Requests 2-month Extension Until 850731 to Complete Implementation of New Emergency Plan,Due to Unexpected Delays in Completing Reactor Mods
ML20115F294
Person / Time
Site: National Bureau of Standards Reactor
Issue date: 04/15/1985
From: Rozier Carter
NATIONAL INSTITUTE OF STANDARDS & TECHNOLOGY (FORMERL
To: Thomas C
Office of Nuclear Reactor Regulation
References
NUDOCS 8504190463
Download: ML20115F294 (1)


Text

!'

y<d *$

  • UNITES STATEO DEPARTMENT OF COMMERCE National Bureau of Standards

.k harts

$# [ Gaithersburg. Maryland 20899 April 15, 1985 Mr. Cecil O. Thomas Chief, Standardization and Special Projects Branch Division of-Licensing U. S. Nuclear Regulatory Commission Washington, DC 20555

Subject:

Docket #50-184

Dear Mr. Thomas:

Due to unexpected delays in completing reactor modifications, NBS respectfully requests a two-month extension, until July 31, 1985, to complete implementation of the new emergency plan. As indicated before, current procedures are more than adequate to. deal with any emergency situation.

Sincerely, N EC# J Robert S. Carter ~

Chief, Reactor Radiation Division O