e o

Omaha Public Power District l

1623 Harney Omaha. Nebraska 68102 l

402/536 4000 October 10, 1984 L IC-84-342 Mr. D. R. Hunter, Chief Reactor Project Branch 2 U.S. Nuclear Regulatory Commission Region IV 611 Ryan Plaza Drive, Suite 1000 Arlington, Texas 76011

Reference:

Docket No. 50-285

Dear Mr. Hunter:

IE Inspection Report 84-17 The District has received the subject report dated September 11, 1984.

In order to provide a complete response to the notices of violation, the Dis-trict requests an extension of the schedule for submitting its response to October 25, 1984. This request and schedule is consistent with information discussed between Mr. Ray Hall of your office and K. J. Morris of my office on October 10, 1984.

Sinc : ely, Div sion Ianager M@MOWM V Nuclear Production RLA/JJF/rh-Y glg cc:

LeBoeuf, Lamb, Leiby & MacRae p

1333 New Hampshire Avenue, N.W.

Washington, D.C.

20036 Mr. E. G. Tourigny, NRC Project Manager Mr. L. A. Yandell, Senior Resident Inspector 0412030162 841029 PDR ADOCK 05000285 O

PDR 45 Si2d Employmen h qual opportunity

.