Informs That Replacement of Control Valve 2-SV481 W/Environmentally Qualified Valve Completed.Valve & Associated Electrical Interface Components Now in Full Compliance w/10CFR50.49
ML20101G861
Person / Time
Site: Point Beach NextEra Energy icon.png
Issue date: 12/13/1984
From: Fay C
WISCONSIN ELECTRIC POWER CO.
To: Harold Denton, John Miller
Office of Nuclear Reactor Regulation
References
TAC-57389, NUDOCS 8412280049
Download: ML20101G861 (1)


Text

- - _ _ _ _ - _ _ _ _ _

8 Msconsm Electnc wecoumr

[-

231 W. MICHIGAN, P.O. BOX 2046, MILWAUKEE, WI 53201 i

I December 13, 1984 l

Mr. H. R. Denton, Director Office of Nuclear Reactor Regulation U.

S. NUCLEAR REGULATORY COMMISSION Washington, D.C.

~20555 Attention:

Mr. J. R. Miller, Chief Operating Reactors, Branch 3 Gentlemen:

DOCKET 50-301 ENVIRONMENTAL QUALIFICATION OF FEEDWATER REGULATING BYPASS VALVES POINT BEACH NUCLEAR PLANT, UNIT 2 On November 14, 1984, we sent a letter to you informing you of the delay in upgrading 2-SV481, a control valve on the feedwater regulating bypass valve, to meet the environmental qualification requirements of 10 CFR 50.49.

An amplifying letter.

dated December 4 was also sent discussing the delay in the work.

This letter is to inform you that the replacement of 2-SV481 with an environmentally qualified valve has now been completed.

This valve and the associated electrical interface componente are now in full compliance with the provisions of 10 CFR 50.49.

Should you desire any further information in this matter, please contact us.

Very truly yours,

~

8412200049 841213 p

PDR ADOCK 0500030 gf p

Vice Presi e Nuclear Power C. W. Fay Copy to NRC Resident Inspector

(

+

.