Discusses Delay of Full Power Operation Pending Compliance by Util W/Requirements Re Const & Operating Procedures. Status Rept & Proposed Timetable for Authorization of Restart & Full Power Operation Requested
ML20105C648
Person / Time
Site: Grand Gulf, 05000000
Issue date: 04/17/1984
From: Jeanne Johnston
SENATE
To: Palladino N
NRC COMMISSION (OCM)
Shared Package
ML20105C130 List:
References
FOIA-84-502 NUDOCS 8502090483
Download: ML20105C648 (1)


Text

.

J. BENNETT JOHNSTON LOUISIANA

'21Cnifeb Sfales Senate April 17, 1984 The Honorable Nunzio J. Palladino Chairman, Nuclear Regulatory Commission 1717 H Street, N. W.

Washington, D.C.

Dear Chairman Palladino:

As. you know, Mississippi Power and Light was issued a full power license for its Grand Gulf Nuclear Power Plant on June 16, 1982.

However, operation under that license was limited to 5% of full power.

Authorization to operate at full power was delayed, I

pending compliance by MPSL with certain commission requirements regarding construction and operating procedure.

MPSL has made the required corrections, yet it still awaits authorization for full power operation.

The continued delay in receiving such authorization poses pra.ctical and financial diffi-culties.

In the near term, a neutron scurce must be procured for In the long term, the high holding costs which

]

power generation.

accumulate with further delay may jeopardize the financial well being of the utility.

For this reason, I would appreciate receiving a status report on the Grand Gulf Nuclear Unit, as well as a proposed timetable for authorization of restart and full power operation.

I appreciate your consideration and I look forward to hearing from you.

With kindest regards, I am Sin g,

i i J. Bennett Joh ston

'ted States enator JBJ: dog 8502090483 840705 PDR FOIA KOLIB4-502 PDR i