Potential Deficiency Rept DER 85-05 Re Nonsegregated Bus Fire Penetrations W/O Proper Taping on Bus Conductor. Final Rept Delayed Until 850617 Due to Extent of Evaluation & Investigation
ML20116P140
Person / Time
Site: Palo Verde  Arizona Public Service icon.png
Issue date: 04/08/1985
From: Van Brunt E
ARIZONA PUBLIC SERVICE CO. (FORMERLY ARIZONA NUCLEAR
To: Kirsch D
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION V)
References
ANPP-32330-TDS, DER-85-05, DER-85-5, NUDOCS 8505070511
Download: ML20116P140 (2)


Text

.,

N 3?>

Arizona Nuclear Power Project g p g7 pp, pie P.o. Box 52034 e PHOENIX, ARIZONA 85072-2034

G2,D ' ' -

April 8, 1985 ANPP-32330-TDS/PJC U. S. Nuclear Regulatory Consission Region V 1450 Maria Lane - Suite 210 Walnut Creek, CA 94596-5368 Attention:

Mr. D. F. Kirsch, Acting Director Division of Reactor Safety and Projects

Subject:

Time Extension for Report - DER 85-05 A 50.55(e) Potentially Reportable Deficiency Relating To Nonsegregated Bus Fire Penetrations Without Proper Taping On The Bus Conductor File:

85-019-026; D.4.33.2

Reference:

(A) Telephone conversation between A. Hon and T. Bradish on February 19, 1985 (B) ANPP-32172, dated March 22, 1985 (Interim Report)

Dear Sir:

The NRC was notified of a potentially reportable deficiency in Refer-ence (A), and an Interim Report was transmitted by Reference (B). At that time, it was estimated that a Final Report would be available by April 5, 1985.

Due to the extensive investigation and evaluation required, it is now expected that this information will be finalized by June 17, 1985, at which time a complete report will be submitted.

There is no new information or change to the Interim Report at this time.

.Very truly yours, 9t. E.

cu n u.A_

E. E. Van Brunt, Jr.

Executive Vice President Project Director EEVB/PJC/nj cc: See Page Two

\\

8505070511 850408 PDR ADOCK 05000528 L

S PDR

[ b [/

- k

'ANPP-32330-TDS/PJC Mr. D. F. Kirsch DER 85-05 Page Two

'cc:

Richard DeYoung, Director Office of Inspection and Enforcement U. S. Nuclear Regulatory Commission Washington, D. C.

20555 D. B. Karner W. E. Ide D. B. Fasnacht A. C.' Rogers L. A. Souza D. E. Fowler T. D. Shriver C. N. Russo B. S. Kaplan J. R. Bynum J. M. Allen D. Canady A. C. Gehr W. J. Stubblefield W. G. Bingham R. L. Patterson

R. W.' Welcher H. D. Foster D. R. Hawkinson R. P. Zimmerman M. L. Clyde M. Matt 1T. J. Bloom D. N. Stover J. D. Houchen J. E. Kirby Records Center Institute of Nuclear. Power Operations 1100 Circle 75 Parkway, Suite 1500 Atlanta, GA 30339

'y.

,. _., _