MONTHYEARML23355A1722024-01-17017 January 2024 Meeting Transcript - Proposed Rule: Regulatory Framework for Fusion Systems, Teleconference, January 17, 2024, Pages 1-123 ML24009A2232023-12-21021 December 2023 Environmental Meeting Related to the Comanche Peak Nuclear Power Plant Draft Supplemental Environmental Impact Statement, Units 1 and 2, License Renewal Application - 12/21/23 Webinar ML24009A2142023-12-0707 December 2023 Public Meeting on the Comanche Peak Nuclear Power Plant Draft Supplemental Environmental Impact Statement, Units 1 and 2, License Renewal Application - 12/07/23 Webinar ML23258A1812023-11-0909 November 2023 Transcript November 9, 2023 Public Meeting - Fusion Systems Proposed Rule ML23331A0052023-11-0808 November 2023 Official Transcript of November 8, 2023, Cer Public Meeting on Renewing Nuclear Power Plant Operating Licenses - Environmental Review ML23319A2602023-10-25025 October 2023 10-25-2023 Public Meeting Transcript - Increased Enrichment Regulatory Basis ML23108A3132023-04-18018 April 2023 March 22, 2023, Monticello Nuclear Generating Plant, Unit 1, Subsequent License Renewal Application Public Environmental Scoping Meeting Transcript ML23108A3182023-04-18018 April 2023 March 29, 2023, Monticello Nuclear Generating Plant, Unit 1, Subsequent License Renewal Application Public Environmental Scoping Webinar Teams Transcript ML23081A5082023-02-23023 February 2023 Transcript of Environmental Scoping Meeting Related to the Comanche Peak Nuclear Power Plant, Units 1 and 2, License Renewal Application, Pages 1-92 ML23037A0212023-01-25025 January 2023 Official Transcript of Environmental Scoping Meeting for an Application for a Special Nuclear Material License for the TRISO-X Proposed Fuel Fabrication Facility at Oak Ridge, Pages 1-54 ML23054A0012023-01-25025 January 2023 Public Meeting Transcript Regarding the Alternatives to the Use of Credit Ratings, Pages 1-31 ML23031A0962023-01-17017 January 2023 Transcript of January 17, 2023 Environmental Scoping Meeting Related to the Comanche Peak Nuclear Power Plant, Units 1 and 2, License Renewal Application ML22318A1982022-11-0303 November 2022 November 3, 2022, DRP Workshop Meeting Transcript (Official Court Reporter) ML22277A0022022-10-0404 October 2022 Public Meeting Transcript for Regulatory Improvements for Production and Utilization Facilities Transitioning to Decommissioning, Pages 1-81 ML22277A0102022-10-0404 October 2022 Public Meeting Transcript for Regulatory Improvements for Production and Utilization Facilities Transitioning to Decommissioning ML22201A0172022-06-22022 June 2022 Public Meeting Transcript Regarding the Discussion of Proposed Rulemaking on Increased Enrichment of Conventional and Accident Tolerant Fuel Designs for Light-water Reactors (Corrected) ML22277A0042022-04-12012 April 2022 Public Meeting Transcript for Regulatory Improvements for Production and Utilization Facilities Transitioning to Decommissioning ML22277A0002022-03-21021 March 2022 Public Meeting Transcript for Regulatory Improvements for Production and Utilization Facilities Transitioning to Decommissioning ML22024A0642022-01-20020 January 2022 Transcript of Rulemaking: Alternative Physical Security Requirements for Advanced Reactors Public Meeting, January 20, 2022, Pages 1-72 ML21341B4512021-11-0404 November 2021 11/4/2021 Transcript of Public Meeting to Discuss the Proposed Rulemaking on Reporting Requirements for Nonemergency Events at Nuclear Power Plants - Pages 1-66 ML22103A0602021-09-28028 September 2021 PSDAR Meeting Transcript - September 28, 2021 ML21273A1052021-09-15015 September 2021 Public Meeting Transcript, Part 53, Subpart I, Maintaining and Revising Licensing Basis Information, 53.1322-Evaluating Changes to Facility as Described in Final Safety Analysis Reports, & Discussion of Other Recent Proposed Rule Language ML21245A4282021-08-26026 August 2021 