MONTHYEARB17894, Monthly Operating Rept for Sept 1999 for Millstone Nuclear Power Station,Unit 2.With1999-09-30030 September 1999 Monthly Operating Rept for Sept 1999 for Millstone Nuclear Power Station,Unit 2.With B17896, Monthly Operating Rept for Sept 1999 for Millstone Nuclear Power Station,Unit 1.With1999-09-30030 September 1999 Monthly Operating Rept for Sept 1999 for Millstone Nuclear Power Station,Unit 1.With B17898, Monthly Operating Rept for Sept 1999 for Millstone Nuclear Power Station,Unit 3.With1999-09-30030 September 1999 Monthly Operating Rept for Sept 1999 for Millstone Nuclear Power Station,Unit 3.With B17879, Monthly Operating Rept for Aug 1999 for Millstone Nuclear Power Station,Unit 2.With1999-08-31031 August 1999 Monthly Operating Rept for Aug 1999 for Millstone Nuclear Power Station,Unit 2.With B17874, Monthly Operating Rept for Aug 1999 for Millstone Nuclear Power Station,Unit 3.With1999-08-31031 August 1999 Monthly Operating Rept for Aug 1999 for Millstone Nuclear Power Station,Unit 3.With B17878, Monthly Operating Rept for Aug 1999 for Mnps,Unit 1.With1999-08-31031 August 1999 Monthly Operating Rept for Aug 1999 for Mnps,Unit 1.With B17858, Monthly Operating Rept for July 1999 for Millstone Nuclear Power Station,Unit 3.With1999-07-31031 July 1999 Monthly Operating Rept for July 1999 for Millstone Nuclear Power Station,Unit 3.With B17856, Monthly Operating Rept for July 1999 for Millstone Nuclear Power Station,Unit 1.With1999-07-31031 July 1999 Monthly Operating Rept for July 1999 for Millstone Nuclear Power Station,Unit 1.With ML20211A6561999-07-31031 July 1999 Monthly Operating Rept for July 1999 for Millstone Nuclear Power Station,Unit 2 ML20209J0541999-06-30030 June 1999 Monthly Operating Rept for June 1999 for Millstone Unit 2 B17833, Monthly Operating Rept for June 1999 for Millstone Power Station,Unit 1.With1999-06-30030 June 1999 Monthly Operating Rept for June 1999 for Millstone Power Station,Unit 1.With B17830, Monthly Operating Rept for June 1999 for Millstone Nuclear Power Station,Unit 3.With1999-06-30030 June 1999 Monthly Operating Rept for June 1999 for Millstone Nuclear Power Station,Unit 3.With ML20211A6751999-06-30030 June 1999 Revised Monthly Operating Rept for June 1999 for Millstone Nuclear Power Station,Unit 2,providing Revised Average Daily Unit Power Level & Operating Data Rept ML20209J0661999-05-31031 May 1999 Revised Monthly Operating Rept for May 1999 for Millstone Unit 2 ML20211A6631999-05-31031 May 1999 Revised Monthly Operating Rept for May 1999 for Millstone Nuclear Power Station,Unit 2,providing Revised Average Daily Unit Power Level,Operating Data Rept & Unit Shutdowns & Power Reductions B17808, Monthly Operating Rept for May 1999 for Millstone Nuclear Power Station,Unit 3.With1999-05-31031 May 1999 Monthly Operating Rept for May 1999 for Millstone Nuclear Power Station,Unit 3.With B17807, Monthly Operating Rept for May 1999 for Mnps,Unit 1.With1999-05-31031 May 1999 Monthly Operating Rept for May 1999 for Mnps,Unit 1.With B17804, Monthly Operating Rept for May 1999 for Mnps,Unit 2.With1999-05-31031 May 1999 Monthly Operating Rept for May 1999 for Mnps,Unit 2.With B17777, Monthly Operating Rept for Apr 1999 for Millstone Unit 2. with1999-04-30030 April 1999 Monthly Operating Rept for Apr 1999 for Millstone Unit 2. with B17782, Monthly Operating Rept for Apr 1999 for Millstone Nuclear Power Station,Unit 1.With1999-04-30030 April 1999 Monthly Operating Rept for Apr 1999 for Millstone Nuclear Power Station,Unit 1.With B17775, Monthly Operating