Other: A05106, Documents That SPDS at Plant Declared Fully Operational on 870324 After Successfully Completing Various Tests & Operator Training,Per NRC 850727 Order Confirming Util Commitments Re Implementation of Suppl 1 to NUREG-0737, B12306, Forwards Addl Info on SPDS Isolation Devices,Per NRC 860211 Request.Encl Info Describes Addl Testing Performed, B12330, Advises That Util Considers Tests on Isolation Devices of SPDS Described in Successful.Acceptance Criteria for Max Credible Faults Testing to Observe No Measurable Effects on Isolator Input W/Digital Storage Scope, B12386, Forwards Pictures of Inadequate Core Cooling (ICC) Instrumentation Sys Displays That Will Appear on Plant Computer,Spds Displays That Include ICC Info & Keyboard by Which Both SPDS & ICC Displays Accessed,Per 861215 Telcon, ML20100E083, ML20100E095, ML20197B392, ML20197B749
|
MONTHYEARML20100E0831985-03-25025 March 1985 Forwards SPDS SAR & Schedule for Implementation of Spds,Per Suppl 1 to NUREG-0737.Sys Will Be Operational by Nov 1986 If Scheduled Maintained Project stage: Other ML20100E0951985-03-31031 March 1985 SPDS Sar,Millstone Nuclear Power Station,Unit 2 Project stage: Other ML20153H0811986-02-11011 February 1986 Forwards Request for Addl Info within 60 Days Re Spds,To Continue Review of 850325 Submittal Project stage: RAI A05577, Forwards Response to 860211 Request for Addl Info on SPDS Beyond Info in .Device Used to Electrically Isolate Described.Verifies Max Credible Faults,Pass/Fail Acceptance Criteria & Environ Qualification Compliance1986-07-31031 July 1986 Forwards Response to 860211 Request for Addl Info on SPDS Beyond Info in .Device Used to Electrically Isolate Described.Verifies Max Credible Faults,Pass/Fail Acceptance Criteria & Environ Qualification Compliance Project stage: Request ML20203K2581986-07-31031 July 1986 Forwards Response to 860211 Request for Addl Info on SPDS Beyond Info in .Device Used to Electrically Isolate Described.Verifies Max Credible Faults,Pass/Fail Acceptance Criteria & Environ Qualification Compliance Project stage: Request ML20197B3921986-10-0808 October 1986 Forwards Addl Info Re Suppl 1 to NUREG-0737 Concerning SPDS, Per NRC 860625 Request.Rev 1 to SAR Also Encl Project stage: Other B12306, Forwards Addl Info on SPDS Isolation Devices,Per NRC 860211 Request.Encl Info Describes Addl Testing Performed1986-10-24024 October 1986 Forwards Addl Info on SPDS Isolation Devices,Per NRC 860211 Request.Encl Info Describes Addl Testing Performed Project stage: Other ML20197B7491986-10-31031 October 1986 Rev 1 to SAR Re Suppl 1 to NUREG-0737 Concerning SPDS Project stage: Other B12330, Advises That Util Considers Tests on Isolation Devices of SPDS Described in Successful.Acceptance Criteria for Max Credible Faults Testing to Observe No Measurable Effects on Isolator Input W/Digital Storage Scope1986-11-17017 November 1986 Advises That Util Considers Tests on Isolation Devices of SPDS Described in Successful.Acceptance Criteria for Max Credible Faults Testing to Observe No Measurable Effects on Isolator Input W/Digital Storage Scope Project stage: Other B12386, Forwards Pictures of Inadequate Core Cooling (ICC) Instrumentation Sys Displays That Will Appear on Plant Computer,Spds Displays That Include ICC Info & Keyboard by Which Both SPDS & ICC Displays Accessed,Per 861215 Telcon1986-12-23023 December 1986 Forwards Pictures of Inadequate Core Cooling (ICC) Instrumentation Sys Displays That Will Appear on Plant Computer,Spds Displays That Include ICC Info & Keyboard by Which Both SPDS & ICC Displays Accessed,Per 861215 Telcon Project stage: Other A05106, Documents That SPDS at Plant Declared Fully Operational on 870324 After Successfully Completing Various Tests & Operator Training,Per NRC 850727 Order Confirming Util Commitments Re Implementation of Suppl 1 to NUREG-07371987-06-0101 June 1987 Documents That SPDS at Plant Declared Fully Operational on 870324 After Successfully Completing Various Tests & Operator Training,Per NRC 850727 Order Confirming Util Commitments Re Implementation of Suppl 1 to NUREG-0737 Project stage: Other ML20215H8291987-06-18018 June 1987 Ack Receipt of Containing Comments Re NRC 870212 Safety Evaluation on Facility Spds.Comments Do Not Change Conclusions of Safety Evaluation.Implementation of SPDS May Continue Project stage: Approval 1986-11-17
[Table View] |
Forwards SPDS SAR & Schedule for Implementation of Spds,Per Suppl 1 to NUREG-0737.Sys Will Be Operational by Nov 1986 If Scheduled Maintained| ML20100E083 |
| Person / Time |
|---|
| Site: |
Millstone  |
|---|
| Issue date: |
03/25/1985 |
|---|
| From: |
Bishop R, Counsil W NORTHEAST NUCLEAR ENERGY CO., NORTHEAST UTILITIES |
|---|
| To: |
John Miller Office of Nuclear Reactor Regulation |
|---|
| Shared Package |
|---|
| ML20100E086 |
List: |
|---|
| References |
|---|
| RTR-NUREG-0737, RTR-NUREG-737, TASK-1.D.2, TASK-TM A02959, A04121, A2959, A4121, TAC-51257, NUDOCS 8504030267 |
| Download: ML20100E083 (4) |
|
Text
}
x w
o gg Generat Offices e Selden Street, Berlin, Connecticut w cowcw m mo m cow."
