Interim Deficiency Rept DER 84-25 Re Failure of Containment Supply Registers to Cycle.Initially Reported on 840501. Final Rept Delayed Until 841031
ML20106C114
Person / Time
Site: Palo Verde  Arizona Public Service icon.png
Issue date: 10/15/1984
From: Van Brunt E
ARIZONA PUBLIC SERVICE CO. (FORMERLY ARIZONA NUCLEAR
To: Bishop T
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION V)
References
ANPP-30855-TDS, DER-84-25, NUDOCS 8410240009
Download: ML20106C114 (2)


Text

..

i Arizona Public Service Company l TO 30(q October 15, 1984 f// f p" ANPP-30855-TDS /TRB U. S. Nuclear Regulatory Commission Ii !'..' r:

Region V Creekside Oaks Office Park 1450 Maria Lane - Suite 210 Walnut Creek, California 94596-5368 Attention: Mr. T. W. Bishop, Director Division of Reactor Safety and Projects

Subject:

Time Extension For Report - DER 84-25 A 50.55(e) Potentially Reportable Deficiency Relating To Containment Supply Registers Would Not Cycle.

File: 84-019-026; D.4.33.2 Reference (A) Telephone conversation between P. Narbut and T. Bradish on May 1, 1984 (B) ANPP-29611, dated May 29, 1984 (Interim Report)

(C) ANPP-30256, dated August 16,1984 (Interim Report)

(D) ANPP-30564, dated September 19,1984 (Time Extension)

Dear Sir:

The NRC was notified of a potentially reportable deficiency in Reference ( A), Interim Reports were transmitted by Reference (B) and (C),

and a Time Extension was requested by Reference (D). At that time, it was estimated that a Final Report would be available by October 18, 1984 Due to the extensive investigation and evaluation required, it is now expected that this information will be finalized by October 31, 1984, at which time a complete report will be submitted.

There is no new information or change to the Interim Report at this time.

Very truly ours,

(

l d

ALL E. E. Van Brunt, Jr.

l APS Vice President i

Nuclear Production l-ANPP Project Director EEVB/TRB/nj cc: See Page Two i.

k0 I

8410240009 841015 PDR ADOCK 05000528 1

N-

I j.. -

F-V

+

} --

Mr. T. W. Bishop

- DER ' 84-25 Page Two f

cct Richard DeYoung, Director Office of Inspection and Enforcement U. S. Nuclear Regulatory Commission Washington,- D. C.

20555 T. G. Woods, Jr.

D. B. Karner W. E. Ide I

D. B. Fasnacht '

. A. C. Rogers L. A. Sousa D. E. Fowler T. D. Shriver C. N. Russo J. Vorees J. R. Bynum J. M. Allen A. C. Gehr W. J. Stubblefield W. G. Bingham -

R. L. Patterson R. W. Welcher H. D. Foster D. R. Hawkinson R. P. Zimmerman L. Clyde M. Woods T. J. Bloom Records Center Institute of Nuclear Power Operations 1100 Circle 75 Parkway, Suite 1500 Atlanta, GA 30339 l'

l l

l' i

k'