Dear Sir:

The NRC was notified of a potentially reportable deficiency in Ref-crence (A) and an Interim Report was transmitted by Reference (B).

At that time,it was estimated that a Final Report would be available by May 17, 1985.

The bolt nut retention mechanisms have been installed on the affected

-instrument racks in Unit 1.

Presently, the Project is completing the evaluation for reportability and assembling the final written report.

It is expected the Final Report will be transmitted to the NRC by June 15, 1985.

Very truly yours,

\\

Q A LLC E. E. Van Brunt, Jr.

Executive Vice President Project Director EEVB/PJC/nj cc:

See Page Two

\\ 0 8506140023 850516 TCC PDR ADOCK 05000$28 8

PDR

e; Mr. D. F. Kirsch

-ANPP-32654-TDS/PJC

~

DER 85-07 Page Two.

cc:

Richard DeYoung Director Office of Inspection and Enforcement U. S. Nuclear Regulatory Commission Washington, D. C.

20555 D. B. Karner W. E. Ide D. B. Fasnacht A. C. Rogers L. A. Souza D. E. Fowler T. D. Shriver C. N. Russo B. S. Kaplan J. R. Bynum J. M. Allen D. Canady A. C. Gehr W. J. Subblefield W. G. Bingham R. L. Patterson R. W. Welcher H. D. Foster D. R. Hawkinson R. P. Zimmerman M. L.-Clyde B. T. Parker.

T. J. Bloom D.~N.

Stover J. D. Houchen J. E. Kirby Records Center Institute of Nuclear Power Operacions 1100 circle 75 Parkway, Suite 1500 Atlanta, GA-30339