P.O. BOX 270 HARTFORD. CONNECTICUT 06141-0270
.aos.m..o.w. co.
(203) 666-6911 w"
as u a cow.-
L g
March 25,1985 Docket No. 50-336 A02959 A04121 Director of Nuclear Reactor Regulation Attn:
Mr. James R. Miller Operating Reactors Branch #3 U.S. Nuclear Regulatory Commission Washington, D.C. 7.0555
References:
(1) :1. R. Miller letter to W. G. Counsil, dated June 14, 1984.
(2)
W. G. Counsil letter to D. G. Eisenhut, dated November 28, 1983.
Gentlemen:
Millstone Nuclear Power Station, Unit No. 2 Supplement I to NUREG-0737 Safety Parameter Display System Safety Analysis Report By Reference (1), the NRC issued an Order confirming various commitments made by Northeast Nuclear Energy Company (NNECO) on behalf of Millstone Unit No. 2 regarding the implementation of Supplement I to NUREG-0737. This Order requires the submittal by March 25, 1985 of the Safety Parameter Display System (SPDS) Safety Analysis Report (SAR) and a schedule for the implementation of the SPDS. Accordingly, we hereby submit the SPDS SAR for Millstone Unit No. 2.
In addition, we commit to implement (including operator training) the SPDS defined in the attached SAR prior to the start of Cycle 8 or by March 25,1987, whichever is later.
The major milestones and their associated target dates for the implementation of the Millstone Unit No. 2 SPDS are included in Attachment No.1. It is worth noting that, if this schedule is maintained, the SPDS will be operational by November, 1986. However, only the completion date provided above, which allows for any uncertainties in our schedule and for the unexpected, is considered a firm date. Attachment No. I supersedes the SPDS implementation schedule previously provided in Attachment No. 4 in Reference (2).
It is our understanding, per handouts received at the February 22, 1983 regional workshop on Supplement I to NUREG-0737, that the NRC Staff will indicate l
acceptance of the SPDS SAR within approximately two (2) months.
l 0504030267 850325 PDR ADOCK 05000336 d
y)-
F PDR q.~ d
r v
q
. The SPDS SAR in Attachment No. 2 includes a safety evaluation in accordance with 10CFR50.59. However, this evaluation has not been reviewed and approved by the Plant Operations Review Committee (PORC) or the off-site Nuclear Review Board (NRB). The PORC and NRB reviews will occur as required by our normal plant design change process.
We trust that this submittal complies with the requirements of Reference (1).
Very truly yours, NORTHEAST NUCLEAR ENERGY COMPANY b k boamt W. G. Counsil Senior Vice President W
Ce x
/
By: K. W. Bishop ~
Secretary e
a
Docket No. 50-336 Attachment No.1 Millstone Nuclear Power Station, Unit No. 2 SPDS Implementation Milestones March,1985 4
e SPDS Implementation Milestones Milestone Target Date Start SPDS Design February,1985 Submit Safety Analysis Report March,1985 Complete Safety Function Algorithms June,1985 Complete Display Design July,1985 Complete Signal Validation Algorithms August,1985 Complete SPDS Functional Specification September,1985 Install and Test Hardware July,1986 Start Cycle 7 Refueling Outage August,1986 Start of Cycle 8; SPDS Operational November,1986 i
i r