Transcript of Public Meeting Webinar to Receive Comments on the Draft Environmental Impact Statement for the Westinghouse Columbia Fuel Fabrication Facility License Renewal ML21238A0102021-08-18018 August 2021 Transcript for Virtual Public Meeting Held on August 18, 2021, Regarding Indian Point Energy Center Post-Shutdown Decommissioning Activities Report ML21166A2332021-06-10010 June 2021 Public Meeting Transcript Meeting on 10 CFR Part 53 Licensing and Regulation of Advanced Nuclear Reactors Subpart F and 10 CFR Part 73 Emergency Preparedness and Security Preliminary Proposed Rule Language ML21167A2132021-06-0909 June 2021 IMC 2602 Public Meeting Transcript from June 9, 2021 Meeting Titled - Modernization of the Fuel Cycle and Materials Decommissioning Inspection Program ML21096A0112021-04-13013 April 2021 Public Meeting Transcript for Fitness for Duty Drug Testing Requirements Final Rule; Part 26, Cumulative Effects of Regulation Public Meeting ML21106A0042021-04-0808 April 2021 Public Meeting Transcript to Discuss the Part 53 Risk Informed, Technology Inclusive Regulatory Framework for Advanced Reactors Rulemaking Subpart E Rule Language and Revised Preliminary Rule Language ML21061A0302021-02-11011 February 2021 Transcript from February 11, 2021 NRC Public Meeting on Uniform Waste Manifest ML21062A1122021-02-0404 February 2021 Public Meeting Transcript 10 CFR Part 53 Licensing and Regulation of Advanced Nuclear Reactors Objectives and Structure and Subpart D Preliminary Proposed Rule Language ML21026A3432021-01-0707 January 2021 Transcript of 01/07/2021 Public Meeting to Discuss Approaches for Rulemaking on Decommissioning Financial Assurance Requirements for Sealed and Unsealed Radioactive Materials ML20336A1802020-11-18018 November 2020 Category 3 Public Meeting Transcript 10 CFR Part 53 Licensing and Regulation of Advanced Nuclear Reactors Subpart B Preliminary Proposed Rule Language ML20330A2382020-10-20020 October 2020 NAC Pec Transcript of October 20, 2020 Pre-Decisional Enforcement Conference ML20252A1712020-09-0202 September 2020 Transcript of the Public Online Webinar for the Draft Environmental Impact Statement for the Proposed Holtec Hi-Store Consolidated Interim Storage Facility - September 2, 2020 ML20189A1152020-06-24024 June 2020 Public Watchdogs 10 CFR 2.206 Petition - Transcript of Public Meeting Between Petitioner and the NRC Petition Review Board, June 24, 2020, Pages 1-39 ML20180A0002020-06-23023 June 2020 Transcript of Proceedings - Public Online Webinar for the Draft Environmental Impact Statement for the Proposed Holtec Hi-Store Consolidated Interim Storage Facility, June 23, 2020, Pages 1-202 ML20140A3702020-04-30030 April 2020 Final Transcript of the Advisory Committee on the Medical Uses of Isotopes (ACMUI) April 30, 2020 Teleconference Meeting, Pages 1-49 ML20099B3392020-03-30030 March 2020 Category 3 Meeting on Draft Interpretive Rule for Very Low Level Waste (Vllw) Disposal Activities ML20099B3402020-03-30030 March 2020 Transcript of Category 3 Meeting on Draft Interpretive Rule for Very Low Level Waste (Vllw) Disposal Activities, Meeting 03/30/2020, Pages 1-80 ML20099B3382020-03-30030 March 2020 Category 3 Meeting on Draft Interpretive Rule for Very Low Level Waste (Vllw) Disposal Activities ML20092G6672020-03-0909 March 2020 Transcript Independent Spent Fuel Storage Installation (ISFSI) Inspection Enhancement Initiative Recommendations Category 3 Public Meeting, March 9, 2020, Pages 1-59 ML19344A4192019-11-21021 November 2019 Transcript of Rulemaking to Align Licensing Processes and Apply Lessons Learned from New Reactor Licensing: 11/21/19 Public Meeting Transcript & Slides (NRC-2009-0196) ML19336A0042019-11-0707 November 2019 11/7/2019 - Meeting Transcript for Fitness for Duty Drug Testing Requirements Rulemaking ML19319B6772019-10-30030 October 2019 Dodd-Frank Public Meeting Transcript on