ML20098A823

From kanterella
Jump to navigation Jump to search
Responds to NRC Ltr Re Violations Noted in Insp Repts 50-277/84-02 & 50-278/84-02.Corrective Actions:Backlog of Drawing Revs Will Be Eliminated by June 1985 & Mods Will Be Made in Areas of Organizational Changes
ML20098A823
Person / Time
Site: Peach Bottom  
Issue date: 04/04/1984
From: Cooney M
PECO ENERGY CO., (FORMERLY PHILADELPHIA ELECTRIC
To: Martin T
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
References
IEB-79-02, IEB-79-14, IEB-79-2, NUDOCS 8409250257
Download: ML20098A823 (9)


Text

-

i:

~q,

t i

LM L PHILADELPHIA ELECTRIC COMPANY 23ol MARKET STREET P.O. BOX 8699 PHILADELPHIA. PA.191o1 (215) 841-5020

.."15$.."." '

.-,:m"";"*::::=-, -

April 4, 1984 Docket Nos. 50-277 50-278 IMr. Thomas T. Martin, Director-Division of Engineering & Technical Programs U.' S. ; Nuclear Regulatory Commission l

Region I~

631 Park Avenue King of. Prussia, PA.19400

Dear.Mr. Martin:

Your letter of February 15, 1984,. forwarded Combined-f

. Inspection Report 50-277/84-02 and: 50-278/84-02.

Theneed for

.Edelayed submittal;was discussed with Dr. L. H. Bettenhausen of-your. staff-and found' acceptable ~.. Appendix A addresses severall

. items which do not appear to be in full compliance with Nuclear t

Regulatory Commission requirements.- These items are restated below along with our response.

Peach Bottom A tomic Power = Station Units 2 and 3 Technical ~ Specification-Section 6.8.1 states: " Written procedures and administrative policies shall be established, implemented and

-maintained that meet the requirements'of..... Appendix.'A' of

'USAEC Regulatory Guide 1.33 (November 1972)...."

USAEC-

. Regulatory. Guide'l.33 (November 1972) Appendix - A, Paragraph I.5,

discusses General Procedures for the' control of modification work; 1 Administrative-Procedure A-14 (Rev. 9) implements the
above' requirement.

-. Contrary to the above,-the-implementation of the

-Administrative Procedure-was inadequate in that:-

1.- 'The drawing revisions for'several modifications were not completed (for example, completed modifications MOD 21, MOD E

& R 510, MOD 576, and MOD 655, issued prior-to 1982).

~

8409250257 840404 gDRADOCK 05000277 PDR ii J CL 00 j

?

.n 3

f

.,a l%-

c

.v E

Mr. Thomah T. Martin Page~2

.2.

-The Main enance Request Forms-for several modifications were not comple,ted'and returned to the Assistant Modification

. Coordinator for close out (for example, completed modifications MOD 270, MOD.271, and MOD 437 issued prior to

. 1979)..

3..

The' carbon con' tent in the piping.for~ MOD 389, Core Spray Piping' replacement,.was incorrectly recorded on the construction drawings (lll87-022-M-415' Series).

4.

The response times of the installed containment pressure indicator channels were not measured to assure that the actual response times are consistent with the design assumptions.

5.

--A revision to Procedure A-14, initiated in 1981 to address concerns raised by the NRC and the licensee's audits, was.not completed.

6.

A training program wat not established for the Assistant Modification Coordinator in accordance with the requirements-of ANSI N45.2.ll (committed by. the licensee's Quality Assurance Program Description).

'7.

The corrected Plant Modification Control Sheet (PMCS) for

. Modification 510 was.not maintained in'accordance with the

' licensee's letter dated April 28, 1980.

The above collectively constitutes a Severity Level IV Violation (Supplement 'I) Japplicable to both DPR-44 and DPR-56.

Response

ITEM 1 Philadelphia Electric Company has been concerned about the need to expeditiously update modification drawings for some time.

