ML20100E083

From kanterella
Jump to navigation Jump to search

Forwards SPDS SAR & Schedule for Implementation of Spds,Per Suppl 1 to NUREG-0737.Sys Will Be Operational by Nov 1986 If Scheduled Maintained
ML20100E083
Person / Time
Site: Millstone Dominion icon.png
Issue date: 03/25/1985
From: Bishop R, Counsil W
NORTHEAST NUCLEAR ENERGY CO., NORTHEAST UTILITIES
To: John Miller
Office of Nuclear Reactor Regulation
Shared Package
ML20100E086 List:
References
RTR-NUREG-0737, RTR-NUREG-737, TASK-1.D.2, TASK-TM A02959, A04121, A2959, A4121, TAC-51257, NUDOCS 8504030267
Download: ML20100E083 (4)


Text

x

}

w o gg Generat Offices e Selden Street, Berlin, Connecticut w cowcw m mo m cow."

P.O. BOX 270

.aos .m. .o.w. co. HARTFORD. CONNECTICUT 06141-0270 g w" as u a cow.- (203) 666-6911 L

March 25,1985 Docket No. 50-336 A02959 A04121 Director of Nuclear Reactor Regulation Attn: Mr. James R. Miller Operating Reactors Branch #3 U.S. Nuclear Regulatory Commission Washington, D.C. 7.0555

References:

(1) :1. R. Miller letter to W. G. Counsil, dated June 14, 1984.

(2) W. G. Counsil letter to D. G. Eisenhut, dated November 28, 1983.

Gentlemen:

Millstone Nuclear Power Station, Unit No. 2 Supplement I to NUREG-0737 Safety Parameter Display System Safety Analysis Report By Reference (1), the NRC issued an Order confirming various commitments made by Northeast Nuclear Energy Company (NNECO) on behalf of Millstone Unit No. 2 regarding the implementation of Supplement I to NUREG-0737. This Order requires the submittal by March 25, 1985 of the Safety Parameter Display System (SPDS) Safety Analysis Report (SAR) and a schedule for the implementation of the SPDS. Accordingly, we hereby submit the SPDS SAR for Millstone Unit No. 2. In addition, we commit to implement (including operator training) the SPDS defined in the attached SAR prior to the start of Cycle 8 or by March 25,1987, whichever is later.

The major milestones and their associated target dates for the implementation of the Millstone Unit No. 2 SPDS are included in Attachment No.1. It is worth noting that, if this schedule is maintained, the SPDS will be operational by November, 1986. However, only the completion date provided above, which allows for any uncertainties in our schedule and for the unexpected, is considered a firm date. Attachment No. I supersedes the SPDS implementation schedule previously provided in Attachment No. 4 in Reference (2).

It is our understanding, per handouts received at the February 22, 1983 regional l workshop on Supplement I to NUREG-0737, that the NRC Staff will indicate acceptance of the SPDS SAR within approximately two (2) months.

l 0504030267 850325 y)-

PDR ADOCK 05000336 d .

q.~ d F PDR

v r q The SPDS SAR in Attachment No. 2 includes a safety evaluation in accordance with 10CFR50.59. However, this evaluation has not been reviewed and approved by the Plant Operations Review Committee (PORC) or the off-site Nuclear Review Board (NRB). The PORC and NRB reviews will occur as required by our normal plant design change process.

We trust that this submittal complies with the requirements of Reference (1).

Very truly yours, NORTHEAST NUCLEAR ENERGY COMPANY b k boamt W. G. Counsil Senior Vice President

/

W Ce x '

By: K. W. Bishop ~

Secretary e

a

Docket No. 50-336 Attachment No.1 Millstone Nuclear Power Station, Unit No. 2 SPDS Implementation Milestones March,1985 4

,- e SPDS Implementation Milestones Milestone Target Date Start SPDS Design February,1985 Submit Safety Analysis Report March,1985 Complete Safety Function Algorithms June,1985 Complete Display Design July,1985 Complete Signal Validation Algorithms August,1985 Complete SPDS Functional Specification September,1985 Install and Test Hardware July,1986 Start Cycle 7 Refueling Outage August,1986 Start of Cycle 8; SPDS Operational November,1986 i