Interim Deficiency Rept DER 84-62 Re Malfunctioning Load Sequencer During Safeguards Testing.Initailly Reported on 840817.Due to Extensive Investigation & Evaluation,Final Rept Delayed Until 841031
ML20106B593
Person / Time
Site: Palo Verde  Arizona Public Service icon.png
Issue date: 10/11/1984
From: Van Brunt E
ARIZONA PUBLIC SERVICE CO. (FORMERLY ARIZONA NUCLEAR
To: Bishop T
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION V)
References
ANPP-30794-TDS, DER-84-62, NUDOCS 8410230350
Download: ML20106B593 (2)


Text

9-X-

.i

{ ?,,'o e,{.,..

)

~

t 3

. HECEIVED

~

Nn; Arizona Public Service Company L

13R OCT 15 FM 1: 23

' LEG;nfi V1.t c L

11, 1984

~

October ANPP-30794-TDS/TRB U. S. Nuclear Regulatory Commission Region V Creekside Oaks Office Park 1450 Maria Lane - Suite 210 Walnut Creek, California 94596-5368 Attention: Mr. T. W. Bishop, Director Division of Resident Reactor Projects and Engineering Programs i

Subject:

Time Extension For Report - DER 84-62 A 50.55(e) Potentially Reportable Deficiency Relating To Load Sequencer Did Not Function Properly During Safeguaeds Testing.

File 84-019-026; D;4.33.2 Referencet ( A) Telephone conversation between P. Narbut and T. Bradish on August 17, 1984 (B) ANPP-30531, dated September 17, 1984 (Interim Report) l Dear Sir The NRC was notified of a potentially reportable deficiency in Reference (A), and an Interim Report was transmitted by Reference (B).

At that time, it was estimated that a Final Report would be available by October 12, 1984 l

Due to the extensive investigation and evaluation required, it is now l

expected that this information will be finalized by October 31, 1984, at which time a complete report will be submitted.

There is no new inf ornation or change to the Interim Report at this time.

l Very truly yours,

\\

E E.

cm dk E. E. Van Brunt, Jr.

APS Vice President Nuclear Production ANPP Project Director Env5/TRB/nj cc See Page Two-be O

e M

g j7

p.

.d es -y, ;g

(;

N h.

~ Mr. T. W. Bishop-

- DR 84-62

- Page Two e

u-cet Richard DeYoung, Director Office of Inspection and Enf orcement U. S. ' Nuclear Regulatory Commission Wa'shington, D. C.

20555~

T., G. Woods, 'Jr.

D. B. Karner s

W. E. Ide D. B. Fasnacht A. C. Rogers L. A. Souza-D. E. Fowler T. D. Shriver C.' N. Russo J.'Vorees

'J. R. Bynua-J. M. Allen A. C. Gehr W. J. Stubblefield W. G. Bingham R. L. Pa tterson R. W. Welcher H. D. Foster D. R. llawkinson R. P. Zimmerman L. Clyde M. Woods T. J. Bloom Records Center Institute of Nuclear Power Operations 1100 Circle 75 Parkway, Suite 1500 Atlanta, CA 30339 4

4 4