In August 1982,<a special branch was formed within our Engineering Design Division to expedite the drawing revision process.. At that tina, the major workload was related to the investigative efforts associated with I.E.'Bulletins 79-02 and 79-14.

Mere recently, as a result of NRC commentary and our internal

-auditing, we have revised our procedures to remove certain administrative and technical review sign-offs in the interest of

-expediting revisions.

Further, we have subdivided the revision workload into those that-are of particular interest to personnel 2in operating the plants and those of a construction / design k

4 j

l Mr. Yhoma's T. Martin Page 3 orientation.

The piping and. instrument drawings (P&ID's) and electrical. single diagrams, which are of keen interest to the operating staff, are essentially up-to-date and will continue to receive the highest priority.

In order to expedite the.as-built revisions for the balance of the mechanical and electrical drawings, this dedicated group of designers, currently numbering 14, will be expanded by the

. reassignment of manpower, temporary use of contractors, and the use of overtime where necessary.

We estimate that the current backlog of drawing revisions will be eliminated by June 1985.

Additionally, the necessary manpower will be assigned to future revisions 1to preclude the creation of another significant backlog.

' ITEM =2

~ Modification packages are held open until the Maintenance Request Forms (MRF 's) are reviewed in the Modification Coordinator office.

There are current.'y estimated to be 425 outstanding modification packages.

In many cases, to complete the

. modification package, an extensive search must be performed to locate the original completed MRF's.

In order to closecut the backlog of open modification packages, additional manpower will be utilized to close out already completed modifications.

The task of completing these modification packages will be performed by search to locate the original completed MRF's.

If the original completed MRF for an open, but completed modification, cannot be located within a reasonable time, the modification package will be closed by verification that the information contained in the' Plant Modification Control Sheet (PMCS) in Plant Modification Control Administrative Procedure A-14 has been

. satisfactorily performed.

Additionally, walkdowns will be performed on-selected completed modifications as required by the Modification Coordinator in order to close out the modification package.

The expected completion date to eliminate the present backlog of open modifications is October 1, 1985.

The Computerized History and Maintenance Planning System (CHAMPS) is now being utilized in place of the hardcopy MRF system.

CHAMPS will hasten the Modification Office MRF recovery process for newly initiated modifications, thus permitting prompt closing of modification packages after the work is completed.

ITEM 3 The construction drawings ll187-022-M-415 series were reviewed with respect to identifying changes relative to carbon content in J

~

s Mr. Thomas T. Martin Page 4 the piping for MOD 389'.

We have identified that the proper recording of carbon content on the core spray piping drawings for MOD 389 were completed on July 2, 1982, on the drawings listed below:

M 415 - 122 - 4 M 415 - 123 - 3 M 415 - 124 - 4 M 415 - 135 - 3 M 415 - 126 - 3 M 415 - 127 - 4 M'415 - 128 - 3 M 415 - 129 - 3 M 415 - 130 - 4 M 415 - 131 - 3 M 415 - 131 - 3 M 415 - 132 - 3 M 415 - 133 - 5 These revised drawings were available in the station files at the time of the inspection.

However, both the Assistant Modification Coordinator and the inspector did not review these specific prints that properly documented the carbon content.

The drawings that were provided for the inspection were outdated construction prints which were.in the process of being archived.

At the time of the inspection, moving of the Assistant Modification Coordinator and modification files into Peach Bottom's new administration building caused difficulty in locating the proper MOD 389 drawings.

ITEM 4 At the time the Design Input was written (Oct. 1980), the applicable Nuclear Regulatory Commission requirement was a Sept.

5, 1980 letter, " Preliminary Clarification of TMI Action Plan Requirements."

In this letter, "the response time of the containment pressure monitoring channels shall have a time constant of less than 1 second," is specified.

This was incorporated into the Design Input.

NUREG-0737, " Clarification of'TMI Action Plan Requirements",

was issued in November 1980.

