ML20100L931

From kanterella
Jump to navigation Jump to search

Provides Amplifying Info Re 841114 Time Extension Request to Complete Upgrading Program for Environ Qualification of Feedwater Regulating Bypass Valves
ML20100L931
Person / Time
Site: Point Beach NextEra Energy icon.png
Issue date: 12/04/1984
From: Britt R
WISCONSIN ELECTRIC POWER CO.
To: Harold Denton, John Miller
Office of Nuclear Reactor Regulation
References
TAC-57389, NUDOCS 8412120142
Download: ML20100L931 (3)


Text

i I%SCORSin Electnc eom couem 231 W. MICHIGAN, P.O BOX 2046 MILWAUKEE, WI 53201 December 4, 1984 Mr. H. R. Denton, Director Office of Nuclear Reactor Regulation U.

S. NUCLEAR REGULATORY COMMISSION Washington, D.

C.

20555 Attention:

Mr. J.

R. Miller, Chief Operating Reactors, Branch 3 Gentlemen:

DOCKET 50-301 ENVIRONMENTAL QUALIFICATION OF FEEDWATER REGULATING BYPASS VALVES POINT BEACH NUCLEAR PLANT, UNIT 2 On November 14, 1984 we submitted a letter to you discussing the environmental qualification upgrade program for the feedwater regulating bypass valves at Point Beach Nuclear Plant, Unit 2.

On November 28, 1984 Mr. Tim Colburn of your staff and Mr. Roger Newton of my staff discussed the content of the letter and its request for a time extension for completing the upgrade program.

This letter provides amplifying information concerning the time extension request.

The need for the environmental upgrade of 2-SV481, which causes the feedwater regulating bypass valve 2-CV481 to shut upon a safety injection system actuation or a high steam generator level condition, was identified in our letter to you dated May 20, 1983.

In that letter a justification for continued operation was provided until the valve upgrade could be completed.

That justification is still valid.

The letter also requested that a time extension "until November 1, 1984 (i.e., the end of the next refueling outage for Unit 2)" be granted.

Your letter dated July 22, 1983 granted this request based on the justification for continued operation provided.

During the November 28 telephone call, Mr. Colburn expressed concern about the timeliness of our November 14 request.

A review of the circumstances leading to the apparent delay provides an explanation for the timing of our extension request.

During the early 1984 refueling outage at Point Beach Nuclear Plant Unit 1 the upgrade of these valves was performed.

Pre-startup testing at that time showed that the closure time of the main feedwater regulating valves, while acceptable from a safety 84121 0142 841204 DRAOCK05000g

) -

M r.- H. '_ R. Denton December 4, 1984 analysis view, warranted improvement.

Initially our design engineers believed one higher capacity solenoid valve could accomplish this

~

and-five solenoid valves were ordered on April 13, 1984. for the upgrade of Unit 2 (two valves for the main feedwater regulating valves, two for the bypass valves, and one spare).

A review of the i

design showed that using two solenoid valves on each main feedwater regulating valve would be.more appropriate, thus creating a need for'six valves for Unit 2.

Additional valves were ordered May 10, 1984.

The supplier estimated a shipping date of September 19, 1984 for these valves.

A follow-up check on the shipment schedule resulted in the' supplier changing the shipment date to the und of October.- This 4

was acceptable because the refueling outage, wh2ch we believed our time extension request was tied to, was then scheduled to end.in mid-November.

In a follow-up phone call towards the end of October, we were' advised by the supplier of another delay until the end of November.

1 At this point my staff. began considering alternatives for meeting the deadline.

One option considered was to install only one qualified solenoid valve on the main feedwater regulating valve-and put the other solenoid valve on the bypass valve.

The second option was to leave the unqualified solenoid valve on the

. bypass valve and have a fast closure time on the main feedwater regulating valve.

The second option was chosen based on the conclusion that the plant would be safer with the main feedwater regulating valve able to perform as designed at all times while at power instead of having a. qualified valve in place on the bypass valve which is used.very little in operation.

After-making and acting upon this decision, we prepared our November 14 letter to the NRC to Anform you of the situation.

We regret this represents some delay after the November l' deadline date; however, we believed that sending

-you a complete description of our problems, including our solution for rectifying the situation and schedule for accomplishing this In the future, we will be more timely i

action, was also important..

in completing such analyses and deliberations and in notifying you of the circumstances well before the expiration of such deadlines.

In summary, we believe that Wisconsin Electric Power Company has in good faith attempted to be timely and continued our strong effort of completing the environmental qualification effort at Point Beach.

Safe ~ operation is assured as explained by our original L

justification for continued operation.

Additionally, the supplier has informed us that the valves were shipped to our facility on December 3.

'9 i - = ~._,

,-,.e%.

o..

_m,,,,,.,

,.~.-__.,,.,.,,.,,,,,...,%y.

_.r.__

,-r,,-g-w.c,-,.

.,,,e

-,,-,-,m,,,n_w--,y-e

,p

_e m m..n,,m-,4,,3,

. *l

- er Mr. H. R. Denton'. December 4, 1984 Should you have any additional questions regarding this. matter,.please contact us.

Very truly yours,

/

/

President R. ' W. Britt Copy to NRC Resident Inspector i

i s

e l

I i

I

. _.... _., _ _ _., _. _. _. _. - - _. _ _. _. -.