7 AVERAGE D AILY UNIT POWER LEVEL 50-285 DOCKET NO.
Fort Calhoun Station UNIT DATE April 10, 1985 COMPLETED BY T. P. Matthews TELEPHONE (402) 536-4733 March, 1985 MONTH DAY AVERAGE DAILY POWER LEVEL DAY AVER AGE DAILY POWER LEVEL (MWe Net)
(MWe Net) 24.3 487.5 37 487.1 101.2 2
18 19 319.4 3
484.4 487.2 20 4
487.3 484.8 5
2:
'I 22 485.4 6
487.3 485.5 7
23 485.3 487.2 24 8
484.9 407.2 9
23 485.2 487.6 26 to 86.3 485.2 27 485.8 485.1 12 28 484.1 486.3 29 13 486.2 14 30 4Rd 8i 459.4 485.0 is 3:
10.8 16 INSTRUCTIONS On this format.hst the average daily unit Power levelin MWe. Net for each day ni the reporting month.Coinpute to the nearest whole nwgawatt, (9/77 )
h51gggghs5 PDR '-
16IN g
I\\
m #
g OPERATING DATA REPORT DOCKET NO.
50-285 DATE April 10, 1985 COMPLETED BY T. P. Matthews TELEPilONE (402) 536-4733 OPERATING STATUS Notes Fort Calhoun Station
- 1. Unit Name:
March, 1985
- 2. Reporting Period:
- 3. Licensed Thermal Power (MWt):
1500 502
- 4. Nameplate Rating (Gross MWe):
478
- 5. Design Electrical Rating (Net MWe):
502
- 6. Maximum Dependable Capacity (Gross MWe):
470
- 7. Maximum Dependable Capacity (Net MWe):
- 8. If Changes occur in Capacity Ratings (items Number 3 Through 7) Since Last Report. Give Reasons:
N/A N/A
- 9. Power Level To which Restricted.If Any (Net MWe):
- 10. Reasons For Restrictions.lf Any:
None This Month Yr. to Date Cumulative 744.0 2,160.0 100,946.0 II. Ilours in Reporting Period 717.6 2,133.6 77,413.8
- 12. Number Of flours Reactor Was Critical
- 13. Reactor Reserve Shutdown llours 0.0 0.0 1.309.5 709.7 2,125.7 76.793.1
- 14. Hours Generator on Line 0.0 0.0 n0
- 15. Unit Reserve Shutdown flours
- 16. Gross Thermal Energy Generated (MWil) 1,006,028.3 3.115.459.4 97.302.226.4
- 17. Gross Electrical Energy Generated (MWil) 341,792.0 1,061,194.0 31,830,819.0
- 18. Net Electrical Energy Generated (MWil) 325,245.5 1.013.011.2 30.424.648.5 95.4 98.4 76.1
- 19. Unit Senice Factor 95.4 98.4 76.1
- 20. Unit Availability Factor 91.5 98.1 65.6
- 21. Unit Capacity Factor (Using MDC Net) 91.5 98.1 63.3
- 22. Unit Capacity Factor (Using DER Net) 0.0 0.0 3.7
- 23. Unit Forced Outage Rate
- 24. Shutdowns Scheduled Over Next 6 Months tType. Date.and Duration of Eacht:
None.
N/A
- 25. If Shut Down At End Of Report Period. Estimated Date of Startup:
- 26. Units in Test Status IPrior to Commercial Operation): N/A Forecast Achiesed INIIIA L CRITICALITY INITIAL ELEC TRICITY CO\\lM ERCIA L OPER ATION (9/77 )
0 50-285 DOCKET NO.
Fort Calhoun Station UNIT SHUTDOWNS AND POWER REDUCTIONS UNIT NAME DATE April 10. 1985 j
COMPLETED BY
_T. P_ Matthows
\\,
March, 1985 TELEPHONE (402) W a733 REPORT MONTH i
-h Cause & Corrective 3?
"h
.Eh E
Licensee
, r, Action to Date g
3g 5
2s5 Event gg pU Prevent Recurrence mo e
Report :
yE 3 5 =g H
u e
C The unit was shutdown on March 16, 85-01 850316 S
34.3 8
1 N/A RB CRDRVE 1985 to replace Control Element Drive Mechanism No. 22 (CEDM 22).
While down, other miscellaneous maintenance was performed. The unit was returned to service March 17, 1985.