The-requirement was changed to "the accuracy and response time specification of the pressure monitor shall be provided and justified _to be adequate for their intended functions."

As noted in the inspection report, the NRC, on September 7,

1983, issued a Safety Evaluation Report (SER) approving the response time for containment pressure indication.

This approval was based on a response time for individual components of the

Mr. Thomno T. Martin Page 5 instrument channel, which were submitted to the NRC by PECo on March 4, 1983.

The NRC had computed an overall channel response

. time and specifically stated in a letter from J.

F.

Stolz, USNRC, to E. G. Bauer, PECo, dated January 5, 1983, that PECo was not to attempt to calculate-a. response time.

This overall response time was furnished to PECo in( the NRC in the September 7, 1983 SER.

Response time testing was not performed, as it was no longer required by NUREG-0737.

This item was identified by the Philadelphia Electric Company, Quality Assurance Division, as a result of a finding in Combined Inspection Report 50-277/82-07 and 50-278/82-07.

In response to the item, the Design Input documents were revised to eliminate response time testing.

Since channel response time testing was

'not required by NUREG-0737, we believe this item does not constitute a failure to properly administer Plant Modification Procedure A-14.

ITEM 5 Philadelphia Electric Company realizes that a major revision is required to rectify problem areas in Administrative Procedure, A-14.

This revision has been initiated and will be completed by July 1, 1984.

Philadelphia Electric Company will increase the staff dedicated to modification control by the addition of clerical support and a j

gi^,/ 'g technical assistant.

These individuals will relieve the Assistant Modification Coordinator of those routine administrative functions which he now must perform himself, thereby allowing him to become more involved with each modification and the proper administration and control of plant modification procedures to preclude similar future occurrences.

ITEM 6 Philadelphia Electric Company has assigned an additional, well-qualified, technically competent individual to assist the Modification Coordinator.

The present Assistant Modification Coordinator is a degreed engineer and a qualified Shift Technical Advisor who has also worked in the Electrical Engineering Division in the Corporate offices.

These qualities were carefully considered prior to assigning the Assistant Modification Coordinator responsibilities to this individual.

Administrative Procedure A-14 states that all requirements of the procedure.may be performed by the Assistant Modification Coordinator except Part 1 of the Plant Modification Control Sheet (PMCS) and submission of the modification to the Plant Operations

2

-h-

-Mr. Thomas T. Martin-Pcgn.6 L

.~.

! Review; Committee'(PORC). :These exceptions are waived if'the individual. possesses a senior operator's license.

The Assistant Modification. coordinator does not possess a senior operator

-licenser however, the responsibility for the exceptions mentioned

,are:being assumed by the Modification Coordinator.

Therefore, we

believe that the Assistant Modification Coordinator need not possessTa senior operator's license.

TheiPeach> Bottom Final ~ Safety Analysis Report commits Philadelphia Electric Company to ANSI N45.2.11 (1973) titled

~" Quality Assurance Requirements _for the Design of Nuclear Power Plants".

We.believe'we meet'the intent of this standard.

Paragraph-TR2.2 of.the Peach Bottom Quality Assurance Plan, Volume:3, specifies that-training-of non-licensed professionals

is not: required if the-individual has the necessary qualifications tx) perform the task.

The qualifications of the

'present Assistant-Modification Coordinator, as. stated above, are isufficient to preclude specific training for this individual..

?The_ qualifications of the Assistant Modification Coordinator have been reviewed by_the Assistant Station Superintendent, and this

review has been documented in his training records.

ITEM 7 In the. letter'from S. L..Daltroff to B. H. Grier, dated April 28, 1980,.respondingzto the violation concerning MOD 510, the PMCS twas committed to be corrected to reflect-the need for procedural revision.

Certain procedural revisions were added to the Loriginal PMCS but not dated'nor otherwise documented in the modification package.

Our intent'in the April' 28,-1980, letter

. response was to. commit to revising of the PMCS form in the procedure, not to' prepare a new PMCS for this particular modification.