October 30, 2019 Re Alternatives to Use Credit Ratings Proposed Rulemaking. Part 2 of 2 ML19319B6762019-10-30030 October 2019 Dodd-Frank Public Meeting Transcript on October 30, 2019 Re Alternatives to Use Credit Ratings Proposed Rulemaking. Part 1 of 2 ML19284B5742019-10-24024 October 2019 Official Transcript of Proceedings for NEIMA-Kewaunee Meeting Dated 9/24/2019 ML19295G5272019-10-10010 October 2019 Transcript for Public Meeting to Discuss Citizen Advisory Board Best Practices Held Near the Crystal River Nuclear Plant on October 10, 2019 ML19318G4382019-10-0505 October 2019 NEIMA Meeting Transcript ML19317D0772019-09-10010 September 2019 NEIMA Meeting Transcript ML20112F1792019-08-29029 August 2019 Testimony of Prof. David G. Victor, Chairman of the San Onofre Community Engagement Panel 2024-01-17
[Table view]Some use of "" in your query was not closed by a matching "". |
Text
Record of WebEx Q&A Session NUCLEAR REGULATORY COMMISSION
Title:
Category 3 Meeting on Draft Interpretive Rule for Very Low-level Waste (VLLW)
Disposal Activities Docket Number: (n/a)
Location: Teleconference / Webinar Date: Monday, March 30, 2020 Earl Fordham - 11:01 AM Q: How do you take into account say 50 years of rad waste at an "authorized recipient?"
Marlayna Doell - 11:07 AM A: Thanks Earl. I will note your question to the speakers.
Martin Karr - 11:16 AM Q: How much time and/or cost does NRC expect from the licensee, disposal facility, and NRC for preparation, review and approval for this process?
Marlayna Doell - 11:24 AM A: Thanks Martin. We will add this to the list of comments/considerations for next steps.
1
Vern Rogers - 11:16 AM Q: If Agreement States seek to grant exemptions per 20.2001, what public information should be required to be disclosed so that an informed comment can be provided?
Marlayna Doell - 11:25 AM A: Thanks Vern. I will add this to our list of comments/considerations for moving forward with this topic.
Marcus Quinlan - 11:17 AM Q: Will the evaluated cumulative dose from all disposal include a dose from radon?
Marlayna Doell - 11:27 AM A: Thanks Marcus. I will add this to our list of comments/considerations for moving forward with this topic.
Vern Rogers - 11:18 AM Q: How does the proposed interpretative rule impact governance by the LLRW Compact system? If exempted from licensed disposal, would a licensee be exempt from LLRW Compact requirements?
Marlayna Doell - 11:29 AM A: Thanks for this too Vern!
Holly Harris - 11:22 AM Q: Snake River Alliance in Idaho uniformly opposes both the substantive and procedural aspects of this effort. At a minimum, NRC should not proceed with this reckless proposal when the public cannot participate due to the international COVID-19 health crisis!
Marlayna Doell - 11:35 AM A: Thanks Holly. I will add this to our list of comments/considerations for moving forward with this topic.
Jim Lieberman - 11:22 AM Q: 1) will the NRC require the performance objectives of Part 61 be met?
Jim Lieberman - 11:24 AM Q: 2) since RCRA sites need not be owned by a government after closure, how will the intruder be assessed?
Jim Lieberman - 11:24 AM Q: 3) how will the NRC monitor compliance with the terms of the exemption?
Jim Lieberman - 11:25 AM Q: 4) why not license these facilities rather than the use of exemptions?
2
Marlayna Doell - 11:37 AM A: Thanks Jim. I will add these to our list of comments/considerations for moving forward with this topic.
Earl Fordham - 11:25 AM Q: Did the public comment period get extended? I was told the NRC hoped to have a decision by this meeting.
Marlayna Doell - 11:39 AM A: Hi Earl. We will address this at the end, but yes we are considering an extension and should determine the duration after this meeting.
Laura Schwartz - 11:27 AM Q: Process question for today - will NRC panelists be answering questions today, or just taking questions and comment without answering?
