EgED Arizona Nuclear Power Project P.o. box 52034 e PHOENIX, ARIZONA 85072-2034 nEG!c 9 V "J November 30, 1984 ANPP-31261-TDS/TRB U. S. Nuclear Regulatory Commission Region V 1450 Maria Lane - Suite 210 Walnut Creek, California 94596-5368 Attention: Mr. D. F. Kirsch, Acting Director Division of Reactor Safety and Projects
Subject:
Time Extension For Report - DER 84-64 A 50.55(e) Potentially Reportable Deficiency Relating To Pipe Support Could Not Be Cycled Through Ent; ire Stroke.
File: 84-019-026; D.4.33.2
Reference:
(A) Telephone conversation between D. Hollenbach and T. Bradish on September 4, 1984 (B) ANPP-30734, dated October 3, 1984 (Interim Report)
(C) ANPP-30993, dated October 29, 1984 (Tice Extension)
(D) ANPP-31150, dated November 15, 1984 (Time Extension)
Dear Sir:
The NRC was notified of a potentially reportable deficiency in Reference (A), an Interim Report was transmitted by Reference (B),
and Time Extensions were requested by References (C) and (D). At that time, it was estimated that a Final Report would be available by November 30, 1984.
Due to the extensive investigation and evaluation required, it is now expected that this information will be finalized by December 12, 1984, at which time a complete report will be submitted.
There is no new information or change to the Interim Report at this time.
Very truly yours, g12110393841130
~
8%%Alx E. E. Van Brunt, Jr.
05000Q APS Vice President S
Nuclear Production ANPP Project Director EEVB/TRB/nj cc See Page Two
\\0
_rE-A7 c
[~
g3 4 :'-
- Mr. D. F. Kirsch DER 84-64 Page Two cc:
Richard DeYoung, Director Office of Inspection and Enforcement U. S. Nuclear Regulatory Commission Washington, D. C.
20555 T. G. Woods, Jr.
D. B. Karner W. E. Ide 4
D. B. Fasnacht A. C. Rogers L. A. Souza D. E. Fowler T. D. Shriver C. N..Russo B. S. Kaplan J. R. Bynum J. M. Allen A. C. Gehr W. J. Stubblefield W. G. Bingham R. L. Patterson R. W.' Welcher II. D. Foster D. R. Hawkinson R. P. Zimmerman L. Clyde M. Matt i
T. J. Bloom Records Center Institute of Nuclear Power Operations 1100 circle 75 Parkway, Suite 1500 Atlanta, GA 30339