ML20108D670
| ML20108D670 | |
| Person / Time | |
|---|---|
| Site: | Palo Verde |
| Issue date: | 12/03/1984 |
| From: | Van Brunt E ARIZONA PUBLIC SERVICE CO. (FORMERLY ARIZONA NUCLEAR |
| To: | Kirsch D NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION V) |
| References | |
| ANPP-31286-TDS, DER-84-41, NUDOCS 8412130346 | |
| Download: ML20108D670 (2) | |
Text
..
h Arizona Nuclear Power Project DEC -5 hi 3 0 i P.o. box 5,2034
- PHOENIX. Am2ONA 85072-2034 MGlC,'W ly December 3,1984 ANPP-31286-TDS/LBS U. S. Nuclear Regulatory Commission Region V 1450 Maria Lane - Suite 210 Walnut Creek, CA 94596-5368 Attention: Mr. D. F. Kirsch, Acting Director Division of Reactor Safety and Projects
Subject:
Time Extension For Report - DER 84-41 A 50.55(e) Potentially Reportable Deficiency Relating To Adequacy of Cardinal Industrial Products Program For Supplier Qualification.
File: 84-019-026; D.4.33.2
Reference:
(A) Telephone conversation between P. Narbut and T. Bradish on May 24, 1984 (B) ANPP-29809, dated June 22, 1984 (Interim Report)
(C) ANPP-30410, dated August 31, 1984 (Time Extension)
(D) ANPP-30591, dated September 2J, 1984 (Interin Report)
(E) Telephone conversation between L. Miller and W. E. Ide on November 2, 1984 (F) ANPP-31083, dated November 7, 1984 (Time Extension)
(G) ANPP-31190, dated November 20, 1984*(Time Extension)
Dear Sir:
The NRC was notified of a potentially reportable deficiency in Reference (A), Interim Reports were transmitted by References (B) and (D), and Time Extensions were requested by References (C), (F), and (G).
Reference (G) estimated that a Final Report would be available by December 3, 1984.
As stated in reference (F), the overall results of the PVNGS review of this matter and associated testing programs were presented to the NRC on November 13, 1984. However, due to the extensive Materials testing performed, final review of test data is taking longer than originally expected. It is now expected that this information will be finalized by December 13, 1984.
Very truly yours, Q2[0 E. E. Van Brunt, Jr.
Nuclear Production ANPP Project Director gll 0 EEVB/LBS/nj cc: See Page Two
. ~ b-4-
u Mr. D. F. Kirsch DER 84-41; Page Two cct Richard DeYoung, Director
- 0ffice of-Inspection and Enforcement U. S. Nuclear Regulatory Commission Washington, D. C.
-20555 T. G. Woods, Jr.
D. B. Karner W. E. Ide D. B. Fasnacht A. C. Rogers L. A. Souza D. E. Fowler T. D. Shriver C. N. Russo B. S. Kaplan J. R. Bynum J. M. Allen D. Canady A. C. Gehr W. J. Stubblefield W. G. Bingham R. L. Patterson R. W. Welcher H. D. Foster -
D. R. Hawkinson R. P. Zimmerman M. L. Clyde M. Woods T. J. Bloom Records Center Institute of Nuclear Power Operations 1100 circle 75 Parkway, Suite 1500 Atlanta, GA 30339 6