Informs That 1-2A DG Outage Currently Rescheduled for 960429 Due to to Revised Ship Date for Intercooler Tube Bundle,Per GL 87-02
ML20101K501
Person / Time
Site: Farley  Southern Nuclear icon.png
Issue date: 03/29/1996
From: Dennis Morey
SOUTHERN NUCLEAR OPERATING CO.
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
References
REF-GTECI-A-46, REF-GTECI-SC, TASK-A-46, TASK-OR GL-87-02, GL-87-2, NUDOCS 9604020391
Download: ML20101K501 (1)


Text

....

South 1rn Nucisar Operating Company Post Offics Box 1295

  • * ' @rrrfingham. Alabama 35201 Teltphona (205) 868 5131 Southern Nuclear Operating Company
o.. uor.y L

Vice President Farley Project the Southern electric system l

March 29, 1996 Docket Nos: 50-348 10 CFR 50.4 50-364 U. S. Nuclear Regulatory Commission A'ITN: Dxument Control Desk Washin-tan, D. C. 20555-0001 i

l Joseph M. Farley Nuclear Plant l

Resolution of Seismic Outliers Ladies and Gentlemen:

l By letter dated December 21,1995, Southern Nuclear provided a revised schedule to resolve certain outliers with regard to seismic evaluation criteria in response to Generic Letter 87-02, l

" Verification of Seismic Adequacy of Mechanical and Electrical Equipment in Operatmg Reactors, l

Unresolved Safety Issue (USI) A-46." Two items associated with the Diesel Generator 1 2A were l

scheduled to be completed during the next scheduled generator outage and were to be completed by April 1,1996. These items involve improvements to equipment suchorage for the Local Control Panel and Relay Panel.

i The Diesel Generator 1-2A outage was scheduled for March 9,1996, but due to a revised ship date l

for an intercooler tube bundle, the 1-2A Diesel Generator outage is currently rescheduled for April 29,1996. 'Ihe improvements to the Diesel Generator 1-2A equipment anchorage will be completed during the next scheduled 1-2A Diesel Generator outage.

If you have any questions, please advise.

Respectfully submitted, f )/lo"*

Dave Morey BDM:maf NRCSEL. DOC I

cc:

Mr. S. D. Ebneter, Region II Admmistrator Mr. B. L. Siegel, NRR Senior Project Manager l

Mr. T. M. Ross, Plant Resident Inspector 1

i I

020098 l

9604020391 960329 i

PDR ADOCK 05000348 9

p PDR 4

j

.