Jim Lieberman - 11:27 AM Q: 5) how does this proposal differ from the process envisioned by the notice of proposed rulemaking issued in the 2002/3 period?
Lynn Anderson - 11:30 AM Q: UNACCEPTABLE TO EXEMPT Here in Youngstown, Ohio: PA's Marcellus fracking waste with Radium 226 and Radium 228 has been trucked in and downblended in the open air, then trucked to Poland Landfill where it set off alarms NEED MORE REGULATION, PROTECTION!
Marlayna Doell - 11:40 AM A: Thanks Lynn. I will add this to our list of comments/considerations for moving forward with this topic.
Pat Marida - 11:35 AM Q: Are you at the NRC planning to track where all this waste will be going, so your grandchildren and great grandchildren can avoid the birth defects, cancers and anemia that will affect the rest of us?
Marlayna Doell - 11:40 AM A: Thanks Pat. I will add this to our list of comments/considerations for moving forward with this topic.
Lleonard Slosky - 11:36 AM Q: Given the current work environment a significant extension to the comment period should be granted. Submitted by the Rocky Mountain LLW Compact Marlayna Doell - 11:44 AM A: Thanks Leonard. We will address this at the end, but yes we are considering an extension and should determine the duration after this meeting.
3
Dan Shrum - 11:37 AM Q: Several commenters have mentioned that there is no e-mail address. The FRN provides an e-mail address - is that address only valid for questions about the FRN?
Marlayna Doell - 11:45 AM A: Hi Dan. The email address is indeed primarily for asking questions and not submitting comments. We prefer that the comments come in over regulations.gov whenever possible.
Vern Rogers - 11:39 AM Q: NRC discussed transparency by authorized recipient on what could be accepted. How will NRC and Agreement states ensure transparency?
Charma Waring - 11:42 AM Q: What measures would be put in place to prevent access to the waste sites by the public?
What would stop individuals from gaining access to the materials and prevent them form using the material and using it to make Radiological Dispersal Devices?
Marlayna Doell - 11:46 AM A: Thanks Charma. I will add this to our list of comments/considerations for moving forward with this topic.
Lynn Anderson - 11:42 AM Q: Yes, Attorney Terry Lodge is correct, the radium from fracking is accumulating here and we already have ENOUGH of a TOXIC load! We have a LOT of cancer here now, and do not need it to keep increasing!
Lynn Anderson - 11:44 AM Q: Sounds like Tennessee and Texas need to get some regulations to protect their citizens. We do NOT need a "race to the bottom!"
Steve Erickson - 11:45 AM Q: How will this proposed change affect processing and disposal of "alternate feed material"?
How will this affect the roles of other federal agencies' review and permitting of waste disposal facilities (e.g. Army Corps of Engineers 404 permits)? What requirements will be put in place for post-closure clean up and assurance.
Marlayna Doell - 11:48 AM A: Thanks Steve. I will add these to our list of comments/considerations for moving forward with this topic.
Steve Erickson - 12:04 PM Q: How does the NRC expect state and local regulatory authorities to inspect, oversee, and assure compliance with other state and local rules, statutes and standards?
4
Steve Erickson - 12:06 PM Q: Doesnt this amount to an unfunded mandate and a federal usurpation of state regulatory primacy?
John Greeves - 12:10 PM Q: What is NRC definition of VLLW?
Priority: N/A-Marlayna Doell - 12:13 PM A: Thanks John. This is a topic we want to address in the proposed interpretive rule, so I will make sure this comment is added to the list.
John Greeves - 12:12 PM Q: Reopening the Disposition of Solid Materials rulemaking back in 2004 would be a better approach.
Marlayna Doell - 12:16 PM A: Good comment. Thanks for this as well.
Lynn Anderson - 12:18 PM Q: Yes, Ms. Martinez! Work for Humanity, not the profits of the nuclear industry!
John Greeves - 12:18 PM Q: This proposal will undermine currently licensed disposal sites.
Jim Lieberman - 12:33 PM Q: 5) If a site-specific analysis will need to be made, why not just issue a license?
Marlayna Doell - 12:43 PM A: Thanks Jim...I will add this to the comment list.