Responds to NRC GL 88-20,Suppl 4, IPEEE for Severe Accident Vulnerabilities. Milestones & Submittal Schedule Encl
ML20118A828
Person / Time
Site: Peach Bottom, Limerick  Constellation icon.png
Issue date: 09/18/1992
From: Beck G
PECO ENERGY CO., (FORMERLY PHILADELPHIA ELECTRIC
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
References
GL-88-20, NUDOCS 9209280231
Download: ML20118A828 (5)


Text

GL 88-20 Supp. 4 PIIII,ADELPillA El.ECTRIC COMPANY NUCLEAR GROUP litiADQUARTERS 955 65 CllESTERilROOK lilND.

WAYN,, PA 19087-5691 als) Mo wn September 18, 1992 Docket Nos. 50-277 5

NUCitAk EISVICI,$ 11M%50 MINT 5

50-353 License Nos. DPR-44 DPR-56 NPF-39 NPF-85 U.

S.

Nuclear Regulatory Commission ATTH: Document Control Desk Washington, D.C.

20555 SUllJECT:

Peach Bottom Atomic Power Station, Units 2 and 3 Limerick Generating Station, Units 1 and 2 Supplemental Response to NRC Generic Letter 88-20 Supplement 4,

" Individual Plant Examination of External Events for Severo Accident. Vulnerabilities"

REFERENCE:

Letter from D.

R.

llolwig, (PECo) to NRC dated December 26, 1991 Dear Sir NRC Generic Letter (GL) 88-20, Supplomont 4, " Individual Plant.

Examination of Er.tornal Events (IPEEE) for Severo Accident Vulnerabilitlos," dated June 28, 1991, required licensees to submit withir :gr' days from the issuanco date of the GL a response which describos their propoerd pengrams f or completing the IPEEE. The GL stated that the responso should:

1.

identify the methods and approach selected for performing the IPEEE, 2.

describe the method to be used if it has not been previously submitted for staff review (the description may be by reference), and 3.

identify the milestonos and schedulo for performing the IPEEE, and submitting the results to the NRC.

9209280231 920918 PDR ADDCK 05000277 1

g P

PDR

, ')

l I

"U

' U

!s.

h{gq&Q;

.s mm my g q q

y U.

S. Nuclear Regulatory Commission September 18, 1992

.PBAPS Units 2 & 3, LGS Units 1& 2 Page 2

' Supplemental Response to GL 88-20 Supp. 4

)

i The referenced letter provided Philadelphia Electric Company's (PECo) response to GL 88-20 Supplement 4, wherein we identifled the methods and approach for performing the IPEEE at Peach Bottom Atomic Power Station (PBAPS) and Limerick Generating Station (LGS).

The l e t,ter did not however identify milestones or completion schedules for performing the IPEEE at either PBAPS or LGS.

We informed the NRC at. that time of our preference to coordinate our IPEEE seismic evaluations and the actions to complete Unresolved Safety Issue (USI)

A-46,

" Verification of Seismic Adequacy of Mechanical and E l ec t.r i ca l Equipment in Operating Reactors" for PBAPS, by combining plant walkdowns for each program into a single o f t o r t..

in order to coordinat.e this eifort, we were awaiting the isuuance of t.he Supplemental Safety Evaluation Report (SSER) on the Seismic Qualjf1 cation Utility Group's (SQUG's)

Generic Implementation Procedure (GIP) f or resolution of USI A-46.

In lieu of coutpletion schedules, we commit.t.ed to providing a supplemental response to GL 88-20 Supplement 4, 120 days after the receipt of the GIP SSER, which was subsequent.ly issued on May 22, 1992.

The supplementel response would provide the specific completion schedules for performing the IPEEE at, PBAPS and LGS.

1 Accordingly, Attachments 1 and 2 to this letter are the IPEEE milestones and completion schedules for PBAPS and LGS respectively.

It should be noted that the milestone dates are estimates and are being provided for information purposes.

While every effort will be made to meet t.he milestone dates, we do not intend to inf orm the NRC 1f a revision to them becomes necessary unless such a revisien would cause the submittal of the final report to be delayed.

