t U-0776 054-84( 01-09)L L30-84 (01-09)L I^*I U
/LLINDIS POWER 00MPANY IP CLINTON POWER STATION. P.o. 80X 678. CLINToN. ILLINOIS 61727 January 9, 1985 Docket No. 50-461 Director of Nuclear Reactor Regulation Attention:
Mr. A. Schwencer, Chief Licensing Branch No. 2 Division of Licensing U. S. Nuclear Regulatory Commission Washington, D.C.
20555
Subject:
Clinton Power Station (CPS) Unit 1 Emergency Operating Procedures Generation Package Confirmatory Issue #41
Dear Mr. Schwencer:
This is in response to NRC Staff reviewer, Mr. Bill Kennedy's questions regarding the schedule for resubmittal of the revised E0P Writer's guide and incorporating all changes committed to in IP letter U-0755 dated October 24, 1984.
Illinois Power will submit the revised E0P Writer's Guide and a revi.2 ion of the Emergency Procedure Guidelines by July 30, 1985. This should support completion of these items prior to fuel load so that operator training can be completed.
It is our understanding that the above commitments should resolve the NRC Staff concerns regarding the scheduled dates for submittal of the E0P Writer's Guide and the revised Emergency Procedure Guidelines.
Sincerely yours, M*
F. A. Spangenberg Director - Nuclear Licensing and Configuration Nuclear Station Engineering TLG/im cc:
B. L. Siegel,,NRC Clinton Licensing Project Manager NRC Resident Office Regional Administrator, Region III USNRC Illinois Department of Nuclear Safety b
8501180150 850109
/
DRADOCK05000g I
J