Rept for Apr 1999 for Millstone Nuclear Power Station Unit 3.With1999-04-30030 April 1999 Monthly Operating Rept for Apr 1999 for Millstone Nuclear Power Station Unit 3.With B17748, Monthly Operating Rept for Mar 1999 for Millstone Nuclear Power Station Unit 3.With1999-03-31031 March 1999 Monthly Operating Rept for Mar 1999 for Millstone Nuclear Power Station Unit 3.With B17735, Monthly Operating Rept for Mar 1999 for Millstone Nuclear Power Station,Unit 2.With1999-03-31031 March 1999 Monthly Operating Rept for Mar 1999 for Millstone Nuclear Power Station,Unit 2.With B17747, Monthly Operating Rept for Mar 1999 for Millstone Nuclear Power Station,Unit 1.With1999-03-31031 March 1999 Monthly Operating Rept for Mar 1999 for Millstone Nuclear Power Station,Unit 1.With B17693, Monthly Operating Rept for Feb 1999 for Mnps,Unit 2.With1999-02-28028 February 1999 Monthly Operating Rept for Feb 1999 for Mnps,Unit 2.With B17694, Monthly Operating Rept for Feb 1999 for Millstone Nuclear Power Station,Unit 1.With1999-02-28028 February 1999 Monthly Operating Rept for Feb 1999 for Millstone Nuclear Power Station,Unit 1.With B17701, Monthly Operating Rept for Feb 1999 for Millstone Nuclear Power Station,Unit 3.With1999-02-28028 February 1999 Monthly Operating Rept for Feb 1999 for Millstone Nuclear Power Station,Unit 3.With B17627, Monthly Operating Rept for Dec 1998 for Millstone Nuclear Power Station,Unit 1.With1998-12-31031 December 1998 Monthly Operating Rept for Dec 1998 for Millstone Nuclear Power Station,Unit 1.With B17617, Monthly Operating Rept for Dec 1998 for Millstone Unit 2. with1998-12-31031 December 1998 Monthly Operating Rept for Dec 1998 for Millstone Unit 2. with B17461, Monthly Operating Rept for Dec 1998 for Millstone Nuclear Plant,Unit 3.With1998-12-31031 December 1998 Monthly Operating Rept for Dec 1998 for Millstone Nuclear Plant,Unit 3.With B17460, Monthly Operating Rept for Nov 1998 for Millstone Nuclear Power Station,Unit 3.With1998-11-30030 November 1998 Monthly Operating Rept for Nov 1998 for Millstone Nuclear Power Station,Unit 3.With B17576, Monthly Operating Rept for Nov 1998 for Millstone Nuclear Power Station,Unit 2.With1998-11-30030 November 1998 Monthly Operating Rept for Nov 1998 for Millstone Nuclear Power Station,Unit 2.With B17579, Monthly Operating Rept for Nov 1998 for Millstone Nuclear Power Station,Unit 1.With1998-11-30030 November 1998 Monthly Operating Rept for Nov 1998 for Millstone Nuclear Power Station,Unit 1.With ML20195E1871998-10-31031 October 1998 Monthly Operating Rept for Oct 1998 for Mnps,Unit 2 B17545, Monthly Operating Rept for Oct 1998 for Mnps,Unit 1.With1998-10-31031 October 1998 Monthly Operating Rept for Oct 1998 for Mnps,Unit 1.With ML20195F9821998-10-31031 October 1998 Monthly Operating Rept for Oct 1998 for Millstone,Unit 3 B17497, Monthly Operating Rept for Sept 1998 for Millstone Nuclear Power Station,Unit 2.With1998-09-30030 September 1998 Monthly Operating Rept for Sept 1998 for Millstone Nuclear Power Station,Unit 2.With ML20195F9871998-09-30030 September 1998 Corrected Page to MOR for Sept 1998 for Millstone,Unit 3 B17493, Monthly Operating Rept for Sept 1998 for Mnps,Unit 1.With1998-09-30030 September 1998 Monthly Operating Rept for Sept 1998 for Mnps,Unit 1.With B17458, Monthly Operating Rept for Sept 1998 for Mnps,Unit 3.With1998-09-30030 September 1998 Monthly Operating Rept for Sept 1998 for Mnps,Unit 3.With B17437, Monthly Operating Rept for Aug 1998 for Millstone Nuclear Power Station,Unit 21998-08-31031 August 1998 Monthly Operating