Additionally,-the letter stated that the-intent of the " Design Review" signature on the PMCS of A-14 is toidocument only design reviews for " minor modifications" generated on-site and that

~

Administrative Procedure A-14 would.be revised to reflect this.

A-14-was revised;and since MOD 510 was a " major modification" with the design review performed of f-site by the Engineering and

~

Research:-Department,~the " Design Review" signature was not

' required to be signed on the PMCS.

An Appendix, Modification Status Sheet for Document Revisions,

.has:been added to the Administrative Procedure A-14, Plant Modification, since MOD 510 was initiated.

This Appendix will be completed for.this~modificationfpackage to avoid any future confusion.

ls is.['

'f.

W Mr.s hhbaas T. Martin.

Page 7

-1 iThe cover letter.;for this combined inspection report

-statesrin part:

"we are concerned about continued weaknesses in the plant' modification area.

At the exit meeting, the 0

Assistant Station Superintendent informed the inspector that. management was. aware of these weaknesses and had initiated actions to'-strengthen the weaknesses.

In your response:to the-Notice of Violation, you are requested; to; include your-plans and schedules to strengthen-the

~

plant, modification activities."

Response

Wo.haveLreviewed_the findings-in this inspection report and recognize a need for additional. improvement in the administrative control of plant modifications.

Actions specifically intended to

-improve control of modifications will be made.in the following

-areas: (1) Organizational changes, (2) Increased staffing, (3)

^ Procedural revisions, and (4) Corporate.

'The first: area will be resolved by assigning the Assistant.

Modification Coordinator: to the staff of the plant Technical

-Engineer.- This will improve communication and coordination between the' Assistant Modification Coordinator and the test engineering; staff personnel-assigned to plant modifications.

The A'ssistant Modification. Coordinator will be assigned to the plant Technical Engineer by. April 6, 1984.

.-Additionally, Philadelphia Electric-Company is currently establishing Electric Production Department Requirements a d n

Guidelines.'These' documents are departmental policy-requirements regarding nuclear operations, including a guideline entitled icontrol'of Modifications.. The purpose of this document is to specify the requirements and guidelines for Electric Production Department responsibilities"and provides direction for

' interfacing with other departments for-control of modifications.

The-requirements and guidelines in this document will govern

~

controliof major, minor.and emergency modifications, both safety and non-safety related,~ from inception to completion.

This document is currently in.the' draft and approval ~ process.

It is expected'thatnit will'be approved for trial-use by June 1, 1984.

~

~ Philadelphia Electric Company will increase the staff dedicated to modification control by the addition of clerical support and a

-technical ~ assistant..These i'ndividuals will relieve.the Assistant Modification Coordinator of those routine

~

administrative functions which he now must perform himself,

w,,

E

~.' ;

Mr. Thomas T.? Martin

+-

Page 8

.thereby allowing him to become more involved with each modification and'the. proper administration and control of plant modification-procedures to preclude similar future occurrences as covered in this inspection report.

In the: third area and as stated in the response to Item 5,

. Philadelphia Electric Company has initiated a major revision to Administrative-Procedure A-14, Plant Modification.

The revision

-will. require a substantial rewrite of the existing _A-14 procedure and will concentrate on the following areas: improvement of communication between groups, improvement.in the delineating of responsibilities and reduction of paperwork.

In addition, a new Administrative Procedure will be: written for improved controlf of

. plant modification preoperational acceptance tests.

The revision to Procedure A-14 and generation of the new procedure regarding acceptance tests will be. completed by July 1, -1984.

Finally, a corporate' level committee will examine all aspects of

~

the modification process.

This ad hoc-committee.will examine the fprocesses internal to the involved departments and divisions as well as their interdependence and interactions.

We expect this committee toJcomplete its task by August 1, 1984.

It is expected that the findings _ of: this committee.will result in an enhancement -

i; over the current modification process.

Very truly yours, 4

i

- cc:.

A. R. Blough, Site Inspector

[-'

3

-