OPERATING DATA REPORT DOCKET NO. 50-336 DATE 1/14/85 COMPLETED BY Gary Neron TELEPHONE-(203) 447-1791:

Ext. 4417 OPERATING STATUS

1. Unit Name: Millstone-Unit 2 Notes Items 21 and 22 cumulative
2. Reporting Period: December 1984 are Weighted Ave. Unit'
3. Licensed Thermal Power-(MWt): 2700 operated at 2560 MW Thermal
4. Nameplate Rating (Gross MWe): 909 prior to its uprating to

- 5. Design Electrical Rating.(Net MWe): 870 the current 2700 MW

6. Maximum Dependable Capacity (Gross MWe): 866.25 Thermal Power Level. *
7. Maximum Dependable Capacity (Net MWe): .833.25
8. If Changes Occur _in Capacity Ratings (Items Number 3 Through 7)

Since Last Report, Give Reasons:

N/A

, 9. Power Level To Which Restricted, If Any (Net MWe): N/A-

10. Reasons For Restrictions, If Any:

N/A 4

This Month Yr. -to-Date Cumulative

11. Hours In Reporting Period 744 8784 79056 1.2. Number Of Hours Reactor Was Critical 744 8596.8 56962.1
13. Reactor Reserve Shutdown Hours 0 0 2205.5
14. Hours Generator On-Line 733.4 8210.8 54393.0
15. Unit Reserve Shutdown Hours 0 0 468.2
16. Gross Thermal Energy Generated (MWH) 1935523 21372788 137684457
17. Gross Elec. Energy Generated (MWH) 634200 6875301 44681679
18. Net Electrical Energy Generated (MWH) 611426 6607822 42823523
19. Unit Service Factor 98.6 93.5 68.8
20. Unit Availability Factor 98.6 93.5 69.4
21. Unit Capacity Factor (Using MDC Net) 98.6 87.6 64.6
22. Unit Capacity Factor (Using DER Net) 94.5 86.5 63.6
23. Unit Forced Outage Rate .

1.4 3.8 17.1

24. Shutdowns Scheduled Over Next 6 Months (Type, Date, and Duration of Each):

Millstone Unit 2 is scheduled to shutdown in February 1985 fer a 16 week Refueling and Maintenance Outage.

25. If Shut Down At End Of Report Period, Estimated Date of Startup: N/A
26. Units In Test Status (Prior to Commercial Operation): Forecast Achieved INITIAL CRITICALITY N/A N/A INITIAL ELECTRICITY N/A N/A COMMERCIAL OPERATION N/A N/A
  • Item 21 Yr-To-Date is Weighted Ave. due to a change in MDC effective November 1, 1984.

A C oh$36 PDR I/

' AVERAGE DAILY UNIT POWER LEVELL DOCKET ~NO. 50-336'

UNIT Millstone 2-DATE 1/14/85
COMPLETED BY Gary Neron TELEPHONE (203) 447-1791

... . . Ext. 4417 MONTH December 1984 DAY- AVERAGE DAILY POWER LEVEL' DAY AVERAGE DAILY POWER LEVEL (MWe-Net) '(MWe-Net) ,

1 105 17 855 2 560" 18 855 3 851 19 -856 4 855 20 856 5 856 21 856 6 856 22 855 7 857 23 855' 8 857 24 855 9 857 25 855 10 856 26 856 11 855 27 856 12 855 28 -856 13 856 29 855 14 856 30 856

-15 857 31 855 16 '- 856 INSTRUCTIONS

. On this format, list the average ' daily unit power level in MWe-Net for each day in the reporting month. Compute to the nearest whole megawatt.

s E

, .~ , --w,, ,, ,,

DOCKET NO. 50-336' UNIT SHUTDOWNS AND POWER REDUCTIONS UNIT NAME Millstone 2 --

DATE 1/14/85 COMPLETED BY Gary Neron-REPORT MONTH December 1984 TELEPHONE (203) 447-1791 Ext. 4417 l 2 No. Date Type Duration Reason Method of Licensee Systeg Compogent Cause &' Corrective (Hours) Shutting 3 Event Code Code ' Action to-Down Reactor Re ort # Prevent Recurrence.

13- 841128 F 10.6 A 2 84-12 CH HTEXCH Extension of-Shutdown;for Repair of 5A Feedwater-Heater Tube Leakage.