Rept for Aug 1998 for Millstone Nuclear Power Station,Unit 2 ML20195E2061998-08-31031 August 1998 Revised Monthly Operating Rept for Aug 1998 for Mnps,Unit 2 B17441, Monthly Operating Rept for Aug 1998 for Millstone Nuclear Power Station,Unit 1.With1998-08-31031 August 1998 Monthly Operating Rept for Aug 1998 for Millstone Nuclear Power Station,Unit 1.With B17450, Monthly Operating Rept for Aug 1998 for Millstone Nuclear Power Station,Unit 3.With1998-08-31031 August 1998 Monthly Operating Rept for Aug 1998 for Millstone Nuclear Power Station,Unit 3.With B17410, Monthly Operating Rept for July 1998 for Millstone Nuclear Power Station,Unit 31998-07-31031 July 1998 Monthly Operating Rept for July 1998 for Millstone Nuclear Power Station,Unit 3 B17406, Monthly Operating Rept for July 1998 for Millstone Nuclear Power Station,Unit 11998-07-31031 July 1998 Monthly Operating Rept for July 1998 for Millstone Nuclear Power Station,Unit 1 B17404, Monthly Operating Rept for July 1998 for Millstone Nuclear Power Station,Unit 21998-07-31031 July 1998 Monthly Operating Rept for July 1998 for Millstone Nuclear Power Station,Unit 2 B17365, Monthly Operating Rept for June 1998 for Millstone Nuclear Power Station,Unit 21998-06-30030 June 1998 Monthly Operating Rept for June 1998 for Millstone Nuclear Power Station,Unit 2 B17366, Monthly Operating Rept for June 1998 for Millstone Nuclear Power Station,Unit 31998-06-30030 June 1998 Monthly Operating Rept for June 1998 for Millstone Nuclear Power Station,Unit 3 B17369, Monthly Operating Rept for June 1998 for Mnps,Unit 11998-06-30030 June 1998 Monthly Operating Rept for June 1998 for Mnps,Unit 1 1999-09-30
[Table view] Category:TEXT-SAFETY REPORT
MONTHYEARML20217P5391999-10-25025 October 1999 Rev 0,Change 1 to Millstone Unit 1 Northeast Utils QA Program ML20217C8721999-10-0606 October 1999 Rev 21,change 3 to MP-02-OST-BAP01, Nuqap Topical Rept, App F & G Only B17896, Monthly Operating Rept for Sept 1999 for Millstone Nuclear Power Station,Unit 1.With1999-09-30030 September 1999 Monthly Operating Rept for Sept 1999 for Millstone Nuclear Power Station,Unit 1.With B17894, Monthly Operating Rept for Sept 1999 for Millstone Nuclear Power Station,Unit 2.With1999-09-30030 September 1999 Monthly Operating Rept for Sept 1999 for Millstone Nuclear Power Station,Unit 2.With B17898, Monthly Operating Rept for Sept 1999 for Millstone Nuclear Power Station,Unit 3.With1999-09-30030 September 1999 Monthly Operating Rept for Sept 1999 for Millstone Nuclear Power Station,Unit 3.With ML20216J4341999-09-24024 September 1999 Mnps Unit 3 ISI Summary Rept,Cycle 6 ML20211N8401999-09-0202 September 1999 Rev 21,change 1 to Northeast Utils QA TR, Including Changes Incorporated Into Rev 20,changes 9 & 10 B17878, Monthly Operating Rept for Aug 1999 for Mnps,Unit 1.With1999-08-31031 August 1999 Monthly Operating Rept for Aug 1999 for Mnps,Unit 1.With B17874, Monthly Operating Rept for Aug 1999 for Millstone Nuclear Power Station,Unit 3.With1999-08-31031 August 1999 Monthly Operating Rept for Aug 1999 for Millstone Nuclear Power Station,Unit 3.With ML20216F5141999-08-31031 August 1999 Rept on Status of Public Petitions Under 10CFR2.206 B17879, Monthly Operating Rept for Aug 1999 for Millstone Nuclear Power Station,Unit 2.With1999-08-31031 August 1999 Monthly Operating Rept for Aug 1999 for Millstone Nuclear Power Station,Unit 2.With ML20211G9631999-08-30030 August 1999 SER Accepting Licensee Response to GL 96-05, Periodic Verification of Design-Basis Capability of Safety-Related Motor-Operated Valves