UNITED STATES
[
j NUCLEAR REGULATORY COMMISSION j
g
't WASHINGTON, D.C.== =1 e.,...../
l ARIZONA PUBLIC SERVICE COMPANY. ET AL.
DOCKET NO. STN 50-529 i
l PALO VERDE NUCLEAR GENERATING STATION. UNIT NO. 2 AMENDMENT TO FACILITY OPERATING LICENSE Amendment No. 96 License No. NPF-51 l
1.
The Nuclear Regulatory Commission (the Commission) has found that:
A.
The application for amendment by the Arizona Public Service Company (APS or the licensee) on behalf of itself and the Salt River Project Agricultural Improvement and Power District, El Paso Electric Company, Southern California Edison Company, Public Service Company of New Mexico, Los Angeles Department of Water and Power, and Southern California Public Power Authority dated April 1,1996, as supplemented by letters dated April 3, 1996, complies with the standards and requirements of the Atomic Energy Act of 1954, as amended (the Act) and the Commission's regulations set forth in 10 CFR Chapter I; B.
The facility will operate in conformity with the application, the provisions of the Act, and the rules and regulations of the Commission; C.
There is reasonable assurance (i) that the activities authorized by this amendment can be conducted without endangering that health and safety of the public, and (ii) that such activities will be conducted in compliance with the Commission's regulations; l
D.
The issuance of this amendment will not be inimical to the common defense and security or to the health and safety of the public; and E.
The issuance of this amendment is in accordance with 10 CFR Part 51 of the Commission's regulations and all applicable requirements have been satisfied.
2.
Accordingly, the license is amended by changes to the Technical Specifications as indicated in the attachment to this license amendment, i
and paragraph 2.C(2) of Facility Operating License No. NPF-51 is hereby l
amended to read as follows:
)
j 9604100198 960403 i
l PDR ADOCK 05000529 P
PDR l
! (2) Technical Soecifications and Environmental Protection Plan.
The Technical Specifications contained in Appendix A, as revised through Amendment No. 96, and the Environmental Protection Plan contained in Appendix B, are hereby incorporated into this license.
APS shall operate the facility in accordance with the Technical Specifications and the Environmental otherwise stated in specific license Protection Plant,exgwhere conditions.
~
~'
3.
This license amendment is effective as of the date of issuance.
FOR THE NUCLEAR REGULATORY COMMISSION f/
U"'~
/h;JD
/ William H. Bateman, Director Project Directorate IV-2 l
Division of Reactor Projects III/IV l
Office of Nuclear Reactor Regulation
Attachment:
Changes to the Technical Specifications
~
l Date of Issuance: April 3, 1996 uasN l
i ATTACHMENT TO LICENSE AMENDMENT AMENDMENT NO. 96 TO FACILITY OPERATING LICENSE NO. NPF-51 DOCKET NO. STN 50-529 Replace the following page of the Appendix A Technical Specifications with the enclosed page. The revised page is identified by amendment number and contains marginal lines indicating the areas of change. The corresponding overleaf page is also provided to maintain document completeness.
=
REMOVE INSERT
~
3/4 9-6 3/4 9-6 i
l I
i
REFUELING OPERATIONS 3/4.9.5 COMUNICATIONS LIMITING CONDITION FOR OPERATION 3.9.5 Direct communications shall be maintained between the control room and personnel at the refueliing station.
APPLICABILITY: During C0RE ALTERATIONS.
ACTION:
When direct communications between the control room and personnel at the refueling station cannot be maintained, suspend all CORE ALTERATIONS.
SURVEIttANCE' REQUIREMENTS i
4.9.5 Direct communications between the control room and personnel at the refueling station shall be demonstrated within 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> prior to the start of and at least once per 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> during CORE ALTERATIONS.
i PALO VERDE - UNIT 2 3/4 9-5
REFUELING OPERATIONS l
l 3/4.9.6 REFUELING MACHINE LIMITING CONDITION FOR OPERATION l
3.9.6 The refueling machine
- shall be used for movement of fuel assemblies and l
l shall be OPERABLE with:
l a.
A minimum capacity of 3590 pounds and an overload cut off limit of l
1ess than or equal to 1600 pounds for the refueling machine.
l l
APPLICABILITY: During movement of fuel assemblies within the refueling l
cavity.
ACTION:
With the above requirements for the refueling machine
- not satisfied, suspend l
use of the refueling machine from operations involving the movement of fuel assemblies.
l SURVEILLANCE REOUIREMENTS 4.9.6.1 Therefuelingmachine*usedTo7movementoffuelassembliesshallbe l
demonstrated OPERABLE within 72-hours prior to the start of such operations by performing a load test of at least 3590 pounds and demonstritka an automatic load cut off when the refueling machine load exceeds 1600 poahdi.
l l
t i
l
- A hoist may be used for movement of the fuel assembly at core location A-07 during core offload of Unit 2, sixth refueling outage. The hoist shall have j
a minimum capacity of 2400 pounds. A load cut off limit of 1600 pounds will be applied administratively using a load cell. The hoist shall be demonstrated operable within 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> prior to the start of fuel movement by performing a load test of at least 2400 pounds.
4 PALO VERDE - UNIT 2 3/4 9-6 Amendment No. 30,75,05,96 i