I 4
3 Exhibit G. Instructions I
2 Method:
for Preparation of Data F: Forced Reason:
I-Manual S: Scheduled A Equipment Failure (Explain) 2-Manual Scram.
Entry Sheets for Licensee Event Report (LER) File (NUREG.
B-Maintenance of Test 3 Automatic Scram.
Ol6!)
C-Refueling 4-Other (Explain)
D Regulatory Restriction E-Operator Training & License Examination 5
F-Administrative Exhibit I - Same Source G Operational Error (Explain)
(9/77) 1101her (Explain)
-e OMAHA PUBLIC POWER DISTRICT Fort Calhoun Station Unit No. 1 March, 1985 Monthly Operations Report I.
OPERATIONS
SUMMARY
Fort Calhoun Station operated at essentially 100% power until March 15, 1985, when a scheduled maintenance outage was initiated to repair Control Element Drive Mechanism No. 22 (CEDM 22).
A complete containment inspec-tion was conducted with no major problems identified. All planned mainte-nance was completed and the Station returned to service on March 17.
Power escalation to 100% was completed on March 19 after a chemistry hold at 30% power.
The initial auxiliary operator-nuclear class has started using the training program proposed for INP0 accreditation. Two Senior Reactor Operator candidates successfully passed the requalification exam
' administered by the NRC. This exam was a retake of an exam given in November, 1984.
Chemistry and Radiation Protection monitored performance of the secondary system chemistry during the outage with a special sampling program.
Pre-liminary results indicate that the power reduction did result in a purge of certain impurities from the' steam generators.
No safety valve or PORV challenges or failures occurred.
A.
PERFORMANCE CHARACTERISTICS None B.
CHA,NGES IN OPERATING METHODS None C.
RESULTS OF SURVEILLANCE TESTS AND INSPECTIONS None D.
CHANGES, TESTS AND EXPERIMENTS CARRIED OUT WITHOUT COMMISSION APPROVAL System Acceptance Committee Packages for March,1985:
Package Description / Analysis EEAR FC-84-11 Relocate Records Center Within the TSC.
[
This modification divided an existing room in l
the Technical Support Center and has no adverse effect on the safety analysis.
I r
L
7 g-Monthly Operations Report March,"1985 Page fhvo
~
D. - ' CHANGES, TEST AND EXPERIMENTS CARRIED OUT WITHOUT COMMISSION APPROVAL (continued)
System Acceptance Committee Packages for March, 1985:
(continued) -
Package Description / Analysis EEAR FC-80-84B Toxic Gas Monitors.-
This modification provided for changes to the toxic gas monitoring. system which will effect the automatic function of the control room ventilation system. These modifications merely increase _ the margin of safety for the.
control room operators in the event of a toxic gas release accident, and have no adverse effect on the safety-analysis.
E.
RESULTS OF LEAK RATE TESTS None F.
CHANGES IN PLANT OPERATING STAFF During March, Mr. Tracy Prouty reported to the Fort Calhoun Station as Auxiliary Operator-Nuclear. Mr. John J. Tesarek was appointed to theJposition of Reactor Engineer.
G.
TRAINING
. During March,1985,' development of performance-based training programs-for non-licensed operators continued.
Training for new operators is
._in progress.
Licensed operator requalification training included plant systems, emergency. procedures and Technical Specifications. A hot license training class began on March 25, 1985.
H.
CHANGES, TESTS AND EXPERIMENTS REQUIRING NUCLEAR REGULATORY COMMISSION AUTHORIZATION PURSUANT TO 10CFR50.59 L
l_
None l:
4 o,..-
Monthly Operations Report
. March, 1985 Page.Three
- II.. MAINTENANCE (Significant Safety Related)
None
,, 5A4 AV, /
W. Gary Gates Manager Fort Calhoun Station h
pin k) wnYi atqfy t
e n
3 "a g e
Omaha Public Power District 1623 Harney Omaha. Nebraska 68102
/
402/536-4000 April 15, 1985 g
LIC-85-158 7
'k
% D( O
/
Mr. James M. Taylor, Director i,V
{ [,,J Office of Inspection and Enforcement
/
U. S. Nuclear Regulatory Commission Washington, DC 20555
Reference:
Docket No. 50-285
Dear ifr. Taylor:
March Monthly Operating Report Please find enclosed ten (10) copies of the March,1985 Monthly Operating Report for the Fort Calhoun Station Unit No.1.
Sincerely, M
R. L. Andrews Division Manager Nuclear Production RLA/TPM/dao Enclosures cc: