Text
,
ARIZONA NUCLEAR POWER PROJECT Post Offica Box 21666 Phoenix, Arizon: 85036 MCGVED L!! 8-51 December 5, 1984
?
ANPP-31330-TDS/LBS U. S. Nuclear Regulatory Commission Region V 1450 Maria Lane - Suite 210 Walnut Creek, California 94596-5368 Attention: Mr. D. F. Kirsch, Acting Director Division of Reactor Safety and Projects
Subject:
Time Extension For Report - DER 84-27 A 50.55(e) Potentially Reportable Deficiency Relating To Improperly Handled Instrumentation From The Waldinger Corporation.
File: 84-019-026; D.4.33.2
Reference:
A) Telephone Conversation between P. Narbut and T. Bridish on May 10, 1984 B) ANPP-29648, dated June 4, 1984 (Interim Report)
C) ANPP-30317, dated August 23, 1984 (Time Extension)
D) ANPP-30665, dated September 26, 1984 (Time Extension)
E) ANPP-30953, dated October 25, 1984 (Time Extension)
F) ANPP-31095, dated November 12, 1984 (Time Extension)
G) ANPP-31219, dated November 26, 1984 (Time Extension)
Dear Sir:
The NRC was notified of a potentially reportable deficiency in Reference (A), an Interim Report was transmitted by Reference (B),
and Time Extensions were requested by References (C), (D), (E), (F), and (G). At that time, it was estimated that a Final Report would be available by December 7,,1984.
Due to the extensive investigation and evaluation required, it is now expected that this information will be finalized by December 14, 1984, at which time a complete report will be submitted.
There is no new information or change to the Interim Report at this time.
Very truly yours,
(
GM g41220]95g0 PDR APS Vice President 20 E. E. Van Brunt, Jr.
Nuclear Production ANPP Project Director EEVB/TRB/nj
/!Q cc: See Page Two yt-29
. ~ =, -
,s
-hY
~r:
Mr. D. F. Kirsch
- DER 84-27 Page TWo a
cc:
Richard DeYoung,_ Director Office.of Inspection and Enforcement U. S. Nuclear Regulatory Commission Washington, D. C.
20555 T. G. Woods, Jr.
D. B. Karner W. E. Ide l
D. B. Fasnacht
' ~ A.fC. Rogers L. A. Souza 4
D. E. Fowler T. D. Shriver C. N. Russo B. S. Kaplan J. R. Bynum J. M. Allen A. C. Gehr W. J. Stubblefield W. G. Bingham R. L. Patterson R. W. Welcher H. D. Foster D. R. Hawkinson R. P. Zimmerman L. Clyde M. Matt T. J. Bloom Records Center Institute of Nuclear Power,0perations 1100 Circle 75 Parkway, Suite 1500 Atlanta, GA 30339 o