University of California-Davis Approval of Extension Request to Submit the Revised Updated Final Safety Analysis Report Renewal of Facility Operating License No. R 130 for the University of California-Davis Mcclellan Nuclear Research Center
ML20114E277
Person / Time
Site: University of California-Davis
Issue date: 05/13/2020
From: Linh Tran
NRC/NRR/DANU/UNPL
To: Frey W
McClellan Nuclear Research Center
Linh Tran, NRR/DANU/ UNPL, 4150293
References
EPID L 2018 RNW-0014
Download: ML20114E277 (4)


Text

May 13, 2020 Dr. Wesley D. Frey, Reactor Director McClellan Nuclear Research Center University of California, Davis 5335 Price Avenue, Building 258 McClellan, CA 95652-2504

SUBJECT:

UNIVERSITY OF CALIFORNIA-DAVIS-APPROVAL OF EXTENSION REQUEST TO SUBMIT THE REVISED UPDATED FINAL SAFETY ANALYSIS REPORT RE: RENEWAL OF FACILITY OPERATING LICENSE NO. R-130 FOR THE UNIVERSITY OF CALIFORNIA, DAVIS MCCLELLAN NUCLEAR RESEARCH CENTER (EPID NO. L-2018-RNW-0014)

The U.S. Nuclear Regulatory Commission (NRC) staff is continuing its review of the University of California, Davis (UCD) application for renewal of Facility Operating License No. R-130, dated June 11, 2018 (a copy of the application letter is available on the NRCs public website at www.nrc.gov under Agencywide Documents Access and Management System (ADAMS)

Accession No. ML18179A501), for the UCD McClellan Nuclear Research Center. By letter dated May 10, 2019 (ADAMS accession No. ML19132A147), UCD requested to supplement the license renewal application with an updated final safety analysis report (UFSAR) which reflected its decision to reduce the licensed power level to approximately 1.0 megawatt-thermal, and to eliminate pulsing capability and irradiation of explosive materials in the reactor tank. By letter dated June 14, 2019 (ADAMS Accession No. ML19197A260), UCD provided a date of April 10, 2020, for the submission of the UFSAR.

By letter dated April 3, 2020 (ADAMS Accession No. ML20121A176), UCD stated that the UFSAR is near completion. However, due to the COVID-19 pandemic and subsequent shelter-in-place order from the State of California, the final preparation of the documents has been delayed and requested a 3-month extension to July 10, 2020, for submitting the UFSAR.

Based on the information described above, the NRC staff finds the July 10, 2020, date to be acceptable, and the new estimated completion date for review of the UCD license renewal is September 2022.

W. Frey If you any questions, please contact me at (301) 415-4103, or by electronic mail at Linh.Tran@nrc.gov or Geoffrey Wertz at (301) 415-0893, or by electronic mail at Geoffrey.Wertz@nrc.gov.

Sincerely,

/RA/

Linh N. Tran, Senior Project Manager Non-Power Production and Utilization Facility Licensing Branch Division of Advanced Reactors and Non-Power Production and Utilization Facilities Office of Nuclear Reactor Regulation Docket No. 50-607 License No. R-130 cc: See next page

University of California-Davis/McClellan Docket No. 50-607 cc:

David Reap, Radiation Safety Officer 5335 Price Avenue, Bldg. 258 McClellan, CA 95652-2504 Mr. Walter Steingass, Reactor Supervisor 5335 Price Avenue, Bldg. 258 McClellan, CA 95652-2504 California Energy Commission 1516 Ninth Street, MS-34 Sacramento, CA 95814 Radiological Health Branch California Department of Public Health P.O. Box 997414, MS 7610 Sacramento, CA 95899-7414 Test, Research and Training Reactor Newsletter Attention: Ms. Amber Johnson Dept of Materials Science and Engineering University of Maryland 4418 Stadium Drive College Park, MD 20742-2115 Dr. Prasant Mohapatra Vice Chancellor for Research Department of Computer Science University of California Davis, CA 95616

ML20114E277 *concurred via email NRR-106 OFFICE NRR/DANU/PM* NRR/DANU/PM* NRR/DANU/LA* NRR/DANU/BC* NRR/DANU/PM*

NAME LTran GWertz NParker GCasto LTran DATE 4/30/2020 4/30/2020 4/24/2020 5/13/2020 5/13/2020