As indicated in the Attachments, our schedule calls for the completion of the LGS IPi.EE by June 30, 1995, and by November 20, 1995, for PBAPS.

GL 88-20, Supplement 4, requested licensees to s@m! ' their IPEEE results to the NRC within three years from the issuance datr>

of the GL (i.e.,

June 28, 1994).

However, due to the delay i t.

Issuance of the GIP, the NRC has stated that they would consider submittal extensions beyond t. hat date on a case by case basis, but in no case beyond June 1995.

We have found it necessary to extend the PBAPS IPEEE completion date beyond June 1995, for the following reasons.

1)

We plan to conduct a significant portion of the IPEEE evaluation in house.

2)

We plan to coordinate the PBAPS IPEEE seismic and USI A-46 system walkdowns.

This effort will therefore be larger in scope than the IPEEE required walkdown at LGS.

)

.__...__.._.___...-___.-__.._..._-___._-..____m.

..--m.

U. S. Nuclear Regulatory Commission September 18, 1992 i

PilAPS Units--3 & 3. LG8 Units 1 & 3 Pago 3 Supplomontal Hospanse to GL 88-30 Supp. 4 t

i 3)

Wo havo multiplo units to ovaluato.

4)

The required equipment.

walkdowns are constrained by the units' outago schedules.

We are available, at the IIRC 's convenience, to discuss the P!3APS IPl:EE completion schedulo if necessary.

If you havo any questions concerning this submittal or requiro additional information, planso contact us.

1 Sincoroly,

'Y G. J;' Bock, Manager Licensing Section Attachments cci T.

T.

Martin, Regional Administrator, Rogion I J.

J.

Lyash, USNRC Senior Resident Inspector, PBAPS T.

J.

Kenny, USNRC Senior Resident Inspector, LGS I

t h

. i

.. i.~. -;

4

,.n._,

... ~...

___,__..i...,,,L,.,

,_,,,,,....._,.L..,~

..,...,_m,.._.m~,..,,.i,.....Lu

..,__..,,..r_.y....,'.,,-

ATTACHMENT 1 PEACil BOTTOM ATOMIC POWER STATION, UNITS 2 AND 3 SUPPLEMCNTAL RESPONSE TO GENERIC LETTER 88-20 SupprJMENT 4,

' INDIVIDUAL PLANT EXAMINATION OF EXTERNAL EVENTS (IPEEE)

FOR SEVERE ACCIDENT VULNERABILITIES" MILESTONES AND SUBMITTAL SCHEDULE MILESTONE DATE

- Perf or:n Pre-Seismic Walkdown Activities September 30, 1993

- Perform Unit 3 Soismic Walkdown January 31, 1994

- Perform Unit 2 Seismic Walkdown November 30, 1994

- Perform Other External Events Evaluations August 31, 1994

- Perform Fire Analysis March 31, 1995

- Assess Vulnerabilities, Preparo Draft Report, and Obtain Management Approval October 30, 1995

- Subm.t Final Report to NRC Nove'nber 20, 1995 l

l 1

2

.....2

-l ATTACHMENT 2 1.IMERICK GENERATING trM/1UN, UNITS 1 AND 2 SUPPLEMENTAL RESPONSE TO GENERIC LLTTER 88-20 SUPPLEMENT 4

" INDIVIDUAL PLANT EXAMINATION OF EXTERNAL EVENTS (IPEEE)

FOR SEVERE ACCIDENT VULNERABILITIES" MILESTONES AND SUBMITTAL SCHEDULE MILESTONE DATE

- Perform Pre-Scismic Walkdown Activities February 28, 1993

- Perform Unit ? Seismic Walkdown September 30, 1993 Perform Unit 1 Seismic Walkdown April 30, 1994

- Perform Other External Events Evaluations May 31, 1994

- Perform Fire Analysit October 31, 1994

- Assess Vulnerabilities, Prepare Draft Report, and Obtain Management Approval May 31, 1995

- Submit Final Report to NRC June 30, 1995 I