Interim Deficiency Rept DER 84-55 Re Unqualified Foxboro Modules.Initially Reported on 840817.Due to Extensive Investigation & Evaluation Next Rept Delayed Until 841106
ML20106D495
Person / Time
Site: Palo Verde  Arizona Public Service icon.png
Issue date: 10/17/1984
From: Van Bruent E, Van Brunt E
ARIZONA PUBLIC SERVICE CO. (FORMERLY ARIZONA NUCLEAR
To: Bishop T
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION V)
References
ANPP-30872-TDS, DER-84-55, NUDOCS 8410260004
Download: ML20106D495 (2)


Text

1 g

., =,

fiCCEIVEu

!ac Arizona Public Service Company 2 OCT22 M Ol4

' Region w.c October 17,~ 1984 ANPP-30872-TDS/TRB U. Si-Nuclear Regulatory Commission

-Region V Creekside Oaks Office Park

'1450 Maria Lane - Suite 210 Walnut Creek,. California' 94596-5368 Attention: Mr. T. W. Bishop, Director Division of Reactor Safety and Projects

Subject:

Time Extension For Report - DER 84-55 A 50.55(e) Potentially Reportable Deficiency Relating To Unqualified Foxboro Modules.

File: 84-019-026; D.4.33.2

Reference:

(A) Telephone conversation between P. Narbut and T. Bradish on August 17, 1984 (B) ANPP-30536, dated September 17, 1984 (Interim Report)

D' ear Sir:

The NRC was notified-of a potentially reportable deficiency in-Reference (A), and an Interim Report was transmitted by Reference (B).

At that time, it was estimated that a Final Report would be available by October 19,~1984.

Due to the extensive' investigation and evaluation required, it is now

expected that this information will be finalized by November 6,1984, at which time-a complete report will be submitted.

There is no new information or change to the Interim Report at this time.

Very truly yours, G

i l

-L.

CUUL_.

r\\ LR E. E. Van Brunt, Jr.

APS Vice President Nuclear Production ANPP Project Director

.EEVB/TRB/nj cc: See Page Two 8410260004 841017 PDR ADOCK 05000528 i

S PDR 5 0 i

d(1

? 4 ',..

Mr. T. W. Bishop

. DER 84-55 Page Two-cc:

Richard DeYoung, Director Office of Inspection and Enforcement U. S. Nuclear Regulatory Connaission Washington, D. C.

20555 1

T. G. Woods, Jr..

D. B. Karner W. E. Ide D. B. Fasnacht A. C. Rogers L. A; Souza D.-E. Fowler T. D. Shriver C. N. Russo J. Vorees

-J. R. Bynum J. M. Allen A. C.-Gehr W. J. Stubblefield W. G. Bingham R. L. Patterson R. W. Welcher H. D. Foster D. R. Hawkinson R. P. Zinnaerman L. Clyde

.M. Woods T. J. Bloom Records Center Institute of Nuclear Power Operations 1100 circle 75 Parkway, Suite 1500 Atlanta, GA 30339

~.,

__.