Interim Significant Deficiency Rept 414/85-02 Re Defective Safety Injection Sys Accumulator Tanks.Insp of Accumulator Tanks Delayed Until Wk of 850325.Final Rept Will Be Submitted by 850430
ML20100L516
Person / Time
Site: Catawba 
Issue date: 03/20/1985
From: Tucker H
DUKE POWER CO.
To: Grace J
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
References
414-85-02, 414-85-2, NUDOCS 8504170030
Download: ML20100L516 (1)


Text

.._

h DUKE POWER GOMPANY P.O. HOX 33180 CHAHMyrTE, N.C. 28242 HAL H. TUCKER wp,,on 85 M,\\R 26,Ph 503 1985

" " ~

c Dr. J. Nelson Grace, Regional Administrator U. S. Nucicar Regulatory Commission Region 11 101 Marietta Street, NW, Suite 2900 Atlanta, Georgia 30323 RE: Catawba Nuclear Station Unit 2 Docket Nos. 50-414 Significant Deficiency No. 414/85-02

Dear Mr. O'Reilly:

Our corrective action for this deficiency was to include an examination of the inside of the Unit 2 SIS Accumulator Tanks. This inspection was to be completed by March 15, 1985 with a final report to be submitted by March 26, 1985. We have been prevented from completing the inspection due to system testing. This inspection has been rescheduled for the week of the 25th of March. Barring any further delays, the final report will be submitted by April 30, 1985.

Very truly yours, Y

lh

-Hal B. Tucker LTP/mjf cc: Director Mr. Robert Guild, Esq.

Office of Inspection and Enforcement Attorney-at-Law U. S. Nuc1 car Regulatory Commission P. O. Box 12097 Washington, D. C. 20555 Charleston, South Carolina 29412 NRC Resident Inspector Mr. Jesse L. Riley Catawba Nucicar Station Carolina Environmental Study Group Palmetto Alliance 854 Henley Place 2135 Devine Street Charlotte, North Carolina 28207 Columbia, South Carolina 29205 INPO Records Center Suite 1500 1100 Circic 75 Parkway Atlanta, Georgia 30339 8504170030 850320 PDR ADOCK 05000414-S PDR ID arm