Forwards Suppl to 911111 Application for Amend to License DPR-40,revising Reporting Requirements Upon Loss of 161 Kv, from Contacting Region IV to Contacting NRC Operations Ctr & Clarifying Type of Written Rept to Be Submitted
ML20101P524
Person / Time
Site: Fort Calhoun Omaha Public Power District icon.png
Issue date: 06/25/1992
From: Gates W
OMAHA PUBLIC POWER DISTRICT
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
Shared Package
ML20101P527 List:
References
LIC-92-189R, NUDOCS 9207130107
Download: ML20101P524 (1)


Text

9

. o was:

~

Omaha Public Power District 444 South 16th Street Mall l June 25, 1992 Omaha. Nebraska 68102-2247 LIC-92-189R 402/636-2000 U. S. Nuclear Regulatory Commission Attn: Cocument Control Desk Mail Station Pl-137 Washington, DC 20555

References:

1. Docket No. 50-285
2. Letter from OPPD (W. G. Gates) to NRC (Document Control Desk) dated June 21, 1991 (LIC-91-173A)
3. Letter from OPPD (W. G. Gates) to NRC (Document Control Desk) dated November 11, 1991 (LIC-91-305R)

Gentlemen:

SUBJECT:

Suppleinent to Application for Amendment of Operating License dated November 11, 1991 Enclosed please find a supplement to Omaha Public Power District's (OPPD)

" Application for Amendment of Operating License" which seeks to amend the Fort Calhoun Station Unit No.1 Technical Specifications. The changes requested are to revise the reporting requirements, upon loss Of 161kV, from calling the NRC Region IV to calling the NRC Operations Center and to clarify what type of written report will be submitted. This submittal supercedes the application submitted in Reference 3 on a replacement page basis.

Attachment A contains a markup reflecting the requested changes of the Technical Specification. Attachment 8 provides a Discussion, Justification and No Significant Hazards Consideration Analysis, for the changes requested. OPPD respectfully requests 60 days from the date of issuance to implement these changes.

If you have any additional questions, or require further information, please do not hesitate to contact me or members of my staff.

Sincerely, 0W. G. Gates/

Division Manager Nuclear Operations WGG/sel Attachment c: LeBoeuf, Lamb, Leiby & MacRae R. D. Martin, NRC Regional Administrator, Region IV R. P. Mullikin, NRC Senior Resident Inspector D. L. Wigginton, NRC Senior Project Manager S. D. Bloom, NRC Project Engineer ph-9207130107 DR 920625 k ADOCK 03000285 cs-s t 24 PDR Employment Eq optatunty