ML20211A6561999-07-31031 July 1999 Monthly Operating Rept for July 1999 for Millstone Nuclear Power Station,Unit 2 B17858, Monthly Operating Rept for July 1999 for Millstone Nuclear Power Station,Unit 3.With1999-07-31031 July 1999 Monthly Operating Rept for July 1999 for Millstone Nuclear Power Station,Unit 3.With B17856, Monthly Operating Rept for July 1999 for Millstone Nuclear Power Station,Unit 1.With1999-07-31031 July 1999 Monthly Operating Rept for July 1999 for Millstone Nuclear Power Station,Unit 1.With ML20210J0311999-07-21021 July 1999 Rev 20,Change 10 to QAP 1.0, Organization ML20210E5931999-07-19019 July 1999 Revised Page 16 of 21,to App F of Northeast Util QA Program Plan ML20210C5911999-07-15015 July 1999 Revised Rev 20,change 10 to Northeast Util QA Program TR, Replacing Summary of Changes ML20210A0411999-07-15015 July 1999 Rev 20,change 10 to Northeast Util QA Program Tr B17814, Special Rept:On 990612 B Train EDG Failed to Restart within 5 Minutes Following Completion of 18 Month 24 H Endurance Run Required by TS 4.8.1.1.2.g.7.Caused by Procedural inadequacy.Re-performed Hot Restart Via Manual Start1999-07-12012 July 1999 Special Rept:On 990612 B Train EDG Failed to Restart within 5 Minutes Following Completion of 18 Month 24 H Endurance Run Required by TS 4.8.1.1.2.g.7.Caused by Procedural inadequacy.Re-performed Hot Restart Via Manual Start ML20209D1881999-07-0101 July 1999 Rev 20,change 9 to Northeast Util QA Program Tr ML20196J2191999-06-30030 June 1999 SER Concluding That Licensee USI A-46 Implementation Program,In General,Met Purpose & Intent of Criteria in GIP-2 & Staff Sser 2 for Resolution of USI A-46 ML20211A6751999-06-30030 June 1999 Revised Monthly Operating Rept for June 1999 for Millstone Nuclear Power Station,Unit 2,providing Revised Average Daily Unit Power Level & Operating Data Rept ML20196A8451999-06-30030 June 1999 Post Shutdown Decommissioning Activities Rept ML20209J0541999-06-30030 June 1999 Monthly Operating Rept for June 1999 for Millstone Unit 2 B17830, Monthly Operating Rept for June 1999 for Millstone Nuclear Power Station,Unit 3.With1999-06-30030 June 1999 Monthly Operating Rept for June 1999 for Millstone Nuclear Power Station,Unit 3.With ML20196K1791999-06-30030 June 1999 Addendum 6 to Millstone Unit 2 Annual Rept, ML20196J1821999-06-30030 June 1999 Rev 21,Change 0 to Northeast Utilities QAP (Nuqap) Tr B17833, Monthly Operating Rept for June 1999 for Millstone Power Station,Unit 1.With1999-06-30030 June 1999 Monthly Operating Rept for June 1999 for Millstone Power Station,Unit 1.With ML20195H1011999-06-11011 June 1999 Rev 20,change 8 to Northeast Utilities QAP (Nuqap) TR ML20207G6411999-06-0303 June 1999 Safety Evaluation Supporting Amends 105,235 & 171 to Licenses DPR-21,DPR-65 & NPF-49,respectively ML20211A6631999-05-31031 May 1999 Revised Monthly Operating Rept for May 1999 for Millstone Nuclear Power Station,Unit 2,providing Revised Average Daily Unit Power Level,Operating Data Rept & Unit Shutdowns & Power Reductions B17808, Monthly Operating Rept for May 1999 for Millstone Nuclear Power Station,Unit 3.With1999-05-31031 May 1999 Monthly Operating Rept for May 1999 for Millstone Nuclear Power Station,Unit 3.With ML20211B7351999-05-31031 May 1999 Cycle 7 Colr B17804, Monthly Operating Rept for May 1999 for Mnps,Unit 2.With1999-05-31031 May 1999 Monthly Operating Rept for May 1999 for Mnps,Unit 2.With B17807, Monthly Operating Rept for May 1999 for Mnps,Unit 1.With1999-05-31031 May 1999 Monthly Operating Rept for May 1999 for Mnps,Unit 1.With