Revised Monthly Operating Rept for June 1992 for Point Beach Nuclear Plant,Unit 2
ML20116M476
Person / Time
Site: Point Beach  NextEra Energy icon.png
Issue date: 06/30/1992
From: Peterson D
WISCONSIN ELECTRIC POWER CO.
To:
Shared Package
ML20116M425 List:
References
NUDOCS 9211200290
Download: ML20116M476 (1)


Text

_ _ _.---__ _ _ -

000 REVISED 000 OPERATIEC DATA REPORT DOCKET NO. 50-301 DATE: August 4, 1992 COMPLETED BY: Don C. Peterson k

TELEPHONE:

414-755-2321 Ext. 361 OPERATING STATUS

1. UNIT NAME:

POINT, BEACH NUCLEAR PLANT - UNIT 2 NOTES

2. REPORTING PERIOD: June - 1992
3. LICENSED THERMAL POWER (MWT):

1518.5

4. NAMEPLATE RATING (GROSS MWE):

523.8

5. DESIGN ELECTRICAL RATING (NET ET):

497.0

6. MAXIMUM DEPENDABLE CAPACITY (GROSS MWE):

509.0.

7. MAXIMUM DEPENDABLE CAPACITY (NET MWE):

485.0 S.

IF CHANGES OCCUR'IN CAPACITY RATINGS (ITEMS 3 THROUGH 7) SINCE LAST REPORT, GIVE REASONS:

NA

9. POWER LEVEL TO WHICH RESTRICTED, IF ANY (NET MWE): NA
10. REASONS FOR RESTRICTION, (IF AFY):

NA THIS MONTH YEAR TO DATE CUMULATIVE 720.0 4,367.0 174,576.0

11. HOURS IN REPORTING PERIOD 2 c,o
12. NUMBER OF HOURS REACTOR WAS CRITICAL 720.0 4,367.0 153,096.8 N
13. REACTOR RESERVE SHUTDOWN HOURS 0.0 11.6 228.3
14. HOURS GENERATO.R ON LINE 720.0 4,355.4 150,844.9 0.0 0.0 302.2 DO '
15. UNIT. RESERVE SHUTDOWN HOURS hp3
16. GROSS THERMAL ENERGY GENERATED (MWH) 1,084,791 6,531,193 215,998,350 l
17. GROSS ELECTRICAL ENERGY GENERATED 371,220 2,253,140 73,412,520

'18. NET ELECTRICAL ENERGY GENERATED (MWH) 354,707 2,155,851 69,975,629 100.0%

99.7%

86.4%

hpi

19. UNIT SERVICE FACTOR

@[

20. UNIT AVAILABILITY FACTOR 100.0%

99.7%

86.6%

00~-

21. UNIT CAPACITY FACTOR (USING MDC NET) 101.6%

101.8%

82.0%

20 o

22. UNIT CAPACITY FACTOR (USING DER NET) 99.1%

99.3%

80.7%

JfJ G O.0%

0.0%

1.1%

23. UNIT FORCED OUTAGE RATE
24. SHUTDOWNS SCHEDULED OVER hTJET 6 MONTHS (TYPE, DATE, AND DURATION OF EACH):

Maintenance and refueling outage scheduled for 47 days, 9/25/92 - 11/12/92.

25. IF SHUTDOWN AT END OF REPORT PERIOD, ESTIMATED DATE OF STARTUP:

'NA DATA REPORTED AND FACTORS CALCULATED AS REQUESTED IN NRC LETTER DATED SEPTEMBER 22, 1977

.