1 2 3 4 F: Forced Reason: Method: Exhibit G - Instructions S: Scheduled A-Equipment Failure (Explain) 1-Manual for Preparation of Data B-Maintenance or Test 2-Manual Scram Entry Sheets for Licensee C-Refueling 3-Automatic Scram Event Report (LER) File D-Regulatory Restriction- 4-Continued from (NUREG-0161)

E-Operator Training & License Examination previous month-F-Administrative 5-Power Reduction 5'-

G-Operational Error (Explain) (Duration = 0) Exihibit 1 - Same Source H-Other (Explain) 9-Other (Explain)

1, Docket'No. 50-336 *

.Date 1/14/85 Unit Name Millstone 2 Completed By Gary Neron Telephone (203) 447-1791 Ext. 4417_.

CORRECTIVE MAINTENANCE

SUMMARY

FOR SAFETY RELATED EQUIPMENT REPORT MONTH December 1984 DATE SYSTEM COMPONENT MAINTENANCE, ACTION 12/10/84 Gaseous Radwaste "A" Waste Gas Compressor Replaced Fitting and new Gauge Lines Assembly 12/7/84 Reactor Protection RPS-D Bistable Trip Unit Replaced Power Supply for.TU-4.

System Channel D ' Retested-and Adjusted TU-4 12/13/84 Reactor Coolant Reactor Coolant Loop 2 Replaced Meter and Verifie'd -

and Vessel Hot Leg Temperature Calibration Indicator

7 .

- -~

i .

+ ,' '

Dack2t N2. 50-336 2 '

~,b**

  • 3 . .Date: =1/14/85

, Completed By:-Gary Neron

, ' Telephone: (203)-447-1791

, Ext. 4417 3 . REFUELING INFORMATION' REQUEST' 1; Name of facility ; Millstone'2

2. Scheduled date for-next? refueling shutdown: Next:refuelinglis' scheduled to-
begin on February 16L1985.-

'3. -Schedulei d ate for. restart following refueling:-June 1985-4.' Will~ refueling or resumption of operation thereafter require a.-technical specification change or other_. license amendment?

! .The discharge of failed fuel may r'equire additional technical specification E -

changes ~and a new-reload safety evaluation forlthe revised-core loadingl pattern.

l '5. Scheduled date(s) for submitting licensing action and -

supporting information

a)'A. technical . specification cha'nge request has' been submitted for the Outage Equipment Hatch. -

1

,- b)' A technical specification change request _ for the ' total _ planar peaking

' factor will be submitted in February 1985.

1 . - . -

4 c) A proposed license amendment for reracking the spent fuel pool will-be. submitted in March 1985.

! 6. Important licensing considerations associated with refueling, e.g.,

new or different fuel' design'or supplier, unreviewed design or t performance analysis methods,-sigr.ificant chinges in fuel design,

new operating procedures

The _ discharge of failed fuel may require additional technical specification changes and will impact the reload safety evaluation.

7. The number of fuel assemblies (a) in the core and'(b) in the spent i

fuel storage pool:

i 1 (a) In Core: 217 (b) 376

~

4

8. The present licensed spent' fuel pool storage: capacity and the size l of any increase in licensed storage capacity that has been requested or is. planned, in number of fuel-_ assemblies:

Currently 667 Plans are being formulated to rerack the spent fuel' pool beginning

[.

in July 1985, to increase the storage capacity to 1106 fuel; assemblies.

I. 9. The projected date of the'last refueling that can be: discharged to

, the. spent fuel pool assuming the present licensed capacity:

1985, Spent Fuel Pool, Full ~ core.off load capacity is reached.

1987, Core Full,-Spent Fuel Pool _contains 648 bundles.

4

, , ,-,~.,,,-,-~--,,,i - , , - - - . . < - . . . . . . - - , - - - - - - . . - - . ,- -s.

r O

General Offices

.aos rsa w. co,- HARTFORD. CONNECTICUT 06141-0270 g wwrwasr urw s van w- (203) 666-6911 mmrmasmnse r== cow-January 14, 1985 MP-6570 Director Office of Management Information and Program Control U. S. Nuclear Regulatory Commission Washington, D. C. 20555

Reference:

Facility Operating License No. DPR-65 Docket No. 50-336

Dear Sir:

This letter is forwarded to provide the report of operating and shutdown experience relating to Millstone Unit 2 Monthly Operating Report 84-12 in accordance with Appendix A Technical Specifications, Section 6.9.1.3. One additional copy of the report is enclosed.

Very truly yours, NORTHEAST NUCLEAR ENERGY COMPANY

/

f$ 0 E. J. Mroczka Station Superintendent Millstone Nuclear Power Station EJM/RB:ejz cc: Director, Office of Inspection and Enforcement, Region I Director, Office of Inspection and Enforcement, Washington, D. C. (10)

U. S. Nuclear Regulatory Commission, c/o Document Management Branch, l Washington, D.C. 20555 h