ML20209J0661999-05-31031 May 1999 Revised Monthly Operating Rept for May 1999 for Millstone Unit 2 ML20206M4631999-05-11011 May 1999 Safety Evaluation Supporting Alternative Proposed by Licensee to Perform Ultrasonic Exam on Inner Surface of Nozzle to safe-end Weld ML20206J8351999-05-0707 May 1999 Rev 20,Change 7 to QAP-1.0, Northeast Utls QA Program (Nuqap) Tr ML20206G6221999-05-0404 May 1999 SER Accepting Util Request to Apply leak-before-break Status to Pressurizer Surge Line Piping for Millstone Nuclear Power Station,Unit 2 B17782, Monthly Operating Rept for Apr 1999 for Millstone Nuclear Power Station,Unit 1.With1999-04-30030 April 1999 Monthly Operating Rept for Apr 1999 for Millstone Nuclear Power Station,Unit 1.With ML20205R3531999-04-30030 April 1999 Addendum 4 to Annual Rept, B17775, Monthly Operating Rept for Apr 1999 for Millstone Nuclear Power Station Unit 3.With1999-04-30030 April 1999 Monthly Operating Rept for Apr 1999 for Millstone Nuclear Power Station Unit 3.With ML20205K6141999-04-30030 April 1999 Non-proprietary Version of Rev 2 to Holtec Rept HI-971843, Licensing Rept for Reclassification of Discharge in Millstone Unit 3 Spent Fuel Pool ML20206E2971999-04-30030 April 1999 Rev 1 to Millstone Nuclear Power Station,Unit 2 COLR - Cycle 13 B17777, Monthly Operating Rept for Apr 1999 for Millstone Unit 2. with1999-04-30030 April 1999 Monthly Operating Rept for Apr 1999 for Millstone Unit 2. with ML20205Q5891999-04-0909 April 1999 Rev 20,change 6 to QAP-1.0,Northeast Utils QA Program TR ML20205R8751999-04-0909 April 1999 Provides Commission with Staff Assessment of Issues Related to Restart of Millstone Unit 2 & Staff Recommendations Re Restart Authorization for Millstone Unit 2 ML20206T3991999-03-31031 March 1999 First Quarter 1999 Performance Rept, Dtd May 1999 B17747, Monthly Operating Rept for Mar 1999 for Millstone Nuclear Power Station,Unit 1.With1999-03-31031 March 1999 Monthly Operating Rept for Mar 1999 for Millstone Nuclear Power Station,Unit 1.With 1999-09-30
[Table view] |
Text
<
OPERATING DATA REPORT DOCKET NO. 50-336 DATE 1/14/85 COMPLETED BY Gary Neron TELEPHONE-(203) 447-1791:
Ext. 4417 OPERATING STATUS
- 1. Unit Name: Millstone-Unit 2 Notes Items 21 and 22 cumulative
- 2. Reporting Period: December 1984 are Weighted Ave. Unit'
- 3. Licensed Thermal Power-(MWt): 2700 operated at 2560 MW Thermal
- 4. Nameplate Rating (Gross MWe): 909 prior to its uprating to
- 5. Design Electrical Rating.(Net MWe): 870 the current 2700 MW
- 6. Maximum Dependable Capacity (Gross MWe): 866.25 Thermal Power Level. *
- 7. Maximum Dependable Capacity (Net MWe): .833.25
- 8. If Changes Occur _in Capacity Ratings (Items Number 3 Through 7)
Since Last Report, Give Reasons:
N/A
, 9. Power Level To Which Restricted, If Any (Net MWe): N/A-
- 10. Reasons For Restrictions, If Any:
N/A 4
This Month Yr. -to-Date Cumulative
- 11. Hours In Reporting Period 744 8784 79056 1.2. Number Of Hours Reactor Was Critical 744 8596.8 56962.1
- 13. Reactor Reserve Shutdown Hours 0 0 2205.5
- 14. Hours Generator On-Line 733.4 8210.8 54393.0
- 15. Unit Reserve Shutdown Hours 0 0 468.2
- 16. Gross Thermal Energy Generated (MWH) 1935523 21372788 137684457
- 17. Gross Elec. Energy Generated (MWH) 634200 6875301 44681679
- 18. Net Electrical Energy Generated (MWH) 611426 6607822 42823523
- 19. Unit Service Factor 98.6 93.5 68.8
- 20. Unit Availability Factor 98.6 93.5 69.4
- 21. Unit Capacity Factor (Using MDC Net) 98.6 87.6 64.6
- 22. Unit Capacity Factor (Using DER Net) 94.5 86.5 63.6
- 23. Unit Forced Outage Rate .
1.4 3.8 17.1
- 24. Shutdowns Scheduled Over Next 6 Months (Type, Date, and Duration of Each):
Millstone Unit 2 is scheduled to shutdown in February 1985 fer a 16 week Refueling and Maintenance Outage.
- 25. If Shut Down At End Of Report Period, Estimated Date of Startup: N/A
- 26. Units In Test Status (Prior to Commercial Operation): Forecast Achieved INITIAL CRITICALITY N/A N/A INITIAL ELECTRICITY N/A N/A COMMERCIAL OPERATION N/A N/A
- Item 21 Yr-To-Date is Weighted Ave. due to a change in MDC effective November 1, 1984.
A C oh$36 PDR I/
' AVERAGE DAILY UNIT POWER LEVELL DOCKET ~NO. 50-336'
- UNIT Millstone 2-DATE 1/14/85
- COMPLETED BY Gary Neron TELEPHONE (203) 447-1791
... . . Ext. 4417 MONTH December 1984 DAY- AVERAGE DAILY POWER LEVEL' DAY AVERAGE DAILY POWER LEVEL (MWe-Net) '(MWe-Net) ,
1 105 17 855 2 560" 18 855 3 851 19 -856 4 855 20 856 5 856 21 856 6 856 22 855 7 857 23 855' 8 857 24 855 9 857 25 855 10 856 26 856 11 855 27 856 12 855 28 -856 13 856 29 855 14 856 30 856
-15 857 31 855 16 '- 856 INSTRUCTIONS
. On this format, list the average ' daily unit power level in MWe-Net for each day in the reporting month. Compute to the nearest whole megawatt.
s E
, .~ , --w,, ,, ,,
DOCKET NO. 50-336' UNIT SHUTDOWNS AND POWER REDUCTIONS UNIT NAME Millstone 2 --
DATE 1/14/85 COMPLETED BY Gary Neron-REPORT MONTH December 1984 TELEPHONE (203) 447-1791 Ext. 4417 l 2 No. Date Type Duration Reason Method of Licensee Systeg Compogent Cause &' Corrective (Hours) Shutting 3 Event Code Code ' Action to-Down Reactor Re ort # Prevent Recurrence.
13- 841128 F 10.6 A 2 84-12 CH HTEXCH Extension of-Shutdown;for Repair of 5A Feedwater-Heater Tube Leakage.
1 2 3 4 F: Forced Reason: Method: Exhibit G - Instructions S: Scheduled A-Equipment Failure (Explain) 1-Manual for Preparation of Data B-Maintenance or Test 2-Manual Scram Entry Sheets for Licensee C-Refueling 3-Automatic Scram Event Report (LER) File D-Regulatory Restriction- 4-Continued from (NUREG-0161)
E-Operator Training & License Examination previous month-F-Administrative 5-Power Reduction 5'-
G-Operational Error (Explain) (Duration = 0) Exihibit 1 - Same Source H-Other (Explain) 9-Other (Explain)
1, Docket'No. 50-336 *
.Date 1/14/85 Unit Name Millstone 2 Completed By Gary Neron Telephone (203) 447-1791 Ext. 4417_.
CORRECTIVE MAINTENANCE
SUMMARY
FOR SAFETY RELATED EQUIPMENT REPORT MONTH December 1984 DATE SYSTEM COMPONENT MAINTENANCE, ACTION 12/10/84 Gaseous Radwaste "A" Waste Gas Compressor Replaced Fitting and new Gauge Lines Assembly 12/7/84 Reactor Protection RPS-D Bistable Trip Unit Replaced Power Supply for.TU-4.
System Channel D ' Retested-and Adjusted TU-4 12/13/84 Reactor Coolant Reactor Coolant Loop 2 Replaced Meter and Verifie'd -
and Vessel Hot Leg Temperature Calibration Indicator
7 .
- -~
i .
+ ,' '
Dack2t N2. 50-336 2 '
~,b**
, Completed By:-Gary Neron
, ' Telephone: (203)-447-1791
, Ext. 4417 3 . REFUELING INFORMATION' REQUEST' 1; Name of facility ; Millstone'2
- 2. Scheduled date for-next? refueling shutdown: Next:refuelinglis' scheduled to-
- begin on February 16L1985.-
'3. -Schedulei d ate for. restart following refueling:-June 1985-4.' Will~ refueling or resumption of operation thereafter require a.-technical specification change or other_. license amendment?
! .The discharge of failed fuel may r'equire additional technical specification E -
changes ~and a new-reload safety evaluation forlthe revised-core loadingl pattern.
l '5. Scheduled date(s) for submitting licensing action and -
- supporting information
a)'A. technical . specification cha'nge request has' been submitted for the Outage Equipment Hatch. -
1
,- b)' A technical specification change request _ for the ' total _ planar peaking
' factor will be submitted in February 1985.
1 . - . -
4 c) A proposed license amendment for reracking the spent fuel pool will-be. submitted in March 1985.
! 6. Important licensing considerations associated with refueling, e.g.,
new or different fuel' design'or supplier, unreviewed design or t performance analysis methods,-sigr.ificant chinges in fuel design,
- new operating procedures
The _ discharge of failed fuel may require additional technical specification changes and will impact the reload safety evaluation.
- 7. The number of fuel assemblies (a) in the core and'(b) in the spent i
fuel storage pool:
i 1 (a) In Core: 217 (b) 376
~
4
- 8. The present licensed spent' fuel pool storage: capacity and the size l of any increase in licensed storage capacity that has been requested or is. planned, in number of fuel-_ assemblies:
Currently 667 Plans are being formulated to rerack the spent fuel' pool beginning
[.
in July 1985, to increase the storage capacity to 1106 fuel; assemblies.
I. 9. The projected date of the'last refueling that can be: discharged to
, the. spent fuel pool assuming the present licensed capacity:
1985, Spent Fuel Pool, Full ~ core.off load capacity is reached.
1987, Core Full,-Spent Fuel Pool _contains 648 bundles.
4
, , ,-,~.,,,-,-~--,,,i - , , - - - . . < - . . . . . . - - , - - - - - - . . - - . ,- -s.
r O
General Offices
.aos rsa w. co,- HARTFORD. CONNECTICUT 06141-0270 g wwrwasr urw s van w- (203) 666-6911 mmrmasmnse r== cow-January 14, 1985 MP-6570 Director Office of Management Information and Program Control U. S. Nuclear Regulatory Commission Washington, D. C. 20555
Reference:
Facility Operating License No. DPR-65 Docket No. 50-336
Dear Sir:
This letter is forwarded to provide the report of operating and shutdown experience relating to Millstone Unit 2 Monthly Operating Report 84-12 in accordance with Appendix A Technical Specifications, Section 6.9.1.3. One additional copy of the report is enclosed.
Very truly yours, NORTHEAST NUCLEAR ENERGY COMPANY
/
f$ 0 E. J. Mroczka Station Superintendent Millstone Nuclear Power Station EJM/RB:ejz cc: Director, Office of Inspection and Enforcement, Region I Director, Office of Inspection and Enforcement, Washington, D. C. (10)
U. S. Nuclear Regulatory Commission, c/o Document Management Branch, l Washington, D.C. 20555 h